Construction of a new logistics center
First written in FY2016. 3 of 7 entries say "Advanced", first in FY2017-Q2. Latest entry: FY2018.
No other company in this theme has enough history to compare yet.
- FY2018AchievedAnnual report
「The principal capital expenditure during the consolidated fiscal year was ¥5,791 million for the construction of the Kanto Logistics Center (company-wide).」
Construction of the Kanto Logistics Center was completed, and ¥5,791 million was recorded as the principal capital expenditure for the fiscal year. - FY2018-Q3AchievedAnnual report
「The following major facility addition, which was under planning at the end of the previous fiscal year, was completed during the nine-month period ended 31 December 2017. Kanto Logistics Center (Kisarazu, Chiba) Total investment: ¥5,668 million Funding: internal funds and borrowings from financial institutions Completion: November 2017」
The planned construction of the Kanto Logistics Center was completed in November 2017 at a total investment of ¥5,668 million. - FY2018-Q2AdvancedAnnual report
「This was mainly due to a ¥2,025 million decrease resulting from expenditures for the acquisition of property, plant and equipment.」
The Company spent ¥2,025 million on the acquisition of property, plant and equipment during the six-month period ended 30 September, while construction in progress also increased from ¥2,008 million to ¥4,008 million. Capital expenditure, including construction of the logistics center, is progressing. - FY2017AdvancedAnnual report
「The principal capital expenditure during the consolidated fiscal year was ¥2,008 million in construction in progress for the development of the Kanto Logistics Center (tentative name) (Other).」
The Company recorded ¥2,008 million in construction in progress for the Kanto Logistics Center, indicating that the facility development had advanced from the planning stage to the construction stage. Total planned investment was ¥5,130 million, with completion scheduled for November 2017. - FY2017-Q3RestatedAnnual report
「The following major facility construction plan was newly finalised during the nine-month period ended 31 December 2016.」
Reiterates the plan for the Kanto Logistics Center in Kisarazu: land acquired, building cost of ¥5,130 million, construction scheduled to begin in late October 2016, and completion scheduled for early November 2017. The resolution and construction contract were completed in the previous quarter, and no new progress milestone is presented. - FY2017-Q2AdvancedAnnual report
「At a meeting of the Board of Directors held on 7 October 2016, the Company resolved to construct a new logistics center in order to consolidate logistics functions located at various sites and improve management efficiency as a logistics hub for eastern Japan, and entered into a construction contract on 25 October 2016.」
Formally resolved to construct the Kanto Logistics Center in Kisarazu and entered into a construction contract. The acquisition cost of the building was ¥5,130 million, construction was scheduled to begin in late October 2016, and completion was scheduled for early November 2017. - FY2016First statedAnnual report
「The principal capital expenditure during the consolidated fiscal year was ¥2,585 million for the acquisition of land for construction of a new logistics center (company-wide).」
Acquired land for a logistics center in Kisarazu, Chiba, and plans to construct the building and related facilities.