Reorganization of Assets through the Redevelopment of the Nagaokakyo Tose Building and Transfer of Land
First written in FY2025-H1. 11 of 12 entries say "Advanced", first in 2026-04-09. Latest entry: 2026-10-26.
No other company in this theme has enough history to compare yet.
- FY2026-H1AdvancedAnnual report
「Transfer of the land and buildings of the Nishioji Development Center and start of leaseback March 2027 Completion of the new office building Around October 2027 Relocation of Nishioji Development Center staff to the new Nagaokakyo office building Around January 2028」
In connection with construction of the new Nagaokakyo office building, the company detailed the schedule for the sale and leaseback of the Nishioji Development Center and the relocation of employees. The gain on the transfer of the Nishioji Development Center is estimated at ¥745 million, and the sale proceeds are scheduled to be used to fund construction of the new office building. - 2026-04-09AdvancedEarnings
「We are proceeding with the construction of a new office building in Nagaokakyo, Kyoto Prefecture, which is intended to serve as a key development center.」
While proceeding with construction of the new Nagaokakyo office building, the company has firmed up a plan to transfer the land and buildings of the Nishioji Development Center in March 2027 and use the proceeds to fund construction of the new office building. - FY2025-H1First statedAnnual report
「As the Nagaokakyo Tose Building and the adjacent Nagaoka Terminal Building, both owned by the company in Nagaokakyo, Kyoto Prefecture, have deteriorated with age, the company plans to demolish the 2 buildings and construct 1 new building. Accordingly, after demolishing the Nagaokakyo Tose Building and Nagaoka Terminal Building, the company will transfer the land other than the site planned for construction of the new building.」
The company disclosed an asset restructuring plan to demolish the 2 aging buildings, construct 1 new building and transfer the land other than the planned construction site. Handover of the land is scheduled for August 2026, and the overall transaction is expected to generate a gain of ¥475 million.