Construction of the New Fukushima Station Approach Line
First written in FY2022-Q1. 3 of 6 entries say "Advanced", first in FY2022. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026AdvancedAnnual report
「Construction of a new approach line at Fukushima Station 11,793 7,887 Internal funds August 2018 FY2026」
The amount paid to date for the new approach line at Fukushima Station increased from ¥1,531 million to ¥7,887 million, while the scheduled completion in FY2026 was maintained. - FY2023AdvancedAnnual report
「Construction of a new approach line at Fukushima Station 11,793 1,531 Internal funds August 2018 FY2026」
The amount paid to date for the new approach line at Fukushima Station increased from ¥630 million to ¥1,531 million, while the scheduled completion in FY2026 was maintained. - FY2022AdvancedAnnual report
「Construction of a new approach line at Fukushima Station 11,793 630 Internal funds August 2018 FY2026」
The planned total cost of the new approach line at Fukushima Station remains ¥11,793 million, with completion scheduled for FY2026, and ¥630 million paid to date was disclosed. - FY2022-Q3RestatedAnnual report
「Construction of a new approach line at Fukushima Station 11,793 FY2026」
The plan for the new approach line at Fukushima Station, with a total construction cost of ¥11,793 million and completion scheduled for the end of FY2026, remains in place. - FY2022-Q2RestatedAnnual report
「During the second quarter of the current consolidated cumulative period, construction began on the new approach line at Fukushima Station, part of measures to improve transportation services. The planned total cost of this project is ¥11,793 million, and completion is scheduled for the end of FY2026.」
The plan for the new approach line at Fukushima Station, with a planned total cost of ¥11,793 million and completion scheduled for the end of FY2026, remains in place. - FY2022-Q1First statedAnnual report
「During the first quarter of the current consolidated cumulative period, construction began on the new approach line at Fukushima Station, part of measures to improve transportation services. The planned total cost of this project is ¥11,793 million, and completion is scheduled for the end of FY2026.」
Construction began on the new approach line at Fukushima Station, with a planned total cost of ¥11,793 million and completion scheduled for the end of FY2026.