How it moved
ProgressHeldSoftenedWorseAdvancedFY2017-Q2 – FY2021-Q1AdvancedFY2021-Q3 – 2026-10-092016: 220162017: 420172018: 320182019: 420192020: 420202021: 420212022: 320222023: 420232024: 420242025: 120252026: 102026
Same theme, other companies
Restructuring the Overseas Business Model and Expanding into Growth MarketsA theme 96 companies write about · 2 as a headwind · 93 as a tailwind

The whole theme swung hardest in 2021: 8 of 55 companies on the "Worse" side.

46 other companies' latest entry also says "Advanced".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 96 companies compared. The sentences above are computed from all 96.
Full recordFilings, disclosures and news, newest first
  1. 2026-09-11Advancedwww.nikkei.com

    「技研製:タイで「インプラント工法」継続採用 静かな施工で学習環境を損なわず、強靭な河川護岸を構築」

    タイにおける継続採用の実績が、インプラント工法の海外展開の進展として報じられた。
  2. FY2026-H1AdvancedAnnual report

    「In its overseas expansion, the company is working to establish its comprehensive customer support service, GTOSS, and is accelerating market expansion in collaboration with member companies. At the same time, it is developing new customers who share the value of press-in technology and creating markets through cooperation with local business partners. In Asia, against a backdrop of strong infrastructure demand in Singapore, the company sold multiple units in the second quarter to a customer acquired in the previous fiscal year who was not a GTOSS member, following sales in the first quarter. In Europe, the first project in the commercialization phase of the renovation project for the World Heritage canals in the Netherlands was completed.」

    The company continued working with member companies through GTOSS, and reported overseas expansion progress including multiple-unit sales in Singapore and completion of the first commercialization-phase project in Amsterdam, the Netherlands.
  3. 2026-04-10AdvancedOther Disclosures

    「技研ヨーロッパは、本工事向けに「サイレントパイラー™」2 台を販売しており、継続して「ジャイロパイラー™」のレンタル、鋼管杭の先端に取り付ける切削爪(リングビット)の販売、長期間の工事に伴う機械の保守メンテナンスを担います。」

    欧州で、機械販売に加えてレンタル、部品販売、保守メンテナンスを組み合わせた総合支援型の展開が、大規模治水工事で具体化した。
  4. FY2025AdvancedAnnual report

    「As a result, press-in technology has spread to more than 40 countries and regions worldwide and is contributing to the resolution of construction challenges in each region. The company has also introduced GTOSS, a comprehensive support service for users designed to strengthen partnerships with local companies, and is promoting total support to expand the adoption of its method together with partner companies.」

    Press-in technology has expanded to more than 40 countries and regions, and adoption has progressed through GTOSS’s total-support model in collaboration with local partners.
  5. FY2024AdvancedAnnual report

    「As a result, press-in technology has spread to more than 40 countries and regions worldwide and has contributed to resolving construction challenges in each region.」

    The company has demonstrated that press-in technology has expanded to more than 40 countries and regions worldwide. It is also pursuing market expansion in Europe, Asia and North America using GTOSS.
  6. FY2024-Q3AdvancedAnnual report

    「After this phase, the company’s method is expected to be adopted as one of the standard methods for this project, which plans to renovate 200 km, and to be made generally available to specialist local contractors and others.」

    The company concluded a framework agreement in the commercialization phase with the City of Amsterdam, and progressed to the stage where its method was adopted as one of the standard methods for the 200 km renovation plan and is expected to be made generally available to specialist contractors and others.
  7. FY2024-Q2AdvancedAnnual report

    「In China, the company delivered multiple Silent Pilers to Shijiazhuang Tianyuan Technology Group Co., Ltd. (hereinafter, “Tianyuan”), a major construction equipment distributor in Hebei Province with which it entered into sales agency and designated-factory agreements in 2020. In South Korea, it delivered a third Gyro Piler, a steel pipe pile rotary cutting press-in machine, to a local user.」

