Tokyo Energy & Systems (1945) · InitiativeAdvanced

Construction of New and Renovated Substations

First written in FY2017-Q2. 10 of 14 entries say "Advanced", first in FY2023-Q2. Latest entry: 2026-08-06.

14entries
11years
2from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2017-Q2 – FY2018-Q1AdvancedFY2023-Q2 – 2026-08-062016: 12017: 320172018: 020182019: 020192020: 020202021: 020212022: 120222023: 220232024: 220242025: 220252026: 32026
Same theme, other companies
Expanding orders for new substation construction and substation renovation workA theme 3 companies write about · 0 as a headwind · 3 as a tailwind

1 other company's latest entry also says "Advanced".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. 2026-08-06AdvancedEarnings

    「New substation construction」

    New substation construction contributed to higher orders, while new construction and expansion work associated with rising electricity demand also contributed to revenue.
  2. FY2026AdvancedAnnual report

    「In the substation field, new and expansion construction for substations is expected in response to rising electricity demand resulting from the construction of new data centers and other developments accompanying the spread of generative AI. We will seek to expand our share by leveraging the expertise we have developed in extra-high-voltage substation construction.」

    Regarding new and expansion construction for substations, the company is moving to expand its share by leveraging its expertise in extra-high-voltage substation construction against the backdrop of rising electricity demand from data centers.
  3. 2026-05-12AdvancedEarnings

    「Revenue increased to ¥83,083 million, up 22.7% year on year, due to progress in decommissioning-related work at the Fukushima Daiichi Nuclear Power Station, safety upgrade and repair work at nuclear power plants and other facilities across Japan, new construction and expansion of substations in response to rising electricity demand, construction of battery-related plants, repair and dismantling work at thermal power plants, repair work that increased as a result of establishing a permanent presence at oil refineries, and on-site PPA equipment and construction work in the solar power field.」

    New construction and expansion of substations are cited as factors behind the increase in revenue.
  4. FY2026-H1AdvancedAnnual report

    「In the newly established Substation Construction Department, we are also expanding our share of new and expansion construction for substation equipment in response to rising electricity demand from data centers.」

    Centered on the newly established Substation Construction Department, the company is expanding its share of new and expansion construction for substation equipment against the backdrop of rising electricity demand from data centers.
  5. FY2025AdvancedAnnual report

    「In the substation field, we will seek to expand our share of new and expansion construction for substations, centered on the newly established Substation Construction Department, which was created to address the increase in electricity demand accompanying the progress of DX and GX.」

    The company established a Substation Construction Department and advanced to the stage of seeking to expand its share of new and expansion construction for substations against the backdrop of rising electricity demand driven by DX and GX.
  6. FY2025-H1AdvancedAnnual report

    「Although there was progress in new and capacity-enhancement construction for substation equipment,」

    New and capacity-enhancement construction for substation equipment was identified as a factor behind revenue progress during the interim period.
  7. FY2024-Q3AdvancedAnnual report

    「Orders received during the nine-month consolidated cumulative period totaled ¥41,269 million, down 18.0% year on year. Although orders were received for electrical equipment construction at large public facilities, new substation construction, electrical instrumentation work for factory equipment, renewal of receiving and substation equipment, and biomass fuel sales, construction work for biomass and solar power plants declined.」

    New substation construction and renewal of receiving and substation equipment were disclosed as part of the orders received during the third quarter, together with electrical instrumentation work for factory equipment and other projects.
  8. FY2024-Q2AdvancedAnnual report

    「Orders received in the six-month period ended 30 September amounted to ¥27.790 billion, up 9.6% year on year, due to orders for electrical equipment work at large public facilities, new substation construction, solar power and battery storage facility installation, and biomass fuel sales.」

    Orders for new substation construction, together with electrical equipment construction for large public facilities and other projects, were factors behind the increase in orders received.
  9. FY2024-Q1AdvancedAnnual report

    「Order intake for the cumulative first quarter amounted to ¥1.3995 billion, up 27.9% year on year, due to orders for electrical work at large public facilities, substation equipment work and nuclear power plant safety-related work.」

    Orders for substation equipment construction, together with electrical equipment construction for large public facilities and nuclear safety improvement projects, were factors behind the increase in orders received.
  10. FY2023-Q2AdvancedAnnual report

    「Meanwhile, revenue amounted to ¥37.771 billion, up 33.6% year on year, due to increases in maintenance and repair work on thermal power generation facilities, including work to restart idled thermal power plants to ensure stable electricity supply and demand, as well as progress on hydroelectric power plant and substation construction.」

    Progress in substation construction, together with hydroelectric power plant construction, was identified as a factor behind the increase in revenue.
  11. FY2018-Q1RestatedAnnual report

    「Construction of New and Renovated Substations」

    Although the latest results briefing did not provide a separate description of substation construction, it stated that there were no significant changes to the business activities or major affiliated companies, indicating that the existing construction areas remain unchanged.
  12. FY2017RestatedAnnual report

    「Construction of new and renovated substations」

    Construction of new and renovated substations continues to be identified as a specific construction area.
  13. FY2017-Q3RestatedAnnual report

    「Construction of New and Renovated Substations」

    Construction of new and renovated substations continues to be identified as a specific construction area.
  14. FY2017-Q2First statedAnnual report

    「Construction of New and Renovated Substations」

    Construction of new and renovated substations is identified as a specific construction area.
Moved together

"Decommissioning and safety-related work at nuclear power plants" moved the same way as this thread, in the same document, in 9 of its 14 moves.

999666★123456
  1. ★This thread
  2. 1Decommissioning and safety-related work at nuclear power plants9×
  3. 2Maintenance and Repairs of Power Generation Facilities for a Stable Summer Electricity Supply9×
  4. 3Expansion of Renewable Energy-Related Construction9×
  5. 4Power generation equipment-related work at chemical plants6×
  6. 5Facilities Construction Segment’s Fall from Profit to Loss6×
  7. 6Providing high-value-added services through consultative sales and a one-stop approach6×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Tokyo Energy & Systems's next results are scheduled for 2026-11-05. Read the earnings preview It last moved in the Earnings of 2026-08-06: "Advanced".
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Construction of New and Renovated Substations | TOKYO ENERGY & SYSTEMS INC. (1945) | Komori