Response to the Expert Panel on the Shizuoka Section Issue
First written in FY2020. 16 of 20 entries say "Advanced", first in FY2022-Q1. Latest entry: 2026-07-31.
No other company in this theme has enough history to compare yet.
- 2026-07-31RestatedEarnings
「引き続き、静岡工区のトンネル掘削工事の早期着手に向けて、地域の皆様に理解を深めていただけるよう、双方向のコミュニケーションを大切にしながら、真摯に取り組みます。」
地域との双方向のコミュニケーションを重視し、静岡工区の早期着手を目指す取組みを継続している。 - FY2026AdvancedAnnual report
「Of the matters identified by Shizuoka Prefecture as requiring dialogue, discussions on all water-resource-related items were completed in June. In addition, we held an exchange of views with the mayors of the 8 cities and 2 towns in the Oi River basin in July.」
The company completed discussions on all water-resource-related items and held an exchange of views with the mayors of the 8 cities and 2 towns in the basin. In addition, following the signing of a confirmation document and an agreement on nature conservation with Shizuoka Prefecture, it began preparatory construction, including the development of yard sites. - FY2026-H1AdvancedAnnual report
「Of the matters identified by Shizuoka Prefecture as requiring dialogue, discussions on all water-resource-related items were completed in June. In addition, we held an exchange of views with the mayors of the 8 cities and 2 towns in the Oi River basin in July.」
The company completed discussions on all water-resource-related items and progressed to the stage of holding an exchange of views with the mayors of the 8 cities and 2 towns in the Oi River basin. - FY2025AdvancedAnnual report
「In addition, we held an exchange of views with the mayors of the 8 cities and 2 towns in the Oi River basin last November and began briefing sessions on initiatives to protect the Oi River’s water in March. We will continue to work sincerely toward the early start of tunnel excavation in the Shizuoka Section, emphasizing two-way communication to gain the understanding and cooperation of local communities.」
The company held an exchange of views with the mayors of the 8 cities and 2 towns in the basin and local briefing sessions, and advanced efforts toward an early start of construction on the Shizuoka Section through two-way dialogue. - FY2025-H1AdvancedAnnual report
「In addition, the president met with the newly inaugurated governor of Shizuoka Prefecture in June. We will continue to work sincerely toward the early start of tunnel excavation in the Shizuoka Section, emphasizing two-way communication to gain the understanding and cooperation of local communities.」
The president met with the newly inaugurated governor of Shizuoka Prefecture in June, and the company continues efforts toward an early start of construction, emphasizing two-way dialogue. - FY2024AdvancedAnnual report
「Subsequently, in February, the Ministry of Land, Infrastructure, Transport and Tourism established the “Monitoring Committee for the Shizuoka Section of the Chuo Shinkansen Maglev Line” to continuously monitor the status of measures identified in the expert panel’s reports on water resources and environmental conservation from scientific and objective perspectives. At the second meeting, held in March, we presented the construction plan for the Shizuoka Section and explained that, as 6 years and 4 months had already passed since the construction contract was signed, the Shizuoka Section was directly linked to the delay in the opening of the Shinagawa–Nagoya section and opening in 2027 could not be achieved.」
A monitoring committee was established to verify measures for water resources and environmental conservation, and at its second meeting the company presented the construction plan and explained that opening in 2027 could not be achieved. - FY2024-Q3AdvancedAnnual report
「As part of these measures, in December 2023 we signed a basic agreement with power generation operators on a plan to limit water withdrawals for power generation and return the water to the Oi River. Discussions on environmental conservation in the Southern Alps continued at the expert panel, which finalized the “Report on the Shizuoka Section of the Chuo Shinkansen Maglev Line (2023 Report) — Examination of Environmental Conservation” in December 2023.」
The company signed a basic agreement with power generation operators on measures to return water to the Oi River and progressed to the finalization of the expert panel’s report on environmental conservation in the Southern Alps. - FY2024-Q2AdvancedAnnual report
「As part of these measures, we have continued discussions with power generation operators since June on a plan to limit water withdrawals for power generation and return the water to the Oi River. Discussions on environmental conservation in the Southern Alps have also continued at the expert panel. In addition, we held an exchange of views with the mayors of municipalities in the Oi River basin in September.」
The company continued discussions with power generation operators on measures to return water to the Oi River, and held discussions on environmental conservation in the Southern Alps and an exchange of views with the mayors of municipalities in the basin. - FY2024-Q1AdvancedAnnual report
「As part of these measures, in June we began discussions with power generation operators on a plan to limit water withdrawals for power generation and return the water to the Oi River.」
Regarding measures to address the Oi River’s water resources, the company began discussions with power generation operators in June on a plan to limit water withdrawals for power generation and return the water to the Oi River. - FY2023-Q3AdvancedAnnual report
「Regarding the impact on the Oi River’s water resources, based on the “Interim Report on the Oi River Water Resources Issue” finalized in December two years ago by the Ministry of Land, Infrastructure, Transport and Tourism’s “Expert Panel on the Shizuoka Section of the Chuo Shinkansen Maglev Line,” we have been considering measures to return to the Oi River, for a certain period during construction, an amount of tunnel spring water equal to the amount exceptionally flowing outside Shizuoka Prefecture, and have been explaining them to Shizuoka Prefecture and other parties since April last year. In addition, since July last year we have accepted opinions and questions to help guide future initiatives concerning the Oi River’s water resources and explanations to local communities, responding individually and publishing the main opinions, questions and answers last October.」
