Plan for Accumulation and Drawdown of the Provision for Major Shinkansen Railway Repairs
First written in FY2017-Q1. 28 of 29 entries say "Advanced", first in FY2017-Q2. Latest entry: FY2026-H1.
1 other company's latest entry also says "Advanced".
- FY2026-H1AdvancedAnnual report
「Change in provision for large-scale Shinkansen railway renovations (△ indicates a decrease) 12,000 12,000」
Based on the long-term accumulation plan, a further ¥12 billion was added to the provision during the current interim consolidated accounting period, and the provision balance increased from ¥216 billion at the end of the previous fiscal year to ¥228 billion. - FY2025-H1AdvancedAnnual report
「Change in provision for large-scale Shinkansen railway renovations (△ indicates a decrease) 12,000 12,000」
Based on the long-term accumulation plan, a further ¥12 billion was added to the provision during the current interim consolidated accounting period, and the provision balance increased from ¥192 billion at the end of the previous fiscal year to ¥204 billion. - FY2024AdvancedAnnual report
「The provision for large-scale Shinkansen railway renovations increased from ¥168,000 million at the end of the previous consolidated fiscal year to ¥192,000 million at the end of the current consolidated fiscal year.」
Based on the plan to accumulate ¥24 billion in each fiscal year from fiscal 2016 through fiscal 2030, the provision balance reached ¥192 billion. - FY2024-Q1AdvancedAnnual report
「Provision for large-scale Shinkansen railway renovations 168,000 174,000」
Based on the long-term accumulation plan, the balance of the provision for large-scale Shinkansen railway renovations increased from ¥168 billion to ¥174 billion. - FY2023AdvancedAnnual report
「The provision for large-scale Shinkansen railway renovations increased from ¥144,000 million at the end of the previous consolidated fiscal year to ¥168,000 million at the end of the current consolidated fiscal year.」
Based on the plan to accumulate ¥24 billion in each fiscal year from fiscal 2016 through fiscal 2030, the provision balance increased from ¥144 billion to ¥168 billion. - FY2023-Q2AdvancedAnnual report
「Provision for large-scale Shinkansen railway renovations 144,000 156,000」
The provision for large-scale Shinkansen railway renovations increased from ¥144 billion at the end of the previous fiscal year to ¥156 billion at the end of the second quarter, indicating progress in implementing the long-term accumulation plan. - FY2023-Q1AdvancedAnnual report
「The provision for large-scale Shinkansen railway renovations increased from ¥144,000 million at the end of the previous consolidated fiscal year to ¥150,000 million at the end of the first quarter of the current consolidated fiscal year.」
Based on the long-term accumulation plan, the balance of the provision for large-scale Shinkansen railway renovations increased from ¥144 billion to ¥150 billion. - FY2022AdvancedAnnual report
「The provision for large-scale Shinkansen railway renovations increased from ¥120,000 million at the end of the previous consolidated fiscal year to ¥144,000 million at the end of the current consolidated fiscal year.」
Based on the approved plan to accumulate ¥24,000 million in each fiscal year from fiscal 2016 through fiscal 2030, the provision balance reached ¥144 billion. - FY2022-Q3AdvancedAnnual report
「Provision for large-scale Shinkansen railway renovations 120,000 138,000」
Based on the long-term accumulation plan, the balance of the provision for large-scale Shinkansen railway renovations increased from ¥120 billion at the end of the previous fiscal year to ¥138 billion at the end of the third quarter. - FY2022-Q1AdvancedAnnual report
「The provision for large-scale Shinkansen railway renovations increased from ¥120,000 million at the end of the previous consolidated fiscal year to ¥126,000 million at the end of the first quarter of the current consolidated fiscal year.」
Based on the long-term accumulation plan, the balance of the provision for large-scale Shinkansen railway renovations increased from ¥120 billion to ¥126 billion. - FY2021AdvancedAnnual report
「Regarding accumulation in the provision for large-scale Shinkansen railway renovations, ¥24,000 million (¥360,000 million in total) will be accumulated in each fiscal year from fiscal 2016 through fiscal 2030, and ¥36,000 million (¥360,000 million in total) will be reversed from the provision in each fiscal year from fiscal 2031 through fiscal 2040.」
Based on the long-term accumulation plan, a further ¥24 billion was accumulated during the current fiscal year, bringing the provision balance to ¥120 billion. - FY2021-Q2AdvancedAnnual report
「The provision for large-scale Shinkansen railway renovations increased from ¥96,000 million at the end of the previous consolidated fiscal year to ¥108,000 million at the end of the second quarter of the current consolidated fiscal year.」
Based on the approved long-term accumulation plan, the provision balance increased from ¥102 billion at the end of the previous quarter to ¥108 billion. - FY2021-Q1AdvancedAnnual report
「The provision for large-scale Shinkansen railway renovations increased from ¥96,000 million at the end of the previous consolidated fiscal year to ¥102,000 million at the end of the first quarter of the current consolidated fiscal year.」
Based on the approved long-term accumulation plan, the provision balance increased from ¥96 billion to ¥102 billion. - FY2020AdvancedAnnual report
「Regarding accumulation in the provision for large-scale Shinkansen railway renovations, ¥24,000 million (¥360,000 million in total) will be accumulated in each fiscal year from fiscal 2016 through fiscal 2030, and ¥36,000 million (¥360,000 million in total) will be reversed from the provision in each fiscal year from fiscal 2031 through fiscal 2040.」
Based on the approved long-term accumulation plan, a further ¥24 billion was accumulated during the current fiscal year, bringing the balance at the end of the fiscal year to ¥96 billion. - FY2020-Q3AdvancedAnnual report
