Capital Investment to Expand Production Capacity and Streamline Operations

First written in FY2017. 11 of 22 entries say "Restated". Latest entry: FY2027-H1.

22entries
10years
1from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2019-Q3 – FY2020-Q3RestatedFY2023-Q3 – FY2024-Q2AdvancedFY2024 – FY20252017: 120172018: 220182019: 320192020: 420202021: 220212022: 220222023: 220232024: 120242025: 220252026: 32026
Same theme, other companies
Expansion and Rationalization of Manufacturing FacilitiesA theme 446 companies write about · 0 as a headwind · 486 as a tailwind
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 183 companies compared. The sentences above are computed from all 183.Comparing 200 of the theme's 486 threads.
Full recordFilings, disclosures and news, newest first
  1. FY2027-H1RestatedAnnual report

    「There were no newly finalized major projects involving the construction or disposal of facilities during the interim consolidated accounting period.」

    No significant capital investment plans were newly finalized during the interim period, and no major new milestones related to production capacity expansion or rationalization were disclosed.
  2. FY2026Decline in capital expenditures and no major new construction plansAnnual report

    「The Group's capital expenditures, including those of the Company and its consolidated subsidiaries, totaled ¥1,011 million during the consolidated fiscal year. There were no plans for the construction of major facilities.」

    Capital expenditures on production equipment and other assets continued, but the amount decreased from ¥1,161 million in the previous fiscal year to ¥1,011 million. The Company stated that there were no plans for the construction or disposal of major facilities.
  3. 2026-05-14AdvancedResults

    「Net cash used in investing activities was ¥1,100 million, compared with ¥877 million used in the previous consolidated fiscal year. This was mainly attributable to ¥1,049 million in payments for the acquisition of property, plant and equipment and other items.」

    Payments of ¥1,049 million for the acquisition of property, plant and equipment were reported as actual capital investment.
  4. FY2026-H1RestatedAnnual report

    「There were no newly finalized major projects involving the construction or disposal of facilities during the interim consolidated accounting period.」

    The Company stated that there were no newly finalized major projects involving the construction or disposal of facilities during the interim period, and no large-scale new milestones were indicated for production capacity expansion.
  5. FY2025AdvancedAnnual report

    「The Group's capital expenditures, including those of the Company and its consolidated subsidiaries, totaled ¥1,161 million during the consolidated fiscal year.」

    ¥1,161 million was invested mainly in production equipment, dies and jigs for automotive parts. The Company continued to disclose planned completion in September or October 2025 for trunk interior parts manufacturing equipment at the Gifu factory and the North American subsidiary.
  6. FY2024AdvancedAnnual report

    「Company, First Production Department (Mitake, Kani District, Gifu Prefecture), automotive parts, trunk interior parts manufacturing equipment, 383,000, 740, self-financing and borrowings, October 2023, October 2025 / MEIWA INDUSTRY NORTH AMERICA,INC., Lewisburg, Tennessee, United States, automotive parts, trunk interior parts manufacturing equipment, 113,000, 31,734, investment and loan funds from the Company, March 2024, September 2025」

    The Company finalized plans to construct trunk interior parts manufacturing equipment at the Gifu factory and the North American subsidiary. Planned investments are ¥383 million and ¥113 million, respectively, with completion scheduled for September or October 2025.
  7. FY2024-Q2RestatedAnnual report

    「There were no significant changes during the six months ended the second quarter of the current consolidated fiscal year in the construction of new facilities, suspension of operations, major renovations, disposals or sales. ② Plans for the construction and disposal of facilities There were no newly finalized major projects involving the construction or disposal of facilities during the six months ended the second quarter of the current consolidated fiscal year.」

    There were no significant changes in facilities or newly finalized major capital expenditure plans during the quarter, and no new large-scale milestones were indicated for production capacity expansion.
  8. FY2023-Q3RestatedAnnual report