    Concrete overseas expansion results included the delivery of multiple Silent Pilers to Tianyuan in China and the delivery of a third Gyro Piler to an existing user in South Korea.
  8. FY2024-Q1AdvancedAnnual report

    「In Asia, the company delivered a Gyro Piler, a steel pipe pile rotary cutting press-in machine, to a major user of its technology partner in Singapore. This was the first delivery in Southeast Asia. Going forward, the company will work with group company Giken Seisakusho Asia Pte., Ltd. (headquartered in Singapore) to develop the market for the Gyropress method. In South America, a local company that completed demonstration construction (pilot construction) under the technical guidance of the Group evaluated the superiority of press-in technology in countermeasures against tailings dam failures and decided to adopt it for continuing work.」

    The company made its first delivery of a Gyro Piler in Southeast Asia, in Singapore, and the technology was adopted for continuing work following pilot construction for tailings dam failure countermeasures in Brazil, adding concrete examples of overseas expansion.
  9. FY2023AdvancedAnnual report

    「At the “New Technology Development Project for the Renovation of World Heritage Canal Quay Walls” in Amsterdam, the Netherlands, the press-in work for the demonstration construction by G-Kracht B.V., a joint venture funded by group company Giken Europe B.V. (headquartered in the Netherlands), was completed in March, and all work, including subsequent processes, was completed in July. The work received high praise from the project owner, the City of Amsterdam, and discussions are under way toward the next commercialization phase.」

    All stages of the Amsterdam demonstration project have been completed, and discussions have progressed toward a commercialization phase in which construction contracts covering a total of 3.3 km over 8 years are guaranteed. Market expansion in Germany and Asia is also described.
  10. FY2023-Q3AdvancedAnnual report

    「The press-in work for the demonstration construction by G-Kracht B.V., a joint venture funded by group company Giken Europe B.V. (headquartered in the Netherlands), was completed in March. The work received high praise from the project owner, the City of Amsterdam, and discussions began on the next commercialization phase. In the commercialization phase, contracts for construction covering a total length of 3.3 km over 8 years are guaranteed.」

    The press-in work for the Amsterdam demonstration construction was completed, and discussions moved to the commercialization phase following recognition from the project owner. The commercialization phase guarantees construction contracts covering a total of 3.3 km over 8 years.
  11. FY2023-Q2AdvancedAnnual report

    「As part of its overseas expansion, which targets an overseas sales ratio of 70% (50% for the fiscal year ending August 2031), demonstration construction by the joint venture G-Kracht B.V. has progressed smoothly on the “New Technology Development Project for the Renovation of World Heritage Canal Quay Walls” in Amsterdam, the Netherlands, under technical guidance from group company Giken Seisakusho Co., Ltd. In January, an electric GRB system was deployed at the site, and construction has proceeded using space-saving methods that avoid cutting down the avenue trees. The method has received high praise from the project owner as a way to preserve the environment and visual appeal.」

    The electric GRB system was deployed at the Amsterdam demonstration site, marking concrete progress in overseas expansion by avoiding the cutting down of avenue trees through space-saving construction.
  12. FY2023-Q1AdvancedAnnual report

    「As part of its overseas expansion targeting an overseas revenue ratio of 70% (50% in the fiscal year ending August 2031), the press-in phase of demonstration construction by the joint venture G-Kracht B.V. for Amsterdam’s “New Technology Development Project for the Rehabilitation of World Heritage Canals” began in November under the technical guidance of Giken Seisakusho. Press-in construction using an electric Gyropiler, which contributes to carbon neutrality, and the GRB System is progressing smoothly, with 271 steel pipe piles scheduled to be installed along a 208 m section by next spring. In Asia, the Group delivered a second Silent Piler F301-700 to a user in India acquired in the previous fiscal year and a Silent Piler SA100 to a user in Taiwan. It also received orders from users in Singapore, South Korea and Indonesia for Silent Piler F301-900 and other machines, with user demand steadily expanding as the press-in market grows.」