「Provision for large-scale Shinkansen railway renovations 72,000 90,000」
The provision for large-scale Shinkansen railway renovations increased from ¥72 billion at the end of the previous fiscal year to ¥90 billion at the end of the third quarter, indicating progress in implementing the approved long-term accumulation plan. - FY2020-Q2AdvancedAnnual report
「Change in provision for large-scale Shinkansen railway renovations (△ indicates a decrease) 12,000 12,000」
Based on the approved long-term accumulation plan, a further ¥12 billion was added to the provision during the cumulative period of the second quarter, and the provision balance increased from ¥72 billion at the end of the previous fiscal year to ¥84 billion. - FY2020-Q1AdvancedAnnual report
「Provision for large-scale Shinkansen railway renovations 72,000 78,000」
The provision for large-scale Shinkansen railway renovations increased from ¥72 billion at the end of the previous fiscal year to ¥78 billion at the end of the first quarter. - FY2019AdvancedAnnual report
「Accordingly, ¥24,000 million (¥360,000 million in total) will be accumulated in the provision in each fiscal year from fiscal 2016 through fiscal 2030, and ¥36,000 million (¥360,000 million in total) will be reversed from the provision in each fiscal year from fiscal 2031 through fiscal 2040.」
Based on the approved long-term accumulation plan, a further ¥24 billion was accumulated during the current fiscal year, bringing the provision balance to ¥72 billion. - FY2019-Q3AdvancedAnnual report
「Provision for large-scale Shinkansen railway renovations 48,000 66,000」
The provision for large-scale Shinkansen railway renovations increased from ¥48 billion at the end of the previous fiscal year to ¥66 billion at the end of the third quarter, indicating progress in implementing the long-term accumulation plan. - FY2019-Q2AdvancedAnnual report
「Change in provision for large-scale Shinkansen railway renovations (△ indicates a decrease) 12,000 12,000」
Based on the approved long-term accumulation plan, a further ¥12 billion was added to the provision during the cumulative period of the second quarter, bringing the balance to ¥60 billion. - FY2019-Q1AdvancedAnnual report
「Provision for large-scale Shinkansen railway renovations 48,000 54,000」
The provision for large-scale Shinkansen railway renovations increased from ¥48 billion at the end of the previous fiscal year to ¥54 billion at the end of the first quarter, indicating progress in implementing the long-term accumulation plan. - FY2018AdvancedAnnual report
「Regarding accumulation in the provision for large-scale Shinkansen railway renovations, ¥24,000 million (¥360,000 million in total) will be accumulated in each fiscal year from fiscal 2016 through fiscal 2030, and ¥36,000 million (¥360,000 million in total) will be reversed from the provision in each fiscal year from fiscal 2031 through fiscal 2040.」
Based on the approved accumulation plan, a further ¥24 billion was added to the provision during the current fiscal year, bringing the balance at the end of the fiscal year to ¥48 billion. - FY2018-Q3AdvancedAnnual report
「Provision for large-scale Shinkansen railway renovations 24,000 42,000」
The provision for large-scale Shinkansen railway renovations increased from ¥24 billion at the end of the previous consolidated fiscal year to ¥42 billion at the end of the third quarter, indicating progress in implementing the long-term accumulation plan. - FY2018-Q2AdvancedAnnual report
「Change in provision for large-scale Shinkansen railway renovations (△ indicates a decrease) 12,000 12,000」
Based on the approved long-term accumulation plan, a further ¥12 billion was added to the provision during the cumulative period of the second quarter, bringing the provision balance to ¥36 billion. - FY2018-Q1AdvancedAnnual report
「Provision for large-scale Shinkansen railway renovations 24,000 30,000」
The provision for large-scale Shinkansen railway renovations increased from ¥24 billion at the end of the previous consolidated fiscal year to ¥30 billion at the end of the first quarter, indicating progress in implementing the approved long-term accumulation plan. - FY2017AdvancedAnnual report
「For each fiscal year from fiscal 2016 through fiscal 2030, ¥24,000 million (¥360,000 million in total) will be accumulated in the provision, and for each fiscal year from fiscal 2031 through fiscal 2040, ¥36,000 million (¥360,000 million in total) will be reversed from the provision.」
The first-year provision of ¥24,000 million was recognized under the approved plan, confirming the implementation of the long-term accumulation plan. - FY2017-Q3AdvancedAnnual report
「Under this plan, ¥24,000 million will be added to the provision in each fiscal year from fiscal 2016 through fiscal 2030, for a total of ¥360,000 million, and ¥36,000 million will be drawn down in each fiscal year from fiscal 2031 through fiscal 2040, also for a total of ¥360,000 million.」
Based on the long-term accumulation plan, the provision for large-scale Shinkansen railway renovations on the quarterly consolidated balance sheet amounted to ¥18,000 million. - FY2017-Q2AdvancedAnnual report
「Change in provision for large-scale Shinkansen railway renovations (△ indicates a decrease) ¥12,000 million」
Based on the approved long-term accumulation plan, a provision of ¥12,000 million was recognized during the cumulative period of the current quarter, and the plan proceeded to the implementation stage. - FY2017-Q1First statedAnnual report
「Under this plan, ¥24,000 million will be added to the provision in each fiscal year from fiscal 2016 through fiscal 2030, for a total of ¥360,000 million, and ¥36,000 million will be drawn down in each fiscal year from fiscal 2031 through fiscal 2040, also for a total of ¥360,000 million.」
The company has set out a long-term schedule for building up and drawing down provisions for large-scale Shinkansen renovations, based on a plan approved by the government.