Promotion of Construction of the Chuo Shinkansen between Shinagawa and Nagoya

First written in FY2016. 35 of 39 entries say "Advanced", first in FY2017-Q1. Latest entry: 2026-07-31.

39entries
11years
4from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseAdvancedFY2017-Q1 – FY2020AdvancedFY2021-Q2 – FY2023-Q1AdvancedFY2024 – 2026-07-312016: 320162017: 420172018: 420182019: 420192020: 420202021: 420212022: 320222023: 320232024: 320242025: 220252026: 52026
Same theme, other companies
Promotion of Construction of the Chuo Shinkansen between Shinagawa and NagoyaA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. 2026-07-31AdvancedEarnings

    「南アルプストンネル山梨工区で本坑の品川方が貫通し、第一首都圏トンネル梶ヶ谷工区では都市部トンネルとして初めて非常口となる立坑間が繋がるなど、沿線各地で工事を進めました。」

    品川・名古屋間で本坑の貫通や立坑間の接続など、具体的な工事進展を開示した。
  2. FY2026AdvancedAnnual report

    「For the Shinagawa–Nagoya section, for which the construction implementation plan has been approved, land acquisition and other activities progressed, construction began on the Yamanashi Prefecture Station (provisional name), and work began on all stations between Shinagawa and Nagoya. Full-scale excavation also began in the Onoji section of the First Tokyo Metropolitan Area Tunnel and the Meijo section of the First Chukyo Metropolitan Area Tunnel, among other deep-underground sections excavated using shield machines. In the Tonaka, Mibusawa and Sakashima sections of the Ina Mountain Tunnel in Nagano Prefecture, the main tunnels in adjacent sections achieved a breakthrough for the first time excluding the Yamanashi Maglev Test Line, and construction progressed in areas along the line.」

    Progress included the start of construction on the Yamanashi Prefecture Station, work on all stations between Shinagawa and Nagoya, the start of full-scale excavation in deep-underground sections, and breakthroughs between the main tunnels in adjacent sections.
  3. FY2026-H1AdvancedAnnual report

    「For the Chuo Shinkansen superconducting maglev railway, land acquisition and other activities progressed in the Shinagawa–Nagoya section, for which the construction implementation plan has been approved, and construction contracts were signed for the Yamanashi Prefecture Station (provisional name). Full-scale excavation also began in the Sakashita-Nishi section of the First Chukyo Metropolitan Area Tunnel and the Kita-Shinagawa and Onoji sections of the First Tokyo Metropolitan Area Tunnel, where tunnels are being excavated deep underground using shield machines. In the Tonaka, Mibusawa and Sakashima sections of the Ina Mountain Tunnel in Nagano Prefecture, the main tunnels in adjacent sections achieved a breakthrough for the first time excluding the Yamanashi Maglev Test Line, and construction progressed in areas along the line.」

    Construction between Shinagawa and Nagoya progressed, including the signing of a construction contract for the Yamanashi Prefecture Station and other facilities, the start of full-scale excavation, and breakthroughs between the main tunnels in adjacent sections.
  4. FY2025AdvancedAnnual report

    「For the Shinagawa–Nagoya section, for which the construction implementation plan has been approved, land acquisition and other activities progressed, construction began on the Kanto Rolling Stock Depot (provisional name), and full-scale excavation began in the Kajigaya and Higashi-Yurigaoka sections of the First Tokyo Metropolitan Area Tunnel, where tunnels are being excavated deep underground using shield machines. Construction also progressed in areas along the line.」

    In addition to the start of construction on the Kanto Rolling Stock Depot, full-scale excavation began in the Kajigaya and Higashi-Yurigaoka sections of the First Tokyo Metropolitan Area Tunnel.
  5. FY2025-H1AdvancedAnnual report

    「For the Chuo Shinkansen superconducting maglev railway, land acquisition and other activities progressed in the Shinagawa–Nagoya section, for which the construction implementation plan has been approved. Full-scale excavation also began in the Kajigaya and Higashi-Yurigaoka sections of the First Tokyo Metropolitan Area Tunnel, where tunnels are being excavated deep underground using shield machines, and construction progressed in areas along the line.」