    Pilot construction in Amsterdam began in November, and plans to install 271 steel pipe piles along a 208 m section were finalised. Deliveries to India and Taiwan and orders from Singapore, South Korea and Indonesia added further progress to the Group’s overseas track record.
  13. FY2022AdvancedAnnual report

    「As part of its overseas expansion targeting an overseas revenue ratio of 70%, the Group’s joint venture G-Kracht B.V., established in April 2021 for the “New Technology Development Project for the Rehabilitation of World Heritage Canals in Amsterdam,” entered into a demonstration construction (pilot construction) agreement with the City of Amsterdam, the project owner, in June 2022. Press-in construction using an electric Gyropiler, which contributes to carbon neutrality, and the GRB System is scheduled to begin in November.」

    For the Amsterdam project, G-Kracht entered into a demonstration construction agreement and advanced to the planned start of construction using an electric Gyropiler and the GRB System. Overseas achievements also expanded, with approximately 52 km of riverbank improvements in Thailand, Silent Piler deliveries in India, completion of demonstration construction in Brazil, and continued work on the Sydney Fish Market project in Australia.
  14. FY2022-Q2AdvancedAnnual report

    「For major overseas projects, the newly developed electric GRB System for the Amsterdam canal quay-wall rehabilitation project arrived at the site at the end of January, and preparations for pilot construction are under way. For disaster-prevention work at a tailings dam in Brazil, the Group advanced construction planning for protective walls and technical guidance by Japanese staff to local companies toward full-scale construction. Press-in construction is also progressing on the foundation work, including temporary cofferdam construction, secured for the Sydney Fish Market redevelopment project in Australia.」

    Specific progress was reported on major overseas projects, including the arrival of the electric GRB System in Amsterdam, construction planning and technical guidance in Brazil, and press-in construction at the Sydney Fish Market in Australia.
  15. FY2022-Q1AdvancedAnnual report

    「Overseas, the Group is focusing on proposals for construction methods that maximise the advantages of the press-in principle and observe the Five Great Principles of Construction to a high standard. The number of construction projects resulting from these activities is steadily increasing, raising awareness of the Implant Construction Method. For the Amsterdam canal quay-wall rehabilitation project, demonstration testing in Japan of the electric GRB System for pilot construction scheduled to begin in January 2022 was completed, and preparations for shipment to the site were finalised. For disaster-prevention work at a tailings dam in Brazil, Group employees conducted a site survey and began part of the construction. The Group continues work toward full-scale construction, including construction planning for protective walls and remote technical guidance for local companies. In Australia, the Group began foundation work, including temporary cofferdam construction, for the Sydney Fish Market redevelopment project.」

    For the Amsterdam project, demonstration testing of the electric GRB System was completed and preparations advanced to shipment. In Brazil, part of the construction began, while in Australia foundation work for the Sydney Fish Market redevelopment began.
  16. FY2021AdvancedAnnual report

    「For major projects, Giken Europe B.V., the overseas subsidiary, established a joint venture, G-Kracht B.V. (G-Kracht B.V.), with its local construction-company partner for the new technology development project relating to Amsterdam’s canal quay-wall rehabilitation. In preparation for pilot construction scheduled to begin in January 2022, detailed design and various monitoring plans are being developed locally, while demonstration testing of the newly developed electric GRB System is under way in Japan.」

    For the Amsterdam project, the Group established a joint venture with a local construction company and advanced to detailed design, monitoring plans and demonstration testing of the electric GRB System for pilot construction in January 2022.
  17. FY2021-Q3AdvancedAnnual report

    「Overseas, the Group continues to pursue proposals for construction methods that maximise the advantages of the press-in principle and observe the Five Great Principles of Construction to a high standard, with the aim of becoming a global engineering company. Its overseas subsidiary Giken Seisakusho Asia Pte., Ltd. opened a representative office in Bangkok, the capital of Thailand, where flooding occurs frequently, to raise awareness of press-in technology and strengthen proposals for flood-control measures using the Implant Construction Method. Meanwhile, the quay-wall rehabilitation project at the Port of Dakar in Senegal, secured under a Japanese ODA project, was completed in March. The project has attracted attention from ODA stakeholders as a strong example of the Implant Construction Method, a unique Japanese technology, solving construction challenges in a developing country. It has been widely featured in the media and at seminars and is expected to provide momentum for the global adoption of press-in technology.」