The company continued explaining measures to return an amount equal to the spring water volume to the Oi River, responded to opinions and questions from local communities, and progressed to publishing the main responses. - FY2023-Q2AdvancedAnnual report
「Regarding the impact on the Oi River’s water resources, based on the “Interim Report on the Oi River Water Resources Issue” finalized last December by the Ministry of Land, Infrastructure, Transport and Tourism’s “Expert Panel on the Shizuoka Section of the Chuo Shinkansen Maglev Line,” we are considering measures to return to the Oi River, for a certain period during construction, an amount of tunnel spring water equal to the amount exceptionally flowing outside Shizuoka Prefecture, and have been explaining them to Shizuoka Prefecture and other parties since April. In addition, in July we began accepting opinions and questions to help guide future initiatives concerning the Oi River’s water resources and explanations to local communities.」
The company explained to Shizuoka Prefecture and other parties its measures to return an amount equal to the spring water volume based on the interim report, and began accepting opinions and questions from local communities in July. - FY2023-Q1AdvancedAnnual report
「Regarding the impact on the Oi River’s water resources, based on the “Interim Report on the Oi River Water Resources Issue” finalized last December by the Ministry of Land, Infrastructure, Transport and Tourism’s “Expert Panel on the Shizuoka Section of the Chuo Shinkansen Maglev Line,” we considered measures to return to the Oi River, for a certain period during construction, an amount of tunnel spring water equal to the amount exceptionally flowing outside Shizuoka Prefecture, and explained them to Shizuoka Prefecture in April. Discussions on environmental conservation, including the ecosystem of the Southern Alps, also began at the expert panel in June. We will continue to respond sincerely to gain the understanding and cooperation of local communities.」
Based on the interim report, the company considered measures to return to the Oi River an amount equal to the spring water flowing outside the prefecture and explained them to Shizuoka Prefecture; discussions on environmental conservation, including ecosystems, also began. - FY2022-Q3AdvancedAnnual report
「Against this backdrop, the Ministry of Land, Infrastructure, Transport and Tourism established the “Expert Panel on the Shizuoka Section of the Chuo Shinkansen Maglev Line” in April two years ago to seek a solution through scientific and engineering discussions, and the “Interim Report on the Oi River Water Resources Issue” was finalized in December last year. We also held an exchange of views with the mayors of municipalities in the Oi River basin last September. Based on the expert panel’s interim report, we will respond sincerely to gain the understanding and cooperation of local communities.」
The expert panel finalized the “Interim Report on the Oi River Water Resources Issue,” moving the company to the next stage of gaining local understanding based on the report. - FY2022-Q2AdvancedAnnual report
「At the 12th meeting held in September this year, the panel discussed the “Draft Interim Report on the Oi River Water Resources Issue” and indicated its policy of finalizing it at the next meeting. We also held an exchange of views with the mayors of the municipalities in the Oi River basin during the same month.」
The expert panel reached its 12th meeting and indicated its policy of finalizing the draft interim report at the next meeting; an exchange of views was also held with the mayors of municipalities in the basin. - FY2022-Q1AdvancedAnnual report
「At the 11th meeting held in April this year, the panel discussed the “Draft Interim Report on the Oi River Water Resources Issue.” We will continue working to alleviate the concerns of people in the Oi River basin by responding sincerely to the panel and through other measures.」
The expert panel reached its 11th meeting, where the “Draft Interim Report on the Oi River Water Resources Issue” was discussed. - FY2021-Q3RestatedAnnual report
「We will continue to respond sincerely to the panel, work to alleviate local concerns and achieve an early solution, and pursue the early start of construction on the Shizuoka Section and the early opening of the Shinagawa–Nagoya section.」
The company continues its efforts to alleviate local concerns, achieve an early start of construction on the Shizuoka Section and open the Shinagawa–Nagoya section at an early date through its response to the expert panel. - FY2021-Q2RestatedAnnual report
「We will continue to respond sincerely to the panel, work to alleviate local concerns and achieve an early solution, and pursue the early start of construction on the Shizuoka Section and the early opening of the Shinagawa–Nagoya section.」
The company continues its efforts to alleviate local concerns and achieve an early start of construction on the Shizuoka Section through its response to the expert panel. - FY2020First statedAnnual report
「Against this backdrop, in April 2020, the Ministry of Land, Infrastructure, Transport and Tourism established the “Expert Panel on the Shizuoka Section of the Chuo Shinkansen Maglev Line” to seek a solution to this issue through scientific and engineering discussions. We are making efforts to resolve local concerns and achieve an early solution by responding sincerely to the panel.」
The company first described its efforts to address the water issue in the Shizuoka Section by responding to the Ministry of Land, Infrastructure, Transport and Tourism’s expert panel and seeking to alleviate local concerns and achieve an early solution.