1.5-fold increase in wire electrical-discharge machine production capacity through construction of a new precision factory and office building
First written in FY2022. 3 of 8 entries say "Advanced", first in FY2023-Q3. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026AchievedAnnual report
「In terms of its production system, the company has achieved production capacity 1.5 times its previous level through construction of the new factory and promotion of digital transformation, and will continue preparing for further production increases.」
The company states that it achieved its target of increasing wire electrical-discharge machine production capacity to 1.5 times its previous level through construction of the new precision factory and office building and promotion of digital transformation. - 2026-05-15AchievedFinancial results presentation
「生産体制では、新工場におけるDX推進により従来比1.5倍の生産能力を達成しており」
新精密工場兼事務所棟について、DX推進により従来比1.5倍の生産能力を達成したと記載している。 - FY2026-H1AdvancedAnnual report
「Net sales totaled ¥8,646 million, up 27.0% year on year, as production capacity increased further through the promotion of automation and digital transformation at the new factory.」
The company states that production capacity at the completed new precision factory and office building increased further through the promotion of automation and digital transformation. - FY2025-H1AchievedAnnual report
「During the current interim consolidated accounting period, the precision plant and office building was completed among the major facilities that the company had been planning to newly install as of the end of the previous consolidated fiscal year.」
The company states that the new precision factory and office building, built with an investment of approximately ¥5 billion to increase wire electrical-discharge machine production capacity to 1.5 times its current level, has been completed. - FY2024-Q3RestatedAnnual report
「During the current third-quarter consolidated cumulative period, part of the precision plant and office building was completed among the major facilities that the company had been planning to newly install as of the end of the previous consolidated fiscal year.」
The construction plan for the new precision factory and office building remains at the partial-completion stage described in the previous quarter. - FY2024-Q2AdvancedAnnual report
「During the 2nd quarter cumulative consolidated period, part of the precision plant and office building was completed among the major new facilities that the company had planned to construct as of the end of the previous consolidated fiscal year.」
The construction plan for the new precision factory and office building has reached the specific milestone of partial completion. - FY2023-Q3AdvancedAnnual report
「Company name Operating site Location Segment Type of facility Planned investment Funding source Method Start and scheduled completion Additional capacity after completion Total amount (¥ thousands) Head office factory of the submitting company Koga, Fukuoka Prefecture Precision machinery business Buildings 5,000,000 48,860 Internal funds 2022.12 2024.9 (Note) Production capacity for wire electrical-discharge machines is scheduled to be increased to 1.5 times its current level.」
Construction of the new precision factory and office building began in December 2022, with completion scheduled for September 2024. The company continues to pursue its plan to invest a total of ¥5 billion, of which ¥48.86 million had already been paid, and increase production capacity to 1.5 times its current level. - FY2022First statedAnnual report
「To continue responding accurately to growing demand for our products, we will increase production capacity to 1.5 times its current level through construction of a new factory and strengthen the competitiveness of the business. Construction will involve digitizing the entire manufacturing process, creating an efficient production line, expanding automation across production processes and improving logistics efficiency through the use of AGVs.」
The company plans to invest approximately ¥5 billion to build a new precision factory and office building, with construction starting in December 2022 and completion scheduled for September 2024. Production capacity for wire electrical-discharge machines will be increased to 1.5 times its current level, alongside initiatives in digitization, automation, AGV use and solar power generation.