Komori
Gmb (7214) · InitiativeUpdated capital investment plan and addition of a new US operating site

Investment plans for capacity expansion, rationalisation and R&D equipment at domestic and overseas operating sites

First written in FY2017. 4 of 18 entries say "Restated". Latest entry: FY2026.

18entries
10years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseOtherFY2017 – FY2023-Q2RaisedFY2024-Q3 – FY2026-H12017: 320172018: 220182019: 120192020: 220202021: 120212022: 220222023: 320232024: 220242025: 120252026: 12026
Same theme, other companies

This thread is not in a theme yet. When the same subject shows up in other companies' filings, you can compare them here.

Full recordFilings, disclosures and news, newest first
  1. FY2026Updated capital investment plan and addition of a new US operating siteAnnual report

    「The following were the plans for the construction and renovation of major facilities as of 31 March 2026.」

    The total investment planned for key facilities was ¥5,300 million, including ¥950 million for production expansion facilities at GMB USA ALABAMA INC. in the United States, ¥2,550 million in South Korea and ¥550 million in India, among others, primarily during 2026.
  2. FY2026-H1Increase in the South Korean capital investment planAnnual report

    「(Before the change) 2,250 (After the change) 3,000 1,554 Internal funds and borrowings January 2025 December 2025」

    For GMB KOREA CORP.'s First Plant, Second Plant and Seosan Plant, the total planned investment in production expansion, rationalisation, research and development, and measurement facilities was increased from ¥2,250 million to ¥3,000 million. Payments made were stated as ¥1,554 million.
  3. FY2025-H1Increase in the South Korean capital investment planAnnual report

    「(Before the change) 4,000 (After the change) 5,000 2,173 Internal funds and borrowings January 2024 December 2024」

    For GMB KOREA CORP.'s First Plant, Second Plant and Seosan Plant, the total planned investment in the expansion and renewal of production expansion and rationalisation facilities, research and development facilities, measurement facilities and other facilities was increased from ¥4,000 million to ¥5,000 million. Payments made were stated as ¥2,173 million.
  4. FY2024-Q3AdvancedAnnual report

    「(Before the change) 1,950 (After the change) 2,200 2,184 Internal funds and borrowings January 2023 December 2023」

    Payments made reached ¥2,184 million against GMB KOREA CORP.'s total planned investment of ¥2,200 million in production expansion, rationalisation and other facilities, bringing the increased plan to nearly the implementation stage.
  5. FY2024-Q2Increase in the South Korean capital investment planAnnual report

    「(Before the change) 1,950 (After the change) 2,200 1,113 Internal funds and borrowings January 2023 December 2023」

    For GMB KOREA CORP.'s First Plant, Second Plant and Seosan Plant, the total planned investment in the expansion and renewal of production expansion and rationalisation facilities, and the construction of new research and development and measurement facilities, changed from ¥1,950 million to ¥2,200 million. Payments made were ¥1,113 million, and completion was scheduled for December 2023.
  6. FY2023Updates to the capital investment planAnnual report

    「The following were the plans for the construction and renovation of major facilities as of 31 March 2023.」

    The total investment planned for key facilities in fiscal 2023 was ¥3,950 million: ¥550 million in Japan, ¥2,350 million in South Korea, ¥450 million in China, ¥150 million in Thailand and ¥450 million in Europe, among others. The investments were planned for implementation from January or April through December 2023 or through March 2024.
  7. FY2023-Q3AdvancedAnnual report

    「(Before the change) 1,400 (After the change) 3,000 1,737 Internal funds and borrowings January 2022 December 2022」

    For GMB KOREA CORP.'s First Plant, Second Plant and Seosan Plant, payments made reached ¥1,737 million against the total planned investment of ¥3,000 million in production expansion, rationalisation and other facilities, indicating progress in implementing the plan after the increase.
  8. FY2023-Q2Increase in the South Korean capital investment planAnnual report

    「(Before the change) 1,400 (After the change) 3,000 1,182 Internal funds and borrowings January 2022 December 2022」

    For GMB KOREA CORP.'s First Plant, Second Plant and Seosan Plant, the total planned investment in production expansion, rationalisation and other facilities changed from ¥1,400 million to ¥3,000 million.
  9. FY2022Updates to the capital investment planAnnual report

    「The following were the plans for the construction and renovation of major facilities as of 31 March 2022.」

