- FY2024-Q3AdvancedAnnual report
「Our bank Minami-Nagareyama Branch Chiba Nagareyama Branch facilities, etc. 308 (308) 324 December 2023 Our bank Funabashi Branch Chiba Funabashi Relocation Branch facilities, etc. 368 Internal funds February 2023 March 2024」
The new construction and relocation of the existing Minami-Nagareyama Branch was completed in December 2023. Meanwhile, planned investment for the Funabashi Branch relocation was changed from ¥394 million to ¥368 million, while the scheduled completion month remains March 2024. - FY2024-Q2Change in scheduled completion month and addition of branch relocation planAnnual report
「Our bank Minami-Nagareyama Branch Chiba Nagareyama Relocation Branch facilities, etc. 219 Internal funds December 2022 December 2023 Funabashi Branch Chiba Funabashi Relocation Branch facilities, etc. 394 Internal funds February 2023 March 2024」
The scheduled completion month for the Minami-Nagareyama Branch was changed from September to December 2023, and a relocation plan for the Funabashi Branch was also disclosed, with planned investment of ¥394 million and completion scheduled for March 2024. - FY2023-Q3AdvancedAnnual report
「Our bank Branch Chiba Nagareyama Branch facilities, etc. 219 - Internal funds December 2022 September 2023 (Note) The above refers to the relocation of an existing branch.」
A new relocation plan for the existing branch in Nagareyama, Chiba, was finalized, with planned investment of ¥219 million, work scheduled to begin in December 2022 and completion scheduled for September 2023. - FY2023-Q2AchievedAnnual report
「Our bank Yachiyo Branch / Hanamigawa Branch Chiba Yachiyo Branch facilities, etc. - 203 (203) July 2022 Edogawadai Consulting Plaza Chiba Nagareyama Branch facilities, etc. - 67 (67) August 2022」
The relocation of the Yachiyo and Hanamigawa branches and the establishment of the Edogawadai Consulting Plaza, which were planned in the previous filing, were completed in July and August 2022, respectively. - FY2022AdvancedAnnual report
「Yachiyo Branch / Hanamigawa Branch Yachiyo, Chiba Relocation Branch facilities, etc. 175 Internal funds March 2022 July 2022 Edogawadai Consulting Plaza Nagareyama, Chiba New establishment Branch facilities, etc. 30 Internal funds April 2022 August 2022」
The branch-network development plan was given concrete form, including the relocation of existing branches and the establishment of the Edogawadai Consulting Plaza. - FY2022-Q3AdvancedAnnual report
「The buildings, building fixtures and structures at the operating branches held by our bank had previously been depreciated over useful lives of 3 to 50 years. However, following the Board of Directors' resolution on 29 December 2021 to relocate the branch, the useful life of the fixed assets related to that branch was shortened and changed on a prospective basis.」
In connection with the resolution to relocate the branch, an accounting change was made to shorten the useful lives of the target branch's fixed assets. A new resolution was added to the branch-network development plan centered on relocating existing branches. - FY2022-Q1AchievedAnnual report
「Our bank Mobara Branch Chiba Mobara Branch facilities, etc. - 308 (308) June 2021 (Note) 1. The above refers to the relocation of an existing branch.」
The relocation of the existing Mobara Branch was completed in June 2021. - FY2020-Q1AchievedAnnual report
「Our bank Ohara Branch Chiba Isumi Branch facilities, etc. - 193 (193) April 2019 (Note) 1. The above refers to the relocation of an existing branch.」
The relocation of the existing Ohara Branch, which the previous filing had scheduled for completion in April 2019, was completed in April 2019. - FY2019-Q3AdvancedAnnual report
「Our bank Ohara Branch Chiba Isumi Branch facilities, etc. 67 - Internal funds February 2019 April 2019 (Note) The above refers to the relocation of an existing branch.」
A new relocation plan for the existing Ohara Branch was finalized, with work scheduled to begin in February 2019 and completion scheduled for April 2019. - FY2018-Q2AchievedAnnual report
「Nishikasai Branch Edogawa, Tokyo Branch facilities, etc. - 429 (429) September 2017」
The planned establishment of the Nishikasai Branch was completed in September 2017. Together with the Otakanomori Branch, which was relocated from an existing site, the branch-network development plan is progressing. - FY2018-Q1AchievedAnnual report
「Otakanomori Branch Nagareyama, Chiba Branch facilities, etc. 1,625 (1,625) 696 (696) June 2017 (Note) 1. The above refers to the relocation of an existing branch.」
The relocation of the existing Otakanomori Branch was completed in June 2017. - FY2017ReframedAnnual report
「Otakanomori Branch Nagareyama, Chiba New construction and relocation 242 March 2017 June 2017 Nishikasai Branch Edogawa, Tokyo New establishment 175 March 2017 September 2017」
Based on the results of relocating and rebuilding existing branches, the company is developing a future branch-network development plan that includes new construction and relocation of branches, new branch openings and upgrades to office equipment. - FY2017-Q3First statedAnnual report
「Our bank Yotsukaido Branch Yotsukaido, Chiba Branch facilities, etc. 555 (555) August 2016 Matsudo Branch Matsudo, Chiba Branch facilities, etc. 741 (741) November 2016」