How it moved
ProgressHeldSoftenedWorseFirst statedFY2020WorsenedFY2022-Q1 – FY2023OtherFY2024 – FY2025-H12020: 120202021: 220212022: 420222023: 420232024: 320242025: 220252026: 32026
Same theme, other companies
Earnings pressure from compound cost inflation and supply constraintsA theme 13 companies write about · 13 as a headwind · 0 as a tailwind

Aichi moved to the "Worse" side of this theme in 2021, 1 year before the typical company in this theme (2022).

The whole theme swung hardest in 2022: 8 of 9 companies on the "Worse" side.

5 other companies' latest entry also says "Restated".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. 2026-07-30RestatedEarnings

    「The business environment surrounding the Group remained challenging, as increases in labor costs and parts prices continued.」

    The continued increases in labor costs and parts prices reiterate procurement and cost inflation risks.
  2. FY2026WorsenedAnnual report

    「There is no shortage of adverse factors, including shortages of imported raw materials such as crude oil and naphtha and higher fuel costs associated with rising tensions in the Middle East, global supply chain disruptions resulting from continued deterioration in Japan-China relations, uncertainty surrounding U.S. trade policy, worsening labor shortages, higher interest rates, sharp exchange-rate fluctuations, and increases in various costs, including labor costs.」

    The company specifies shortages of raw materials and higher fuel costs, supply chain disruptions related to Japan-China relations, labor shortages, interest-rate and foreign-exchange risks, and increases in various costs as new or continuing procurement and supply risks.
  3. 2026-04-24RestatedEarnings

    「The business environment surrounding the Group remained challenging, as increases in labor costs and parts prices continued.」

    The continued increases in labor costs and parts prices reiterate procurement and cost inflation risks.
  4. FY2026-H1RestatedAnnual report

    「The operating environment remained difficult as raw material prices stayed high and labor costs and component prices continued to rise.」

    The company continues to identify procurement and cost-increase risks, citing persistently high raw material prices, rising labor costs and continued increases in component prices.
  5. FY2025MitigatedAnnual report

    「Although we worked to establish appropriate price levels, the operating environment remained extremely difficult as the effects of higher labor costs and persistently high raw material prices and energy costs continued. Specialty-vehicle sales exceeded those of the previous consolidated fiscal year, partly because the certification issue involving the chassis for truck-mounted aerial work platforms, which arose in the previous consolidated fiscal year, had been resolved.」

    The company states that the chassis certification issue had been resolved and contributed to higher specialty-vehicle sales. Meanwhile, chassis supply challenges and persistently high labor, raw material and energy costs continued.
  6. FY2025-H1Resolution of the chassis certification issue and continuing supply challengesAnnual report

    「The operating environment remained difficult as chassis supply challenges continued, while procurement costs rose due to higher wages and energy costs, among other factors. Specialty-vehicle sales increased from the previous fiscal year, partly because sales carried over from the previous fiscal year were recognized following resolution of the certification issue involving the chassis for truck-mounted aerial work platforms.」

    The company states that chassis supply challenges and higher procurement costs continued, while the certification issue involving the chassis for truck-mounted aerial work platforms was resolved and sales carried over from the previous fiscal year contributed to higher specialty-vehicle sales.
  7. FY2024Updated component procurement risk improvements and delays in chassis certificationAnnual report

    「Although the component procurement risks that had emerged during the current consolidated fiscal year had been almost resolved, certification of the chassis for our core truck-mounted aerial work platforms was delayed in the fourth quarter, while the effects of persistently high raw material prices and energy costs also continued.」

    Although the component procurement risks had been almost resolved, certification of the chassis for truck-mounted aerial work platforms was newly delayed, while raw material and energy costs remained persistently high.
  8. FY2024-Q3MitigatedAnnual report

    「Although the component procurement risks that had emerged in the previous fiscal year had been almost resolved, the operating environment remained difficult as the effects of persistently high raw material prices and energy costs continued.」

    The company states that the component procurement risks that had emerged in the previous fiscal year had been almost resolved, while raw material prices and energy costs remained persistently high.
  9. FY2024-Q2MitigatedAnnual report

    「Although the component procurement risks that had emerged in the previous fiscal year had been almost resolved, the operating environment remained difficult as the effects of persistently high raw material prices and energy costs continued. Sales of specialty vehicles declined year on year due to supply delays associated with truck manufacturers' model changes, among other factors.」

    The company states that the component procurement risks that had emerged in the previous fiscal year had been almost resolved, while persistently high raw material prices and energy costs and supply delays associated with truck manufacturers' model changes continued.
  10. FY2024-Q1Component procurement risks improved, but chassis supply constraints continuedAnnual report

    「Although the component procurement risks that had emerged in the previous fiscal year showed signs of improvement, the operating environment remained difficult as raw material prices continued to rise. Sales of specialty vehicles declined from the previous fiscal year due to chassis supply constraints associated with truck manufacturers' model changes, among other factors.」

    Although the component procurement risks that had emerged in the previous fiscal year showed signs of improvement, persistently high raw material prices and chassis supply constraints associated with truck manufacturers' model changes continued, resulting in lower specialty-vehicle sales.
  11. FY2023WorsenedAnnual report

    「Amid continuing disruption in the procurement of many components, including semiconductor-related components, which had emerged as an issue in the previous fiscal year, a supply problem also arose involving the chassis for our core truck-mounted aerial work platforms, resulting in an extremely difficult operating environment amid strong headwinds.」

