Development of a large-scale solar power plant with an output of approximately 67 MW in Miyako Town, Fukuoka Prefecture
First written in FY2021. 4 of 9 entries say "Restated". Latest entry: 2026-08-07.
No other company in this theme has enough history to compare yet.
- 2026-08-07Cited as achievedShare Issuance and Disposal
「① Power generation business at the “Fukuoka Miyako Mega Solar Power Plant”」
For the Fukuoka Miyako Mega Solar Power Plant, the company reported full allocation of proceeds raised, installed capacity of approximately 67.0 MW, CO₂ emissions reductions of 27,538 t-CO₂ per year (cumulative: 120,444 t-CO₂), and cumulative employment of 8 people. - FY2023RestatedAnnual report
「The company recorded revenue of ¥2,285 million as EPC for the large-scale solar power plant in Miyako, Kyoto District, Fukuoka Prefecture, progressed smoothly. The plant has generating capacity of approximately 67.0MW, comprising approximately 23.2MW at the North Plant and approximately 43.8MW at the South Plant. Construction of the North Plant was completed in the previous consolidated fiscal year, and construction of the South Plant was completed during the third quarter consolidated accounting period.」
The completion of construction at both the North and South Plants of the approximately 67MW Miyako project and the recognition of revenue from development-oriented EPC are confirmed. - FY2023-Q3AchievedAnnual report
「During the third quarter consolidated cumulative period, the company recorded revenue of ¥2,285 million as EPC for the large-scale solar power plant in Miyako, Kyoto District, Fukuoka Prefecture, a development-oriented project using the Feed-in Tariff (FIT) Scheme (Note 8), progressed smoothly. The plant has generating capacity of approximately 67.0MW, comprising approximately 23.2MW at the North Plant and approximately 43.8MW at the South Plant. Construction of the North Plant was completed in the previous consolidated fiscal year, and construction of the South Plant was completed during the third quarter consolidated accounting period.」
At the approximately 67.0MW Miyako large-scale solar power plant, construction of the South Plant was completed during the third quarter accounting period, following the North Plant, bringing construction of the entire project to completion. - FY2023-Q2RestatedAnnual report
「During the second quarter consolidated cumulative period, the company recorded revenue of ¥1,939 million as EPC for the large-scale solar power plant in Miyako, Kyoto District, Fukuoka Prefecture, a development-oriented project using the Feed-in Tariff (FIT) Scheme (Note 8), progressed smoothly. The plant has generating capacity of approximately 67.0MW, comprising approximately 23.2MW at the North Plant and approximately 43.8MW at the South Plant, and is scheduled for completion in the fiscal year ending June 2023. Construction of the North Plant was completed in the previous consolidated fiscal year.」
The company continues to state the EPC progress and planned completion in the fiscal year ending June 2023 for the approximately 67.0MW Miyako project. - FY2023-Q1RestatedAnnual report
「During the first quarter consolidated cumulative period, the company recorded revenue of ¥1,021 million as EPC for the large-scale solar power plant in Miyako, Kyoto District, Fukuoka Prefecture, a development-oriented project using the Feed-in Tariff (FIT) Scheme (Note 8), progressed smoothly. The plant has generating capacity of approximately 67.0MW, comprising approximately 23.2MW at the North Plant and approximately 43.8MW at the South Plant, and is scheduled for completion in the fiscal year ending June 2023. Construction of the North Plant was completed in the previous consolidated fiscal year.」
The company continues to state the EPC progress and planned completion in the fiscal year ending June 2023 for the approximately 67.0MW Miyako project. The North Plant was completed in the previous consolidated fiscal year. - FY2022-Q3AdvancedAnnual report
「During the third quarter consolidated cumulative period, the company recorded revenue of ¥7,102 million as EPC for the large-scale solar power plant in Miyako, Kyoto District, Fukuoka Prefecture, a development-oriented project using the Feed-in Tariff (FIT) Scheme (Note 8), progressed smoothly. The plant has generating capacity of approximately 67.0MW, comprising approximately 23.2MW at the North Plant and approximately 43.8MW at the South Plant, and is scheduled for completion in the fiscal year ending June 2023.」
For the approximately 67.0MW Miyako project, cumulative EPC revenue reached ¥7,102 million, and the plan for completion in the fiscal year ending June 2023 continues. - FY2022-Q2RestatedAnnual report
「During the second quarter consolidated cumulative period, the company recorded revenue of ¥5,039 million as EPC for the large-scale solar power plant in Miyako, Kyoto District, Fukuoka Prefecture, progressed smoothly. The plant has generating capacity of approximately 67.0MW, comprising approximately 23.2MW at the North Plant and approximately 43.8MW at the South Plant, and is scheduled for completion in the fiscal year ending June 2023. Construction of the North Plant was completed during the first quarter consolidated accounting period.」
The company reports smooth progress in EPC for the approximately 67.0MW project and cumulative revenue of ¥5,039 million, but indicates no new stage of completion since the previous quarter, including the completion of the North Plant. - FY2022-Q1AdvancedAnnual report
「During the first quarter consolidated cumulative period, the company recorded revenue of ¥3,506 million as EPC for the large-scale solar power plant in Miyako, Kyoto District, Fukuoka Prefecture, progressed smoothly. The plant has generating capacity of approximately 67.0MW, comprising approximately 23.2MW at the North Plant and approximately 43.8MW at the South Plant, and is scheduled for completion in the fiscal year ending June 2023. Construction of the North Plant was completed during the first quarter consolidated cumulative period.」
EPC for the approximately 67.0MW large-scale solar power plant progressed, and construction of the approximately 23.2MW North Plant was completed. The overall project is scheduled for completion in the fiscal year ending June 2023. - FY2021First statedAnnual report
「As a development-oriented engineering business, the company is working on a large-scale solar power plant in Miyako, Kyoto District, Fukuoka Prefecture, with generating capacity of approximately 67.0MW, and is advancing the development process with thorough progress management.」
The company identifies the large-scale solar power plant development project individually and provides its generating capacity.