    Full-scale excavation began in the Kajigaya and Higashi-Yurigaoka sections of the First Tokyo Metropolitan Area Tunnel.
  6. FY2024AdvancedAnnual report

    「As for construction, exploratory excavation to verify safety initiatives in practice was completed in the Higashi-Yurigaoka section of the First Tokyo Metropolitan Area Tunnel, where the tunnel is being excavated deep underground using a shield machine. Construction of station structures also began at the Kanagawa Prefecture Station (provisional name), while the main tunnel of the First Minami-Koma Tunnel in Yamanashi Prefecture achieved a breakthrough for the first time excluding the Yamanashi Maglev Test Line, and work progressed energetically in areas along the line.」

    Specific construction progress included completion of exploratory excavation in the Higashi-Yurigaoka section, the start of station-structure construction at the Kanagawa Prefecture Station, and breakthrough of the main tunnel of the First Minami-Koma Tunnel.
  7. FY2024-Q3SoftenedAnnual report

    「Subsequently, in December 2023, the company applied for approval of the station and rolling stock depot building and equipment works, rolling stock and other items as Construction Implementation Plan (3). It also applied for changes to the construction budget, scheduled completion dates and other items already approved, based on design reviews, more detailed surveys, the progress of consultations and construction, and other factors, and received approval. With approval of Construction Implementation Plan (3), all items required for construction between Shinagawa and Nagoya were approved. 7. Scheduled completion date: fiscal 2027 and thereafter」

    While approval of Construction Implementation Plan (3) covered all required items for the Shinagawa–Nagoya section, the scheduled completion date changed from the previous “fiscal 2027” to “fiscal 2027 and thereafter,” softening the wording to allow for a delay.
  8. FY2024-Q2AdvancedAnnual report

    「Work progressed steadily in areas along the line, including completion of excavation within the exploratory excavation range in the Higashi-Yurigaoka section of the First Tokyo Metropolitan Area Tunnel, where the tunnel is being excavated deep underground using a shield machine to verify safety initiatives in practice.」

    Specific construction progress included completion of excavation within the exploratory excavation range in the Higashi-Yurigaoka section of the First Tokyo Metropolitan Area Tunnel.
  9. FY2023AdvancedAnnual report

    「For the Chuo Shinkansen superconducting maglev railway, land acquisition and other activities progressed in the Shinagawa–Nagoya section, for which the construction implementation plan has been approved. Full-scale work newly began at the Gifu Prefecture Station (provisional name), Nagano Prefecture Station (provisional name) and other facilities, while excavation of the main tunnel began in the Nagano section of the Minami-Alps Tunnel. In the Kajigaya and Higashi-Yurigaoka sections of the First Tokyo Metropolitan Area Tunnel, where tunnels are being excavated deep underground using shield machines, exploratory excavation began to verify safety initiatives in practice, and construction progressed steadily in areas along the line.」

    Full-scale work began at the Gifu Prefecture Station and Nagano Prefecture Station, while excavation of the main tunnel in the Nagano section of the Minami-Alps Tunnel and exploratory excavation in the Kajigaya and Higashi-Yurigaoka sections began.
  10. FY2023-Q3AdvancedAnnual report

    「Regarding the Chuo Shinkansen using superconducting magnetic levitation technology (hereinafter, the “superconducting maglev”), for the approved Shinagawa–Nagoya section, we proceeded with land acquisition and other activities. In terms of construction, we began full-scale construction at the newly designated Gifu Prefecture Station (provisional name), Nagano Prefecture Station (provisional name) and other locations, and began excavating the main tunnel at the Nagano section of the Minami-Alps Tunnel, making steady progress at locations along the route.」

    Full-scale work newly began at the Gifu Prefecture Station, Nagano Prefecture Station and other facilities, and excavation of the main tunnel began in the Nagano section of the Minami-Alps Tunnel.
  11. FY2023-Q2RestatedAnnual report

    「As for construction, full-scale work newly began at the Gifu Prefecture Station (provisional name) and other facilities, while excavation of the main tunnel began in the Nagano section of the Minami-Alps Tunnel, and work progressed steadily in areas along the line.」