    「There were no significant changes during the nine months ended the third quarter of the current consolidated fiscal year in the construction of new facilities, suspension of operations, major renovations, disposals or sales. There were also no newly finalized major projects involving the construction or disposal of facilities during the nine months ended the third quarter of the current consolidated fiscal year.」

    The Company stated that there had been no significant changes in facilities or newly finalized major capital expenditure plans during the quarter regarding capital expenditures and production capacity expansion.
  9. FY2022Decline in capital expenditures and continuation of North American capital expenditure plansAnnual report

    「The Group's capital expenditures, including those of the Company and its consolidated subsidiaries, totaled ¥769 million during the consolidated fiscal year.」

    Capital expenditures decreased from ¥1,308 million in the previous fiscal year to ¥769 million. Meanwhile, the North American subsidiary disclosed a plan for trunk interior parts manufacturing equipment, scheduled to start in August 2021 and be completed in October 2022, with total planned investment of ¥125.950 million.
  10. FY2022-Q3RestatedAnnual report

    「① Status of major facilities There were no significant changes during the nine months ended the third quarter of the current consolidated fiscal year in the construction of new facilities, suspension of operations, major renovations, disposals or sales. ② Plans for the construction and disposal of facilities There were no newly finalized major projects involving the construction or disposal of facilities during the nine months ended the third quarter of the current consolidated fiscal year.」

    There were no significant changes in facilities or newly finalized major capital expenditure plans during the quarter, and no new large-scale milestones were indicated for production capacity expansion.
  11. FY2022-Q2RestatedAnnual report

    「① Status of major facilities There were no significant changes during the six months ended the second quarter of the current consolidated fiscal year in the construction of new facilities, suspension of operations, major renovations, disposals or sales. ② Plans for the construction and disposal of facilities There were no newly finalized major projects involving the construction or disposal of facilities during the six months ended the second quarter of the current consolidated fiscal year.」

    There were no significant changes in facilities or newly finalized major capital expenditure plans during the quarter, and no new large-scale milestones were indicated in the policy for capital expenditures and production capacity expansion.
  12. FY2021SoftenedAnnual report

    「The Group's capital expenditures, including those of the Company and its consolidated subsidiaries, totaled ¥1,308 million during the consolidated fiscal year.」

    Capital expenditures on production equipment, dies and jigs totaled ¥1,308 million, down from ¥1,384 million in the previous fiscal year. The Company stated that there were no plans for the construction or disposal of major facilities.
  13. FY2021-Q2RestatedAnnual report

    「Net cash used in investing activities was ¥766 million, compared with ¥688 million used in the same quarter of the previous year. This was mainly due to ¥818 million in payments for the acquisition of property, plant and equipment, among other factors.」

    The Company spent ¥818 million on the acquisition of property, plant and equipment during the six months ended the second quarter. At the same time, it stated that there had been no significant changes in the construction of new facilities, suspension of operations, major renovations, disposals or sales, and no newly finalized major capital expenditure plans.
  14. FY2021-Q1SoftenedAnnual report

    「There were no newly finalized major projects involving the construction or disposal of facilities during the first quarter of the current consolidated fiscal year.」

    The previous fiscal year included disclosures on investments in production equipment and capital expenditure plans, but there were no newly finalized major capital expenditure plans during the quarter. The Company is also working to restrain capital expenditures amid the infectious disease outbreak.
  15. FY2020AdvancedAnnual report

    「The Group's capital expenditures totaled ¥1,384 million during the consolidated fiscal year.」

    ¥1,384 million was invested mainly in production equipment, dies and jigs for automotive parts. The Company also planned to complete ¥115.257 million of equipment for manufacturing trunk interior parts at the Foshan factory in August 2020 and ¥232.070 million of similar equipment at the Gifu factory in April 2021.
  16. FY2020-Q3RestatedAnnual report

    「There were no significant changes during the nine months ended the third quarter of the current consolidated fiscal year in the construction of new facilities, suspension of operations, major renovations, disposals or sales.」

