Komori
Fp (7947) · InitiativeAdvanced

Consideration of a New Production and Logistics Facility in Bando, Ibaraki Prefecture

First written in FY2022. 6 of 9 entries say "Advanced", first in FY2023-Q1. Latest entry: 2026-07-31.

9entries
5years
3from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseAdvancedFY2023-Q1 – FY20252022: 320222023: 020232024: 020242025: 220252026: 42026
Same theme, other companies
Plan to build a new production and logistics site in Bando, Ibaraki PrefectureA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. 2026-07-31AdvancedEarnings

    「To establish a full-scale mass-production system, the Company has begun construction of the Bando Plant (provisional name) in Bando City, Ibaraki Prefecture.」

    The Company reported progress following the start of construction of the Bando Plant and distribution center, including ¥10.061 billion spent during the quarter on construction work, production equipment and other items.
  2. FY2026AdvancedAnnual report

    「Construction of the new Bando Plant and Distribution Center (tentative name) ¥4,739 million」

    For the new hub in Bando, the company decided to construct the Bando Plant and Distribution Center and invested ¥4,739 million during the fiscal year. The capital investment plan calls for total investment of ¥58.0 billion, completion in September 2028, production of new OPP sheets and other products, and an increase of 280,000 cases in food container storage capacity.
  3. FY2026-H1SoftenedAnnual report

    「We ordered new OPP sheet production equipment in November 2024 and are considering constructing a new plant in Bando, Ibaraki Prefecture, with the aim of commencing operations in 2028.」

    For the new OPP sheet plant in Bando, the project has progressed to the ordering of production equipment, while the target for commencing operations has been updated from the previous target of the second half of 2027 to 2028.
  4. FY2025AdvancedAnnual report

    「For the ultra-high-rigidity biaxially oriented polypropylene sheet announced as successfully developed in April 2024 (hereinafter, the “new OPP sheet”) and the new OPP laminated plate, we ordered new OPP sheet production equipment in November of the same year. We are considering constructing a new plant in Bando, Ibaraki Prefecture, with the aim of commencing operations in the second half of 2027.」

    The new production hub plan in Bando has taken concrete shape, progressing from the acquisition of land and consideration of a production plant and distribution center to the order of new OPP sheet production equipment and consideration of a new plant targeted to begin operations in the second half of 2027.
  5. FY2023-Q2AdvancedAnnual report

    「In addition, we acquired new land at the Bando Inter Industrial Park in Ibaraki Prefecture in July 2022 (site area: 51,819.61 m²) and plan to construct a production plant and distribution center to secure production and storage capacity capable of providing a stable long-term supply to the Tokyo metropolitan area.」

    The land acquisition in Bando planned for the previous fiscal year was completed in July 2022, and the plan to construct a production plant and distribution center took concrete shape.
  6. FY2023-Q1AdvancedAnnual report

    「In addition, we acquired new land at the Bando Inter Industrial Park in Ibaraki Prefecture in July 2022 (site area: 51,819.61 m²) and plan to construct a production plant and distribution center to secure production and storage capacity capable of providing a stable long-term supply to the Tokyo metropolitan area.」

    The land acquisition in Bando planned for the previous fiscal year was completed in July 2022, advancing the plan to construct a 51,819.61 m² production and logistics hub.
  7. FY2022First statedAnnual report

    「In addition, we plan to acquire new land in Bando, Ibaraki Prefecture, in July 2022 (sale and purchase agreement concluded in April 2022; site area: 51,810 m²), and are considering constructing a production plant and distribution center to secure production and storage capacity capable of providing a stable long-term supply to the Tokyo metropolitan area.」

    The company announced a new hub development plan involving the planned acquisition of a 51,810 m² site in Bando, Ibaraki Prefecture, and consideration of constructing a production plant and distribution center serving the Tokyo metropolitan area.
Moved together

"Completion of the Nationwide Logistics Network and Stable Supply" moved the same way as this thread, in the same document, in 6 of its 9 moves.

644333★123456
  1. ★This thread
  2. 1Completion of the Nationwide Logistics Network and Stable Supply6×
  3. 2Promoting Tray-to-Tray and Bottle-to-Tray Recycling4×
  4. 3Accelerating the Development of High-Value-Added, Original Products4×
  5. 4Growth and Environmental Investment Using Retained Earnings3×
  6. 5Strengthening the Supply Chain and Optimizing Total Costs3×
  7. 6R&D and Talent Development Using the General Research Institute3×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Fp's next results are scheduled for 2026-10-30. Read the earnings preview It last moved in the Earnings of 2026-07-31: "Advanced".
Consideration of a New Production and Logistics Facility in Bando, Ibaraki Prefecture | FP CORPORATION (7947) | Komori