    In addition to opening a representative office in Bangkok and strengthening proposals for flood-control measures, the quay-wall rehabilitation project at the Port of Dakar in Senegal was completed in March, adding another specific achievement to the Group’s overseas expansion.
  18. FY2021-Q2SoftenedAnnual report

    「Overseas, the Group strengthened its efforts to become a global engineering company by advancing proposals for construction methods that maximise the advantages of the press-in principle and observe the Five Great Principles of Construction to a high standard. For the Amsterdam canal quay-wall rehabilitation project, the Group is advancing detailed structural design and machinery development toward demonstration construction from 2022. It is also continuing to propose measures to ensure the safety of a tailings dam in Brazil, while advancing specific construction-method proposals for major projects in Australia and Thailand.」

    The Group is advancing construction-method proposals overseas, detailed design and machinery development for the Amsterdam project, and proposals for major projects in Brazil, Australia and Thailand. Meanwhile, the previously stated demonstration construction schedule has been updated from September 2021 to 2022.
  19. FY2021-Q1AdvancedAnnual report

    「For overseas expansion, the Group’s basic policy is to provide total-package solutions covering design, procurement and construction, and it is shifting toward proposals tailored to each regional market. Although inquiries are increasing, the Group is selecting projects for which the advantages of the press-in principle can be maximised and the Five Great Principles of Construction can be observed to a high standard. For major projects, preparations were made for demonstration construction on the Amsterdam canal quay-wall rehabilitation project from September 2021, including quay-wall structural design, machinery development and establishment of the project structure. For the proposed solution for a tailings dam in Brazil, discussions are under way toward selection, covering structural design, construction planning and the supply of equipment and materials. The Group also sold 3 Silent Pilers to Tianyuan in Hebei, China, with which it entered into sales agency and designated factory agreements in October 2020, as it prepared to expand the press-in market.」

    Overseas expansion advanced through the shift to total-package proposals, preparations for demonstration construction in Amsterdam, discussions on the Brazilian project, agreements with a sales agent and designated factory in Hebei, China, and the sale of 3 Silent Pilers.
  20. FY2020AdvancedAnnual report

    「J Steel Group Pty Limited, the Australian subsidiary, is shifting away from a business focused primarily on steel materials sales and has already secured a project on a turnkey basis, from design through construction.」

    Regarding the packaged global expansion of the Implant Construction Method, J Steel has shifted away from its focus on steel materials sales and has secured projects on a turnkey basis, from design through construction.
  21. FY2020-Q3AdvancedAnnual report

    「In May, the Group’s Gyropress Method and GRB System received the highest rating in Amsterdam’s review of proposals for a new technology development partnership relating to the rehabilitation of canal quay walls in a World Heritage area, and the Group entered into a partnership agreement with the City of Amsterdam. The city’s canals under its jurisdiction extend for more than 600 km, of which 200 km requires urgent action. Giken Europe jointly submitted the proposal with its Dutch partner De Koning and local general contractor Van Gelder. Following technology development and pilot construction by the 3 companies, and subject to a further review, quay-wall rehabilitation work will initially be carried out for 4 years from January 2023, with an extension of up to 8 years, at a maximum rate of approximately 1 km per year and an annual budget of approximately ¥2.0 billion.」

    The Group received the highest rating for canal quay-wall rehabilitation in Amsterdam and entered into a partnership agreement with the city. The project has advanced to detailed plans for construction beginning in January 2023 following technology development and pilot construction.
  22. FY2020-Q2AdvancedAnnual report

    「The press-in method was adopted for railway-related construction projects in Minneapolis, United States, and Melbourne, Australia.」

