Making the Approximately 46 MW Imari Biomass Power Generation Business a Wholly Owned Subsidiary

First written in FY2022-Q1. 9 of 15 entries say "Advanced", first in FY2022-Q2. Latest entry: 2026-08-07.

15entries
6years
2from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2022-Q3 – FY2023-Q1AdvancedFY2023-Q2 – FY20252021: 12022: 320222023: 420232024: 320242025: 220252026: 22026
Same theme, other companies
伊万里バイオマス発電事業の完全子会社化・運転開始A theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2025AchievedAnnual report

    「In April 2025, the consolidated subsidiary 株式会社伊万里グリーンパワー commenced commercial operations at a large-scale biomass power plant in Imari, Saga Prefecture, using biomass fuels including PKS.」

    The approximately 46 MW Imari biomass power plant progressed from the construction plan to the commencement of commercial operations in April 2025.
  2. FY2025-H1AdvancedAnnual report

    「株式会社伊万里グリーンパワー | Saga Imari Biomass Power Plant (provisional name) | Wood biomass power generation equipment | 32,000 | 30,884 | Proceeds from disposal of treasury shares, borrowings, own funds, and proceeds from capital increases | February 2022 | May 2025 | Generating capacity after completion (MW): 46.0 | No change to the plan since the end of the previous consolidated fiscal year」

    For the approximately 46 MW Imari biomass power plant, the amount paid increased to ¥30,884 million, while total planned investment of ¥32,000 million and completion scheduled for May 2025 remained unchanged.
  3. FY2024AdvancedAnnual report

    「株式会社伊万里グリーンパワー | Saga Imari Biomass Power Plant (provisional name) | Wood biomass power generation equipment | 32,000 | 25,452 | Proceeds from disposal of treasury shares, borrowings, own funds, and proceeds from capital increases | February 2022 | May 2025 | Generating capacity after completion (MW): 46.0 | No change to the plan since the end of the previous fiscal year」

    For the approximately 46 MW Imari biomass power plant, the amount paid increased to ¥25,452 million, while total planned investment of ¥32,000 million and the planned completion date of May 2025 were maintained.
  4. FY2024-Q3AdvancedAnnual report

    「株式会社伊万里グリーンパワー | Saga Imari Biomass Power Plant (provisional name) | Wood biomass power generation equipment | 32,000 | 24,791 | Proceeds from disposal of treasury shares, borrowings, own funds, and proceeds from capital increases | February 2022 | May 2025 | Generating capacity after completion (MW): 46.0 | No change to the plan since the end of the previous consolidated fiscal year」

    For the approximately 46 MW Imari biomass power plant, the amount paid increased from ¥18,559 million in the previous quarter to ¥24,791 million. Total planned investment is ¥32,000 million, completion is scheduled for May 2025, and there is no change to the plan.
  5. FY2024-Q2AdvancedAnnual report

    「株式会社伊万里グリーンパワー | Saga Imari Biomass Power Plant (provisional name) | Wood biomass power generation equipment | 32,000 | 18,559 | Proceeds from disposal of treasury shares, borrowings, own funds, and proceeds from capital increases | February 2022 | May 2025 | Generating capacity after completion (MW): 46.0 | No change to the plan since the end of the previous consolidated fiscal year」

    For the approximately 46 MW Imari biomass power plant, the amount paid increased from ¥12,431 million in the previous quarter to ¥18,559 million. Total planned investment is ¥32,000 million, completion is scheduled for May 2025, and there is no change to the plan.
  6. FY2024-Q1AdvancedAnnual report

    「株式会社伊万里グリーンパワー | Saga Imari Biomass Power Plant (provisional name) | Wood biomass power generation equipment | 32,000 | 12,431 | Proceeds from disposal of treasury shares, borrowings, own funds, and proceeds from capital increases | February 2022 | May 2025 | Generating capacity after completion (MW): 46.0 | No change to the plan since the end of the previous consolidated fiscal year」

    For the approximately 46 MW Imari biomass power plant, the amount paid increased from ¥11,821 million at the end of the previous fiscal year to ¥12,431 million, with total planned investment of ¥32,000 million, completion scheduled for May 2025, and no change to the plan.
  7. FY2023AdvancedAnnual report