    The company states that, amid continuing disruption in component procurement, a supply problem also arose involving the chassis for truck-mounted aerial work platforms, providing further detail on supply chain risks.
  12. FY2023-Q3WorsenedAnnual report

    「In addition to sharp increases in raw material prices, particularly steel and fats and oils, utility costs, including electricity and gas, also rose substantially. Although we implemented cost-improvement and selling-price improvement initiatives to absorb these increases, we were unable to absorb them sufficiently during the nine-month period of the current consolidated fiscal year, resulting in lower profit year on year.」

    In addition to soaring raw material prices, utility costs such as electricity and gas rose significantly. Although the company implemented cost-improvement and selling-price improvement initiatives, it was unable to fully absorb the higher costs, resulting in lower profit.
  13. FY2023-Q2MaterialisedAnnual report

    「As for profit, we worked to reflect the sharp rise in costs, including soaring steel and raw material prices, in selling prices, but were unable to absorb the increase sufficiently during the period. In addition, delays in the normalization of the supply chain and disruptions in the supply of truck chassis resulted in difficult conditions.」

    The company states that it was unable to fully pass higher costs caused by soaring steel and raw material prices on to selling prices, while delays in supply chain normalization and disruptions in truck chassis supplies also occurred, causing procurement and supply chain risks to affect profit.
  14. FY2023-Q1MaterialisedAnnual report

    「However, difficult conditions continued, including further increases in crude oil and raw material prices due to the prolonged situation in Ukraine, disruptions in parts supplies caused by supply chain turmoil resulting from the lockdown in Shanghai, and rising prices accompanying the rapid depreciation of the yen.」

    Further increases in crude oil and raw material prices, delays in component supplies caused by the Shanghai lockdown, and supply chain disruptions are described as part of the actual operating environment, indicating that procurement and supply chain risks have materialized.
  15. FY2022MaterialisedAnnual report

    「The domestic and overseas economies remained uncertain amid global supply chain disruptions, including prolonged semiconductor shortages and delays in component supplies that reduced or halted factory operations, higher costs from rising crude oil and raw material prices, and geopolitical risks related to the situation in Ukraine and elsewhere.」

    Reduced or suspended factory operations caused by delays in component supplies and higher costs from rising raw material prices are described as part of the actual operating environment, indicating that supply chain risks have materialized.
  16. FY2022-Q3MaterialisedAnnual report

    「However, the impact on production from disruptions in the component supply network, which had been a concern since the second quarter of the consolidated fiscal period, has now materialized.」

    The company states that disruptions in the component supply network, which had been a concern since the previous quarter, have materialized as a specific impact on production.
  17. FY2022-Q2WorsenedAnnual report

    「Looking ahead, although a recovery in economic activity is expected as the COVID-19 vaccination rate rises and the economy adapts to living with the virus, concerns remain, including cost increases resulting from shortages of semiconductors and higher crude oil and raw material prices, as well as reduced or suspended plant operations due to disruptions in parts supplies from Southeast Asia.」

    In addition to higher costs from semiconductor shortages and rising crude oil and raw material prices, the company specifically describes reduced or suspended factory operations caused by disruptions in component supplies from Southeast Asia, adding procurement and supply chain risks as adverse factors.
  18. FY2022-Q1WorsenedAnnual report

    「Looking ahead, although a recovery in economic conditions is expected as COVID-19 vaccinations become widespread and take effect, concerns remain, including cost increases resulting from semiconductor shortages and higher raw material prices.」

    The company specifically describes higher costs caused by semiconductor shortages and rising raw material prices as factors creating uncertainty about the outlook for the current quarter.
  19. FY2020First statedAnnual report

    「These sharp price increases and procurement difficulties will raise the manufacturing cost of products. Although our group is working to reflect these increases in selling prices, it may not always be able to pass the full increase in manufacturing costs on to customers. In addition, production may be reduced and manufacturing costs may rise because of supply chain disruptions, which could affect the group's operating results and financial position.」

    The company explicitly identifies for the first time the risk that soaring raw material and component prices, procurement difficulties and supply chain disruptions could affect operating results and financial position through higher costs and reduced production.
Moved together

"Uncertainty over the Outlook Due to an Emerging-Market Slowdown, Yen Appreciation and Falling Crude Oil Prices" moved the same way as this thread, in the same document, in 9 of its 19 moves.

976443★123456
  1. ★This thread
  2. 1Uncertainty over the Outlook Due to an Emerging-Market Slowdown, Yen Appreciation and Falling Crude Oil Prices9×
  3. 2Substantial increases in revenue, operating profit, and net income7×
  4. 3Dependence on demand from the electrical and telecommunications construction and rental industries6×
  5. 4Impairment Losses Due to Declining Profitability of Idle Land and Business-Use Land4×
  6. 5Impact of COVID-19 on Business Activities and Supply Chains4×
  7. 6Expansion of After-Sales Services and 24-Hour Contact System3×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Aichi's next results are scheduled for 2026-10-29. Read the earnings preview It last moved in the Earnings of 2026-07-30: "Restated".
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Rising Prices for Raw Materials and Components, Procurement Difficulties, and Supply Chain Disruptions | AICHI CORPORATION (6345) | Komori