    The construction progress was reconfirmed as being the same as in the previous quarter: the start of work at the Gifu Prefecture Station and the commencement of main-tunnel excavation in the Nagano section of the Minami-Alps Tunnel.
  12. FY2023-Q1AdvancedAnnual report

    「Regarding the Chuo Shinkansen using superconducting magnetic levitation technology (hereinafter, the “superconducting maglev”), for the approved Shinagawa–Nagoya section, we proceeded with land acquisition and other activities. In terms of construction, we began full-scale construction at the newly designated Gifu Prefecture Station (provisional name) and other locations, and began excavating the main tunnel at the Nagano section of the Minami-Alps Tunnel, making steady progress at locations along the route.」

    Construction between Shinagawa and Nagoya progressed, with full-scale work beginning at the Gifu Prefecture Station (provisional name) and other facilities, and main-tunnel excavation beginning in the Nagano section of the Minami-Alps Tunnel.
  13. FY2022-Q3AdvancedAnnual report

    「As for construction, full-scale work newly began at the Chubu General Rolling Stock Depot and other facilities. In the Kita-Shinagawa section of the First Tokyo Metropolitan Area Tunnel, where the tunnel is being excavated deep underground using a shield machine, exploratory excavation began to verify safety initiatives in practice. The main shafts of the Higashi-Yurigaoka and Kajigaya emergency exits in Kanagawa Prefecture, where construction was already under way, were completed. Work also progressed steadily in areas along the line, including the Aokigawa section of the Ina Mountain Tunnel in Nagano Prefecture and the Nishi and Higashi sections of the Fourth Minami-Koma Tunnel in Yamanashi Prefecture, where excavation of the main tunnels newly began.」

    Specific progress included the start of construction at the Chubu General Rolling Stock Depot and other facilities, exploratory excavation in the Kita-Shinagawa section, completion of the shafts at the Higashi-Yurigaoka and Kajigaya emergency exits, and commencement of main-tunnel excavation.
  14. FY2022-Q2AdvancedAnnual report

    「Of these projects, the main shaft of the Higashi-Yurigaoka emergency exit in Kanagawa Prefecture was completed, while in the Aokigawa section of the Ina Mountain Tunnel in Nagano Prefecture, excavation of the inclined shaft was completed and excavation of the main tunnel newly began.」

    Construction between Shinagawa and Nagoya progressed, including the signing of construction contracts for the Nagano Prefecture Station (provisional name) and other facilities, completion of the main shaft of the Higashi-Yurigaoka emergency exit, and completion of inclined-shaft excavation and commencement of main-tunnel excavation in the Aokigawa section of the Ina Mountain Tunnel.
  15. FY2022-Q1AdvancedAnnual report

    「For the Shinagawa–Nagoya section, for which the construction implementation plan has been approved, surveying, design and land acquisition progressed through close coordination with local communities, and construction contracts were signed for the Nagano Prefecture Station (provisional name) and other facilities.」

    New construction contracts were signed for the Nagano Prefecture Station (provisional name) and other facilities, while surveying, design, land acquisition and construction in each section progressed.
  16. FY2021AdvancedAnnual report

    「As for construction, full-scale work newly began on viaducts and other structures in Yamanashi Prefecture. In the Yamanashi section of the Minami-Alps Tunnel, where construction was already under way, excavation progressed on the inclined shaft, pilot tunnel and main tunnel, while in the Nagano section, excavation progressed on the inclined shaft and pilot tunnel. Construction girders and other structures were installed at Shinagawa and Nagoya stations, and work also progressed steadily on mountain tunnels, urban emergency exits and intermediate stations. Of these projects, the main shaft of the Sakashita emergency exit was completed, the first urban emergency exit in the Chukyo metropolitan area to be completed. In the Nishio section of the First Chukyo Metropolitan Area Tunnel in Aichi Prefecture, excavation of the inclined shaft was completed and excavation of the main tunnel began.」