    The Company stated that there had been no significant changes in facilities during the quarter regarding capital expenditures and production capacity expansion, and no newly finalized major capital expenditure plans.
  17. FY2020-Q2RestatedAnnual report

    「Net cash used in investing activities was ¥688 million, compared with ¥1,194 million used in the same quarter of the previous year. This was mainly due to ¥672 million in payments for the acquisition of property, plant and equipment, among other factors.」

    The Company spent ¥672 million on the acquisition of property, plant and equipment, while stating that there had been no significant changes in the construction of new facilities, suspension of operations, major renovations, disposals or sales, and no newly finalized major capital expenditure plans.
  18. FY2020-Q1RestatedAnnual report

    「There were no significant changes during the first quarter of the current consolidated fiscal year in the construction of new facilities, suspension of operations, major renovations, disposals or sales.」

    The Company stated that there had been no significant changes in facilities or new large-scale plans during the quarter regarding capital expenditures and production capacity expansion.
  19. FY2019-Q3RestatedAnnual report

    「This was mainly due to increases of ¥148 million in construction in progress and ¥101 million in machinery, equipment and vehicles, net, among other factors.」

    Among fixed assets, construction in progress and machinery, equipment and vehicles increased. At the same time, the Company stated that there had been no significant changes in major facilities and no newly finalized major capital expenditure plans, with no new large-scale milestones indicated.
  20. FY2019-Q2AdvancedAnnual report

    「Net cash used in investing activities was ¥1,194 million, compared with ¥1,017 million used in the same quarter of the previous year. This was mainly due to ¥1,048 million in payments for the acquisition of property, plant and equipment and ¥341 million in payments for the acquisition of investment securities.」

    The Company spent ¥1,048 million on the acquisition of property, plant and equipment during the six months ended the second quarter. It stated that there had been no significant changes in major facilities and no newly finalized major capital expenditure plans.
  21. FY2018AdvancedAnnual report

    「The Group's capital expenditures, including those of the Company and its consolidated subsidiaries, totaled ¥2,081 million during the consolidated fiscal year. They primarily comprised the acquisition of production equipment, dies and jigs for producing made-to-order products at factories, as well as factory expansions at overseas subsidiaries, and were undertaken to expand production capacity, improve efficiency and replace existing facilities.」

    Capital expenditures increased from ¥1,752 million in the previous fiscal year to ¥2,081 million, with progress made on production equipment for made-to-order products, dies and jigs, and factory expansions at overseas subsidiaries.
  22. FY2017First statedAnnual report

    「The Group's capital expenditures, including those of the Company and its consolidated subsidiaries, totaled ¥1,752 million. By segment, these expenditures were as follows. They primarily comprised the acquisition of production equipment, dies and jigs for producing made-to-order products at factories, as well as factory expansions at overseas subsidiaries, and were undertaken to expand production capacity, improve efficiency and replace existing facilities.」

    ¥1,752 million was invested in production equipment for made-to-order products, dies and jigs, and factory expansions at overseas subsidiaries. The Company also disclosed equipment plans for the expansion of buildings and production equipment at the Foshan factory and the North American subsidiary from 2017 to 2018.
Moved together

"Raw Material Price Volatility Driven by Crude Oil Prices and Foreign Exchange Rates" moved the same way as this thread, in the same document, in 5 of its 22 moves.

554332★123456
  1. ★This thread
  2. 1Raw Material Price Volatility Driven by Crude Oil Prices and Foreign Exchange Rates5×
  3. 2Foreign Exchange Movements Related to the Translation of Overseas Subsidiaries’ Financial Statements5×
  4. 3Sales Dependence on Toyota Motor Group4×
  5. 4Achieving the Medium-Term Management Plan “GT300”3×
  6. 5Strengthening the business base in China, ASEAN and North America3×
  7. 6Domestic automobile parts structure capable of generating profit even under production cuts2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Meiwa Industry yet. It last moved in the Results of 2026-05-14: "Advanced".