    The press-in method was adopted for railway-related construction in Minneapolis, United States, and Melbourne, Australia, adding specific overseas applications to the Group’s track record.
  23. FY2020-Q1AdvancedAnnual report

    「Under an ODA project, the Group won quay-wall rehabilitation work at the Port of Dakar in Senegal using the Gyropress Method. Construction has been under way since the end of July under a schedule running through the end of June 2020, including a total construction period of 7 months. Phase 1 progressed very smoothly and was completed with positive results in early November, and Phase 2 will begin in 2020.」

    Phase 1 of the Port of Dakar project in Senegal was completed with positive results, adding specific progress in overseas construction as the project moves to Phase 2 in 2020.
  24. FY2019AdvancedAnnual report

    「During the fiscal year, the press-in method was adopted and completed in a residential area of Manhattan, New York, providing a major catalyst for future growth. J Steel Group Pty Limited, the Group’s subsidiary, also continued proposing the press-in method, and construction projects based on packaged proposals began to be secured in Australia.」

    Construction in a residential area of Manhattan, New York, was adopted and completed, while construction projects based on packaged proposals were also secured in Australia, adding specific achievements to the Group’s overseas expansion.
  25. FY2019-Q3AdvancedAnnual report

    「The Gyropress Method was selected for the quay-wall rehabilitation project at the Port of Dakar in Senegal, an ODA project for which the Group had been making proposals, and will be used for the first time on the African continent. In addition, the Zero-Clearance Method was selected for hospital construction in Cairo, Egypt, as it allows construction without affecting adjacent structures. Work is scheduled to begin in mid-August.」

    The Gyropress Method was selected for quay-wall rehabilitation work in Senegal, becoming the first application on the African continent. The Zero-Clearance Method was also selected for hospital construction in Egypt, with the planned start of construction announced.
  26. FY2019-Q2AdvancedAnnual report

    「As a specific initiative to expand overseas markets, the US subsidiary Giken America Corporation opened a new base in an office building in central Manhattan, New York City, near Grand Central Terminal, and moved its head-office functions there. Engineers from its partner, Mueser Rutledge Consulting Engineers (MRCE), will work at the new base, where the companies will jointly promote awareness and adoption of the press-in method, mainly in the northeastern United States.」

    Specific progress was made in overseas expansion, including the opening of a new base in the United States, the relocation of head-office functions and the acceptance of MRCE engineers.
  27. FY2019-Q1AdvancedAnnual report

    「Overseas, Giken America Corporation entered into a collaboration agreement with Mueser Rutledge Consulting Engineers (MRCE) in the United States, while Giken Europe B.V. entered into a collaboration agreement with Gebr. De Koning B.V. in the Netherlands.」

    The Group entered into collaboration agreements with companies in the United States and the Netherlands and is strengthening its domestic and overseas structure to raise recognition and accelerate adoption of its construction method overseas.
  28. FY2018AdvancedAnnual report

    「Overseas, potential demand is expected for infrastructure redevelopment and disaster recovery work in urban areas worldwide because of the superiority of the press-in method. The Group is promoting its wider adoption, including in ODA projects. These efforts are beginning to bear fruit, with demand increasing mainly in Asia, including China. In addition, J Steel Group Pty Limited (Australia) became a subsidiary in December last year, and the Group is building a structure to promote global expansion through packaging the Implant Construction Method.」

    The Group says demand increased in Asia, including China, and that it is building a packaged global expansion structure based on making J Steel a subsidiary.
  29. FY2018-Q3AdvancedAnnual report

    「In overseas markets, product sales were at the same level as in the same quarter of the previous year, although large-scale construction projects declined. However, the consolidation of J Steel Group Pty Limited (Australia), which became a subsidiary in December last year, resulted in an increase in total overseas revenue year on year. In December last year, the superiority of the Group’s construction method was recognised for the first time in subway restoration work following hurricane damage in Manhattan, New York City, and subway station redevelopment work, leading to its first adoption. The Group will continue promoting the wider adoption of the construction method worldwide, including in ODA projects.」

