Speed Increase on the Tohoku Shinkansen between Morioka and Shin-Aomori
First written in FY2021-Q2. 4 of 5 entries say "Advanced", first in FY2021. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026AdvancedAnnual report
「Ground facilities work to increase speeds on the Tohoku Shinkansen between Morioka and Shin-Aomori 11,602 10,718 Internal funds September 2017 FY2027」
The amount paid to date for the Tohoku Shinkansen speed-increase work increased from ¥1,017 million to ¥10,718 million, while the scheduled completion in FY2027 was maintained. - FY2023AdvancedAnnual report
「Ground facilities work to increase speeds on the Tohoku Shinkansen between Morioka and Shin-Aomori 11,602 1,017 Internal funds September 2017 FY2027」
The speed-increase work on the Tohoku Shinkansen between Morioka and Shin-Aomori increased the amount paid to date from ¥452 million to ¥1,017 million, while the scheduled completion in FY2027 was maintained. - FY2022AdvancedAnnual report
「With the aim of increasing speeds on the Tohoku Shinkansen between Morioka and Shin-Aomori, construction of the necessary facilities, including noise-control measures, was commenced in October 2020.」
Construction to increase speeds continued. Disclosed amounts paid to date under the facilities plan were ¥452 million, and the construction period runs through fiscal 2027. - FY2021AdvancedAnnual report
「With the aim of increasing speeds on the Tohoku Shinkansen between Morioka and Shin-Aomori, construction of the necessary facilities, including noise-control measures, was commenced in October 2020.」
The initiative advanced from the investigation stage to the commencement of main construction, giving concrete form to the speed-increase project on the Tohoku Shinkansen between Morioka and Shin-Aomori. - FY2021-Q2First statedAnnual report
「During the second quarter of the current fiscal year, construction of ground facilities to increase speeds on the Tohoku Shinkansen between Morioka and Shin-Aomori was commenced as part of transport improvements and other measures in the transportation business. The construction period is expected to be approximately 7 years. The planned total amount for this project is ¥11,602 million.」
Construction of ground facilities to increase speeds on the Tohoku Shinkansen between Morioka and Shin-Aomori was commenced, with a construction period of approximately 7 years and a planned total amount of ¥11.602 billion.