    Specific construction progress included the start of viaduct construction in Yamanashi Prefecture, completion of the main shaft of the Sakashita emergency exit, and completion of inclined-shaft excavation and commencement of main-tunnel excavation in the Nishio section.
  17. FY2021-Q3AdvancedAnnual report

    「Of these projects, the main shaft of the Sakashita emergency exit was completed, the first urban emergency exit in the Chukyo metropolitan area to be completed.」

    For construction between Shinagawa and Nagoya, the main shaft of the Sakashita emergency exit was completed, the first urban emergency exit in the Chukyo metropolitan area to be completed.
  18. FY2021-Q2AdvancedAnnual report

    「As for construction, full-scale work newly began on viaducts and other structures in Yamanashi Prefecture. In the Yamanashi section of the Minami-Alps Tunnel, where construction was already under way, excavation progressed on the inclined shaft, pilot tunnel and main tunnel, while in the Nagano section, excavation progressed on the inclined shaft and pilot tunnel. Construction girders and other structures were installed at Shinagawa and Nagoya stations, and work also progressed steadily on mountain tunnels, urban emergency exits and intermediate stations.」

    While the Shizuoka section remained stalled, full-scale construction newly began on viaducts and other structures in Yamanashi Prefecture, and work progressed in the other sections.
  19. FY2021-Q1WorsenedAnnual report

    「Meanwhile, in the Shizuoka section of the Minami-Alps Tunnel, work has effectively remained at a standstill, as the company has been unable to secure the understanding of Shizuoka Prefecture and the municipalities in the Oi River basin regarding the impact on the river's water resources and has yet to begin developing the yards required before tunnel excavation.」

    While construction is proceeding in the other sections between Shinagawa and Nagoya, yard development has yet to begin in the Shizuoka section, and work has effectively remained at a standstill.
  20. FY2020AdvancedAnnual report

    「For construction, we newly began full-scale work at the Inukura emergency exit in Kanagawa Prefecture, the Nishio section of the Dai-ichi Chukyo Metropolitan Area Tunnel in Aichi Prefecture, and the Kanagawa Prefecture Station (provisional name), the first intermediate station of its kind. At the Yamanashi section of the Minami-Alps Tunnel, where construction had already begun, we advanced excavation of the access, advanced and main tunnels, and at the Nagano section we advanced excavation of the access and advanced tunnels. We also carried out construction girder and other work at Shinagawa and Nagoya stations, while steadily advancing construction at mountain tunnels and urban emergency exits. At the Kita-Shinagawa emergency exit, the main shaft was completed, the first such completion at an urban emergency exit, and the shield machine for tunnel excavation from the emergency exit was completed, with preparations under way for its delivery.」

    Full-scale construction began at the Kanagawa Prefecture Station, the Inukura emergency exit and the Nishio section of the Dai-ichi Chukyo Metropolitan Area Tunnel, while the main shaft and shield machine were completed at the Kita-Shinagawa emergency exit, marking progress on the Shinagawa–Nagoya section.
  21. FY2020-Q3AdvancedAnnual report

    「For construction, we newly began full-scale work at the Inukura emergency exit in Kanagawa Prefecture, the Nishio section of the Dai-ichi Chukyo Metropolitan Area Tunnel in Aichi Prefecture, and the Kanagawa Prefecture Station (provisional name), the first intermediate station of its kind. At the Yamanashi section of the Minami-Alps Tunnel, where construction had already begun, we advanced excavation of the access, advanced and main tunnels, and at the Nagano section we advanced excavation of the access and advanced tunnels. We also carried out construction girder and other work at Shinagawa and Nagoya stations, while steadily advancing construction at mountain tunnels and urban emergency exits. The main shaft of the Kita-Shinagawa emergency exit was completed, the first such completion at an urban emergency exit.」

    Full-scale construction began at the Kanagawa Prefecture Station (provisional name) and other locations, and the main shaft of the Kita-Shinagawa emergency exit was completed, the first such completion at an urban emergency exit, marking progress in construction.
  22. FY2020-Q2AdvancedAnnual report