    Total overseas revenue increased year on year due to the consolidation of J Steel, and the Group’s construction method was adopted for the first time in subway-related work in Manhattan, New York, adding another specific achievement to its overseas expansion.
  30. FY2018-Q2AdvancedAnnual report

    「Based on the “Medium-Term Management Plan (fiscal years ending August 2016 to August 2018),” the Group is actively pursuing ① global expansion through packaging the Implant Construction Method, ② further strengthening a corporate structure specialising in development, and ③ making Kochi the world’s centre for press-in technology, with the aim of achieving its numerical targets of revenue of ¥27.5 billion and operating profit of ¥5.8 billion. Overseas, sales of press-in machines are gradually increasing as the press-in method gains recognition.」

    The Group says it is continuing global expansion under its medium-term management plan and that overseas sales of press-in machines are gradually increasing.
  31. FY2017AdvancedAnnual report

    「In Bangladesh, the Group won bridge foundation construction work using the Implant Construction Method under an ODA project, and most of the work has been completed. Based on this track record, the Group is confident that it will win more overseas construction projects.」

    Most of the bridge foundation construction work in Bangladesh has been completed, adding further progress to the Group’s overseas construction operations.
  32. FY2017-Q3AdvancedAnnual report

    「Overseas, the market is steadily expanding as the press-in method gains recognition, including the first deliveries of Silent Pilers to Cambodia and Australia. In Bangladesh, the Group won bridge foundation construction work using the Implant Construction Method, and construction is now under way. The project is expected to be a major step toward winning more overseas construction projects.」

    The Group’s overseas track record advanced with the first deliveries of Silent Pilers to Cambodia and Australia, together with bridge foundation construction work under way in Bangladesh.
  33. FY2017-Q2AdvancedAnnual report

    「In overseas operations, the Group has built a track record mainly in Asia, including its first delivery of a Silent Piler to Cambodia in January this year and winning and commencing bridge foundation construction work using the Implant Construction Method in Bangladesh.」

    Specific overseas achievements were added, including the first delivery of a Silent Piler to Cambodia and the winning and commencement of bridge foundation construction work in Bangladesh.
  34. FY2017-Q1RestatedAnnual report

    「① Global expansion through packaging the Implant Construction Method」

    The Group has reiterated packaging and global expansion as basic strategies under its medium-term management plan for the fiscal years ending August 2016 to August 2018.
  35. FY2016AdvancedAnnual report

    「The Silent Piler, supplied at the strong request of Myanmar’s Ministry of Construction, is scheduled for use throughout Myanmar. Work sites requiring the machine are being selected, and the deployment of multiple machines is expected.」

    The Myanmar government decided to introduce Silent Piler F111 and the GRB System, and site selection is under way for nationwide operation and the deployment of multiple machines.
  36. FY2016-Q3First statedAnnual report

    「① Global expansion through packaging the Implant Construction Method」

    One of the three priority items in the medium-term management plan for the fiscal years ending August 2016 to August 2018.
Moved together

"Recognition of the advantages of the implant construction method and its expanding adoption in various regions" moved the same way as this thread, in the same document, in 30 of its 43 moves.

302422211716★123456
  1. ★This thread
  2. 1Recognition of the advantages of the implant construction method and its expanding adoption in various regions30×
  3. 2Expansion of the Press-Fit Market Through Broader Applications and Coverage Areas24×
  4. 3Development of Equipment and Construction Methods for Diverse Construction Conditions, Pile Materials and Large-Diameter Piles22×
  5. 4Development and Adoption of Implant-Type Seawalls in Coastal Areas21×
  6. 5GRB System Standardization and Package Rollout with Silent Piling Machines17×
  7. 6Increase in Capital and Capital Reserve Through Exercise of Stock Acquisition Rights16×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Giken's next results are scheduled for 2026-10-09. Read the earnings preview It last moved in the Earnings presentation materials of 2026-10-09: "Advanced".