    The total investment planned for key facilities in fiscal 2022 was ¥3,350 million, including ¥500 million in Japan, ¥1,550 million in South Korea, ¥750 million in China, ¥350 million in Thailand and ¥200 million in Europe, among others. The investments were planned for implementation from January through December 2022 or through March 2023.
  10. FY2021Updates to the capital investment planAnnual report

    「The following were the plans for the construction and renovation of major facilities as of 31 March 2021.」

    The total capital investment planned for fiscal 2021 was ¥4,250 million: ¥800 million in Japan, ¥1,800 million in South Korea, ¥650 million in Europe, ¥600 million in China and ¥400 million in Thailand, among others. The investments were planned mainly for production expansion, rationalisation, maintenance and research and development facilities from January through December 2021 or through March 2022.
  11. FY2020Updates to the capital investment planAnnual report

    「The following were the plans for the construction and refurbishment of major facilities as of 31 March 2020.」

    The total investment planned for key facilities in fiscal 2020 was ¥3,350 million to ¥4,300 million, primarily from January through December 2020, covering production expansion, rationalisation and research and development facilities in South Korea, China, Thailand and Europe, among others.
  12. FY2020-Q3RestatedAnnual report

    「There were no material changes during the nine months ended December 31 to the business and financial issues that the Group needs to address as a priority.」

    It was explicitly stated that there had been no material changes to issues relating to investment plans for capacity expansion, rationalisation and R&D equipment at domestic and overseas operating sites.
  13. FY2019Updates to the capital investment planAnnual report

    「The following were the plans for the construction and refurbishment of major facilities as of 31 March 2019.」

    Major facility plans totalled ¥4.95 billion: ¥700 million for the Company, ¥2 billion for Korea, ¥800 million for China, ¥300 million for Thailand and ¥1.15 billion for Europe, among others. The projects were planned to be carried out mainly from January to December 2019 or through March 2020.
  14. FY2018Updates to the capital investment planAnnual report

    「The following were the plans for the construction and refurbishment of major facilities as of 31 March 2018.」

    The fiscal 2018 facility plan totalled ¥4.6 billion: ¥750 million for the Company, ¥2.45 billion for Korea, ¥1.15 billion for China, ¥100 million for Thailand and ¥150 million for Europe. The plan primarily covered capacity expansion, rationalisation and R&D equipment projects to be carried out from January to December 2018 or through March 2019.
  15. FY2018-Q3RestatedAnnual report

    「There were no material changes during the nine months ended December 31 to the business and financial issues that the Group needs to address as a priority.」

    It was explicitly stated that there had been no material changes to issues relating to investment plans for capacity expansion, rationalisation and R&D equipment at domestic and overseas operating sites.
  16. FY2018-Q2RestatedAnnual report

    「There were no material changes during the second quarter of the current consolidated cumulative period to the issues that the Group needs to address.」

    It was explicitly stated that there had been no material changes to issues relating to investment plans for capacity expansion, rationalisation and R&D equipment at domestic and overseas operating sites.
  17. FY2018-Q1RestatedAnnual report

    「There have been no material changes in the issues that the Group must address during the cumulative consolidated first quarter.」

    It was explicitly stated that there had been no material changes to issues relating to investment plans for capacity expansion, rationalisation and R&D equipment at domestic and overseas operating sites.
  18. FY2017First statedAnnual report

    「The following were the plans for the construction and refurbishment of major facilities as of 31 March 2017.」

    For fiscal 2017, major facility plans totalled ¥3.8 billion: ¥500 million for the Company, ¥1.7 billion for GMB KOREA CORP., ¥350 million for AG TECH CORP., ¥900 million for the Chinese companies, ¥150 million for Thailand and ¥200 million for Romania. Most projects were scheduled to begin in January or April 2017 and be completed in December 2017 or March 2018, covering capacity expansion, rationalisation and R&D equipment.
Moved together

"Continued sales of new-vehicle parts from bases in China and Europe" moved the same way as this thread, in the same document, in 4 of its 18 moves.

443333★123456
  1. ★This thread
  2. 1Continued sales of new-vehicle parts from bases in China and Europe4×
  3. 2Increase in sales of engine components, led by water pumps4×
  4. 3China segment revenue and profit growth3×
  5. 4Higher revenue and earnings in the Korea segment driven by electric water pumps and other products3×
  6. 5Establishment of GMB USA INC. and production of electric water pumps for the US market3×
  7. 6Decision to pay an interim dividend of ¥20 per share3×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Gmb's next results are scheduled for 2026-11-13. Read the earnings preview
News