    「Regarding the Chuo Shinkansen using superconducting magnetic levitation technology (hereinafter, the “superconducting maglev”), for the approved Shinagawa–Nagoya section, we advanced surveys, design and land acquisition while maintaining close cooperation with local communities, and signed construction contracts for the Nagoya Station Higashiyama Line section and the Kanagawa Prefecture Station (provisional name), the first intermediate station of its kind, among others.」

    The company signed new construction contracts for the Nagoya Station Higashiyama Line section, the Kanagawa Prefecture Station (provisional name) and other sections, and also began full-scale construction at the Inukura emergency exit and the Nishio section of the Dai-ichi Chukyo Metropolitan Area Tunnel.
  23. FY2020-Q1AdvancedAnnual report

    「Regarding the Chuo Shinkansen using superconducting magnetic levitation technology (hereinafter, the “superconducting maglev”), for the approved Shinagawa–Nagoya section, we advanced surveys, design and land acquisition while closely coordinating with the relevant local governments and communicating with local stakeholders. We also signed construction contracts for the Nagoya Station Higashiyama Line section and the Kanagawa Prefecture Station (provisional name), the first intermediate station of its kind, among others. For the Shizuoka section of the Minami-Alps Tunnel, we continued preparations for the start of future construction, including construction of accommodation facilities for construction workers and others. In terms of construction, we newly began full-scale construction at the Inukura emergency exit in Kanagawa Prefecture and the Nishio section of the Dai-ichi Chukyo Metropolitan Area Tunnel in Aichi Prefecture.」

    The company signed construction contracts for the Nagoya Station Higashiyama Line section, the Kanagawa Prefecture Station (provisional name) and other sections, and began full-scale construction at the Inukura emergency exit and the Nishio section of the Dai-ichi Chukyo Metropolitan Area Tunnel.
  24. FY2019AdvancedAnnual report

    「The outline of Construction Implementation Plan (2) for the Shinagawa–Nagoya section is as follows: 6. Construction cost: ¥4.8536 trillion (total construction cost: ¥5.5235 trillion, including rolling stock costs and excluding the existing Yamanashi Maglev Test Line section); 7. Scheduled completion year: 2027」

    For the Shinagawa–Nagoya section, the company advanced construction contracts for deep underground tunnels, the start of full-scale construction in multiple sections, and approval to use deep underground space, and stated total construction costs of ¥5.5235 trillion and a scheduled completion year of 2027.
  25. FY2019-Q3AdvancedAnnual report

    「For construction, we newly began full-scale work at the Higashiyukigaya emergency exit in Tokyo, the Todoroki emergency exit in Kanagawa Prefecture, and the Meijo substation in Aichi Prefecture. At the Yamanashi section of the Minami-Alps Tunnel, where construction had already begun, we advanced excavation of the access, advanced and main tunnels, and at the Nagano section we advanced excavation of the access tunnel. We also carried out diaphragm wall and construction girder work at Shinagawa and Nagoya stations, while steadily advancing construction at mountain tunnels and urban emergency exits. In addition, we received approval in October of the previous year to use deep underground space for the Shinagawa–Nagoya section of the Chuo Shinkansen.」

    The company began full-scale construction at the Higashiyukigaya and Todoroki emergency exits and the Meijo substation, and also received approval to use deep underground space, marking progress in the construction scope and approval procedures.
  26. FY2019-Q2AdvancedAnnual report

    「We signed construction contracts for the Kita-Shinagawa section of the Dai-ichi Tokyo Metropolitan Area Tunnel and the Sakashita-Nishi section of the Dai-ichi Chukyo Metropolitan Area Tunnel, among others, where tunnels will be excavated deep underground using the shield method.」

    The company signed new construction contracts for the Kita-Shinagawa section of the Dai-ichi Tokyo Metropolitan Area Tunnel, the Sakashita-Nishi section of the Dai-ichi Chukyo Metropolitan Area Tunnel and other sections, and began full-scale civil engineering work at the Higashiyukigaya and Todoroki emergency exits.
  27. FY2019-Q1AdvancedAnnual report

