Toho Gas (9533) · InitiativeAdvanced

Expansion of the Gas Business Across Wider Areas

First written in FY2016. 3 of 8 entries say "Advanced", first in FY2017-Q2. Latest entry: 2026-03-31.

8entries
11years
1from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2017-Q3 – FY2017RestatedFY2020AdvancedFY2024-Q1 – 2026-03-312016: 220162017: 220172018: 020182019: 120192020: 120202021: 020212022: 020222023: 120232024: 020242025: 020252026: 1
Same theme, other companies
Expansion of the Pipeline Business and Strengthening of Safety and Disaster CountermeasuresA theme 5 companies write about · 1 as a headwind · 4 as a tailwind

0 other companies' latest entry also says "Advanced".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. 2026-03-31AdvancedManagement Planning

    「In fiscal 2026, we will continue to expand the city-gas supply network, roll out the LPG business across a wider area, and advance disaster-prevention and safety measures for both businesses.」

    The Company specifically identified the expansion of the city-gas supply network and the wider-area rollout of the LPG business as continuing initiatives for fiscal 2026.
  2. FY2024-Q1AdvancedAnnual report

    「The South Trunk Line and the Chita–Handa section, a transportation trunk line that had been under planning at the end of the previous consolidated fiscal year, was completed in June 2023.」

    The South Trunk Line and Chita–Handa section, transportation trunk lines related to expanding the gas supply area and improving supply stability, were completed in June 2023.
  3. FY2020RestatedAnnual report

    「The Company also aims to expand the availability of natural gas across wider areas by expanding the pipeline network and developing demand through LNG truck deliveries, while steadily advancing both hardware and software safety and disaster-prevention measures for earthquakes, storms and floods.」

    The policy of expanding operations across wider areas through pipeline-network expansion and LNG truck deliveries remains in place.
  4. FY2019RaisedAnnual report

    「To procure feedstock at low cost and with stability, the Company is diversifying procurement methods and promoting the flexible, efficient operation of receiving terminals. It also aims to expand the availability of natural gas across wider areas by developing demand through pipeline-network expansion and LNG truck deliveries, while steadily advancing safety and disaster-prevention measures, including the renewal of aging facilities and the development of isolation blocks for earthquakes.」

    In addition to expanding the existing pipeline network, the Company has identified demand development through LNG truck deliveries as a means of expanding natural gas operations across wider areas.
  5. FY2017RestatedAnnual report

    「The Company continues to reinforce and extend the city-gas pipeline network, working to improve supply stability and expand service areas toward Gifu and Mie prefectures. It is also strengthening LNG sales and expanding the LPG business by leveraging the region's largest filling and delivery network.」

    The Company continues its expansion across wider areas through reinforcement and extension of the pipeline network, LNG sales, and the LPG filling and delivery network.
  6. FY2017-Q3RestatedAnnual report

    「There were no significant changes in major facilities during the cumulative third quarter of the consolidated fiscal year. The Chita Midorihama Plant BOG reliquefaction facility, which had been under planning at the end of the previous consolidated fiscal year, was completed in June 2016, LNG Tank No. 3 at the Chita Midorihama Plant was completed in July 2016, and the transmission trunk line (the Mie trunk line, between Suzuka and Kawai) was completed in August 2016.」

    The completed transportation trunk lines, comprising the Mie Trunk Line and the Suzuka–Kawage section, remain in place, and there have been no new movements involving major facilities.
  7. FY2017-Q2AdvancedAnnual report

    「At the end of the previous consolidated fiscal year, the Chita Midorihama Plant BOG reliquefaction facility, which had been under planning, was completed in June 2016, LNG Tank No. 3 at the Chita Midorihama Plant was completed in July 2016, and the transmission trunk line (the Mie trunk line, between Suzuka and Kawai) was completed in August 2016.」

    The Mie Trunk Line and the Suzuka–Kawage section, transportation trunk lines related to the expansion of the gas business across wider areas, were completed in August 2016, marking concrete progress on the plan.
  8. FY2016First statedAnnual report

    「In addition to increasing transportation capacity through the construction of trunk pipelines, the Company will improve supply stability and expand its city-gas service areas by extending pipelines toward eastern Gifu Prefecture and northern Mie Prefecture. The Group will also work as an integrated organization to expand sales of LPG, LNG and other products to customers across a wider area.」

    The Company plans to expand its supply area and customer base through trunk-pipeline construction, pipeline extensions, and LPG and LNG sales.
Moved together

"Expansion into new business areas through electricity retailing and smart towns" moved the same way as this thread, in the same document, in 3 of its 8 moves.

332222★123456
  1. ★This thread
  2. 1Expansion into new business areas through electricity retailing and smart towns3×
  3. 2Development and Expansion of a Stable Natural Gas Supply Framework3×
  4. 3Strengthening Technical and On-Site Capabilities and Securing and Developing Talent2×
  5. 4Smart Energy Society, Renewable Energy, and Hydrogen-Related Technologies2×
  6. 5Stable Dividends as a Public Utility Operator2×
  7. 6Deepening Customer Relationships2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Toho Gas's next results are scheduled for 2026-10-29. Read the earnings preview It last moved in the Management Planning of 2026-03-31: "Advanced".