Seismic Reinforcement Work at Major Business Locations
First written in FY2018-Q1. 1 of 6 entries say "Restated". Latest entry: FY2020.
No other company in this theme has enough history to compare yet.
- FY2020AchievedAnnual report
「The company and its domestic subsidiaries carried out seismic reinforcement work from the standpoint of business continuity under their BCP.」
The seismic reinforcement work at the principal business locations progressed from the planning and implementation stage to the completed stage. - FY2019AdvancedAnnual report
「Filing company and domestic subsidiaries | Principal business locations | — | Semiconductor manufacturing equipment | FPD manufacturing equipment | Common to all operations | Seismic reinforcement work | 2,307 | 655 | Internal funds | October 2017 | March 2020」
For the seismic reinforcement work at the principal business locations, ¥655 million in payments made to date has been reported, and the plan remains scheduled for completion in March 2020. - FY2018Update to the planned investment amountAnnual report
「Filing company and domestic subsidiaries | Principal business locations | — | Semiconductor manufacturing equipment | FPD manufacturing equipment | Common to all operations | Seismic reinforcement work | 4,403 | 357 | Internal funds | October 2017 | March 2020」
For the seismic reinforcement work at the principal business locations, the planned investment has been updated from ¥4,501 million to ¥4,403 million, and ¥357 million in payments made to date has been reported. The scheduled completion date remains March 2020. - FY2018-Q3Update to the planned investment amountAnnual report
「Filing company and domestic subsidiaries | Principal business locations | — | Semiconductor manufacturing equipment | FPD manufacturing equipment | Other | Common to all operations | Seismic reinforcement work | 4,501 | — | Internal funds | October 2017 | March 2020」
For the seismic reinforcement work at the principal business locations, the planned completion date of March 2020 remains unchanged, while the planned investment has been updated to ¥4,501 million. - FY2018-Q2RestatedAnnual report
「Filing company and domestic subsidiaries | Principal business locations | — | Semiconductor manufacturing equipment | FPD manufacturing equipment | Other | Common to all operations | Seismic reinforcement work | 4,744 | — | Internal funds | October 2017 | March 2020」
The plan for seismic reinforcement work at the principal business locations is reiterated, with planned investment of ¥4,744 million and completion scheduled for March 2020. - FY2018-Q1First statedAnnual report
「Filing company and domestic subsidiaries | Principal business locations | — | Semiconductor manufacturing equipment | FPD manufacturing equipment | Common to all operations | Other | Seismic reinforcement work | 4,780 | — | Internal funds | October 2017 | March 2020」
Seismic reinforcement work is planned at the principal business locations of the filing company and its domestic subsidiaries. The planned investment is ¥4,780 million, with work scheduled to begin in October 2017 and be completed in March 2020, funded internally.