    「Regarding the Chuo Shinkansen using superconducting magnetic levitation technology (hereinafter, the “superconducting maglev”), for the approved Shinagawa–Nagoya section, we advanced surveys, design and land acquisition while maintaining close cooperation with local communities, and signed construction contracts for the Kita-Shinagawa section of the Dai-ichi Tokyo Metropolitan Area Tunnel and the Sakashita-Nishi section of the Dai-ichi Chukyo Metropolitan Area Tunnel, among others, where tunnels are excavated using the shield method deep underground. We also undertook preparations for the start of future construction, including signing a basic agreement with Shizuoka City on the construction of the Chuo Shinkansen (within the Shizuoka section of the Minami-Alps Tunnel) and regional development. In terms of construction, we began full-scale civil engineering work at the Higashiyukigaya emergency exit in Tokyo.」

    Construction contracts for the Kita-Shinagawa section of the Dai-ichi Tokyo Metropolitan Area Tunnel and other sections, the basic agreement with Shizuoka City, and the start of full-scale construction at the Higashiyukigaya emergency exit in Tokyo marked progress in both the construction scope and regional cooperation.
  28. FY2018AdvancedAnnual report

    「At the Yamanashi section of the Minami-Alps Tunnel, where construction had already begun, we began excavating the main tunnel in March following the access and advanced tunnels. We also excavated the access tunnel at the Nagano section and carried out diaphragm wall construction at Shinagawa Station (North and South sections), while steadily advancing construction at Nagoya Station, mountain tunnels and urban emergency exits. We further began full-scale civil engineering work at Shinagawa Station (the non-excavation section), the Sakashita emergency exit in Aichi Prefecture, and the Fourth Minami-Koma Tunnel in Yamanashi Prefecture. In September of the previous year, pursuant to Article 9 of the National Shinkansen Railway Development Act, we applied for approval of Construction Implementation Plan (2) for the Shinagawa–Nagoya section of the Chuo Shinkansen, focusing on electrical facilities, and received approval in March.」

    The company began excavating the main tunnel in the Yamanashi section of the Minami-Alps Tunnel and began full-scale construction at the Fourth Minami-Koma Tunnel and other locations. It also received approval for Construction Implementation Plan (2), focusing on electrical facilities.
  29. FY2018-Q3AdvancedAnnual report

    「Regarding the Chuo Shinkansen using the superconducting maglev, for the approved Shinagawa–Nagoya section, we advanced surveys, design and land acquisition while maintaining close cooperation with local communities, and signed construction contracts for the Shizuoka section of the Minami-Alps Tunnel and other sections. We also held construction briefings to explain the construction outline, safety measures and other matters to local residents in sections for which construction contracts had already been signed, and undertook preparations for the start of future construction.」

    The company signed new construction contracts for the Shizuoka section of the Minami-Alps Tunnel and other sections, and advanced preparations for the start of construction, including construction briefings and land acquisition.
  30. FY2018-Q2AdvancedAnnual report

    「At the Yamanashi section of the Minami-Alps Tunnel, where construction had already begun, we began excavating the advanced tunnel in July following excavation of the access tunnel. We also excavated the access tunnel at the Nagano section of the Minami-Alps Tunnel and carried out diaphragm wall construction at Shinagawa Station (North and South sections), while steadily advancing construction at Nagoya Station, mountain tunnels and urban emergency exits. We further began full-scale civil engineering work at Shinagawa Station (the non-excavation section) and the Sakashita emergency exit in Aichi Prefecture. In September, pursuant to Article 9 of the National Shinkansen Railway Development Act, we applied for approval of Construction Implementation Plan (2) for the Shinagawa–Nagoya section of the Chuo Shinkansen, focusing on electrical facilities.」

    The company began excavating the advanced tunnel in the Yamanashi section of the Minami-Alps Tunnel and applied for approval of Construction Implementation Plan (2).
  31. FY2018-Q1AdvancedAnnual report

    「Regarding the Chuo Shinkansen using the superconducting maglev, for the approved Shinagawa–Nagoya section, we advanced surveys, design and land acquisition while maintaining close cooperation with local communities. We also held construction briefings to explain the construction outline, safety measures and other matters to local residents in sections for which construction contracts had been signed, and undertook preparations for the start of future construction. In addition, we excavated pilot tunnels at the Minami-Alps Tunnel (Yamanashi and Nagano sections), where construction had already begun, and carried out diaphragm wall construction at Shinagawa Station (North and South sections), while steadily advancing construction at Nagoya Station, mountain tunnels and urban emergency exits. We also began full-scale civil engineering work at Shinagawa Station (the non-excavation section) and the Sakashita emergency exit in Aichi Prefecture.」