    「株式会社伊万里グリーンパワー | Saga Imari Biomass Power Plant (provisional name) | Wood biomass power generation equipment | 32,000 | 11,821 | Proceeds from disposal of treasury shares, borrowings, own funds, and proceeds from capital increases | February 2022 | May 2025 | Generating capacity after completion (MW): 46.0」

    For the approximately 46 MW Imari biomass power plant, the amount paid increased to ¥11,821 million, while the planned completion date of May 2025 was maintained.
  8. FY2023-Q3AdvancedAnnual report

    「株式会社伊万里グリーンパワー | Saga Imari Biomass Power Plant (provisional name) | Wood biomass power generation equipment | 32,000 | 11,224 | Borrowings and own funds | February 2022 | May 2025 | Generating capacity after completion (MW): 46.0 | No change to the plan since the end of the previous consolidated fiscal year」

    For the approximately 46 MW Saga Imari biomass power plant, the amount paid increased from ¥10,637 million to ¥11,224 million, with completion scheduled for May 2025 and no change to the plan.
  9. FY2023-Q2AdvancedAnnual report

    「株式会社伊万里グリーンパワー | Saga Imari Biomass Power Plant (provisional name) | Wood biomass power generation equipment | 32,000 | 10,637 | Borrowings and own funds | February 2022 | May 2025 | Generating capacity after completion (MW): 46.0 | No change to the plan since the end of the previous consolidated fiscal year」

    For the approximately 46 MW Saga Imari biomass power plant, the amount paid increased to ¥10,637 million, while the plan to complete the project in May 2025 was maintained.
  10. FY2023-Q1RestatedAnnual report

    「株式会社伊万里グリーンパワー | Saga Imari Biomass Power Plant (provisional name) | Wood biomass power generation equipment | 32,000 | 6,055 | Borrowings and own funds | February 2022 | May 2025 | Generating capacity after completion (MW): 46.0 | No change to the plan since the end of the previous consolidated fiscal year」

    For the approximately 46 MW Saga Imari biomass power plant, the amount paid increased to ¥6,055 million, with no change to the plan scheduled for completion in May 2025.
  11. FY2022-Q3RestatedAnnual report

    「No change to the plan since the end of the second quarter」

    For the approximately 46 MW Saga Imari biomass power plant, the construction plan remains unchanged, with total planned investment of ¥32,000 million, construction commencing in February 2022, and completion scheduled for May 2025.
  12. FY2022-Q2AdvancedAnnual report

    「As renewable energy becomes a primary power source, the Group is working to monetize its renewable energy power generation business across various phases. 株式会社伊万里グリーンパワー is developing an approximately 46 MW biomass power generation business in Imari, Saga Prefecture, and decided to begin construction of the power plant for commencement of operations in May 2025.」

    The plan for the wholly owned Imari Green Power subsidiary was finalized: construction of the approximately 46 MW power plant, with an investment of approximately ¥32.0 billion, began in February 2022, with operations scheduled to commence in May 2025.
  13. FY2022-Q1AchievedAnnual report

    「株式会社伊万里グリーンパワー was established in September 2016 to develop a biomass power generation business of approximately 46 MW in Imari, Saga Prefecture. It obtained certification for its business plan under the Feed-in Tariff Scheme for Renewable Energy on 9 March 2017 and plans to commence operations in May 2025.」

    The Company acquired the shares on 14 September 2021 and made the company a subsidiary with a 100% voting interest. The acquisition consideration was ¥1,800 million, and the approximately 46 MW biomass power generation business is scheduled to commence in May 2025.
Moved together

"Expansion of EPC Business in Power Generation and Utility Facilities" moved the same way as this thread, in the same document, in 10 of its 15 moves.

10107443★123456
  1. ★This thread
  2. 1Expansion of EPC Business in Power Generation and Utility Facilities10×
  3. 2Ownership, Operation and Electricity Sales from Renewable Energy Power Plants10×
  4. 3On-Site PPA Service Using Self-Consumption Solar Power Generation7×
  5. 4PKS Fuel Sales4×
  6. 5Additional acquisition of silent partnership interests in Fukuoka Miyako Mega Solar4×
  7. 6O&M and Remote Monitoring for Power Generation and Energy Facilities3×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for TESS Holdings yet. It last moved in the Share Issuance and Disposal of 2026-08-07: "Cited as achieved".
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Making the Approximately 46 MW Imari Biomass Power Generation Business a Wholly Owned Subsidiary | TESS Holdings Co.,Ltd. (5074) | Komori