    In addition to surveys, design, land acquisition, construction briefings and work in sections where construction had already begun, the company began full-scale civil engineering work in the non-excavation section of Shinagawa Station and at the Sakashita emergency exit.
  32. FY2017AdvancedAnnual report

    「In addition, we began full-scale civil engineering work on the Minami-Alps Tunnel (Nagano section), the Hiyoshi Tunnel in Gifu Prefecture (Minamigaito section), Nagoya Station (Central East and Central West sections), and the construction of the Kajigaya emergency exit and materials access entrance in Kanagawa Prefecture, among other projects, all of which involve long construction periods and a high degree of difficulty.」

    The scope of full-scale civil engineering work expanded to the Nagano section of the Minami-Alps Tunnel, the Hiyoshi Tunnel, Nagoya Station, and the Kajigaya emergency exit, among others.
  33. FY2017-Q3AdvancedAnnual report

    「In addition, we began full-scale civil engineering work on the Minami-Alps Tunnel (Nagano section), the Hiyoshi Tunnel in Gifu Prefecture (Minamigaito section), and the construction of Nagoya Station (Central East and Central West sections), among other projects, all of which involve long construction periods and a high degree of difficulty.」

    Full-scale civil engineering work began in the Nagano section of the Minami-Alps Tunnel, the Minamigaito section of the Hiyoshi Tunnel, and the Central East and Central West sections of Nagoya Station, among others.
  34. FY2017-Q2AdvancedAnnual report

    「In addition to advancing construction of the difficult Minami-Alps Tunnel (Yamanashi section) and Shinagawa Station (North and South sections), both of which have long construction periods, we began full-scale civil engineering work for the construction of the Kita-Shinagawa emergency exit and the underground section of the substation facility.」

    The company advanced construction of the Minami-Alps Tunnel and Shinagawa Station and began full-scale civil engineering work for the Kita-Shinagawa emergency exit and substation facility.
  35. FY2017-Q1AdvancedAnnual report

    「For Construction Implementation Plan (1) for the Shinagawa–Nagoya section, we conducted centerline surveys to establish the route centerline and explained land requirements to landowners and others. We also signed construction contracts for Shinagawa Station (the non-excavation section), urban emergency exits and other facilities (2 locations), and mountain tunnels (1 location).」

    Specific construction progress included centerline surveys, explanations regarding land acquisition, and construction contracts for Shinagawa Station, emergency exits and a mountain tunnel.
  36. FY2016First statedAnnual report

    「Total construction costs for the Shinagawa–Nagoya section are ¥5.5235 trillion, comprising the ¥4.0158 trillion construction cost in Construction Implementation Plan (1) plus the estimated cost of opening-related facilities scheduled for approval under Construction Implementation Plan (2), excluding the existing Yamanashi Maglev Test Line section.」

    Following approval of the construction plan, explanations regarding land acquisition, construction contracts, and safety prayer and groundbreaking ceremonies, the company began full-scale civil engineering work. The scheduled completion year was stated as 2027.
Moved together

"Expansion of Demand-Responsive Transportation Services and Sales Initiatives" moved the same way as this thread, in the same document, in 25 of its 39 moves.

252317161613★123456
  1. ★This thread
  2. 1Expansion of Demand-Responsive Transportation Services and Sales Initiatives25×
  3. 2Improving Railway Safety Through Security and Station Facilities23×
  4. 3Strengthening Existing Distribution, Real Estate, Hotel and Other Businesses17×
  5. 4Strengthening Railway Facilities and Transportation in Preparation for Natural Disasters16×
  6. 5Commercialization, Advancement and Cost Reduction of Superconducting Maglev Technology16×
  7. 6Response to the Expert Panel on the Shizuoka Section Issue13×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next