Construction of a new Nishinippon plant in Miyakonojo, Miyazaki Prefecture
First written in FY2024. 5 of 9 entries say "Advanced", first in FY2025-H1. Latest entry: FY2027-H1.
No other company in this theme has enough history to compare yet.
- FY2027-H1RestatedAnnual report
「Construction of the new Kyushu Factory in Miyakonojo, Miyazaki Prefecture, which will serve as a new supply base intended to strengthen the production system in western Japan, is progressing smoothly, and the Company aims to complete construction as scheduled in December 2026.」
It reconfirmed its plan for construction of the new Kyushu Factory in Miyakonojo, Miyazaki Prefecture, to progress smoothly and reach completion in December 2026. - 2026-10-14RestatedEarnings
「Construction of the new Kyushu Factory in Miyakonojo, Miyazaki Prefecture, which will serve as a new supply base intended to strengthen the production system in western Japan, is progressing smoothly, and the Company aims to complete construction as scheduled in December 2026.」
九州新工場の建設が順調に進捗し、2026年12月竣工予定を再確認している。 - FY2026AdvancedAnnual report
「Kyushu Plant (Miyakonojo, Miyazaki Prefecture) Food business Food ingredient processing 6,606 3,576 Subsidies, borrowings, etc. September 2025 December 2026 1,300t/month」
The Company has disclosed the capital investment plan for the new Kyushu plant in Miyakonojo, Miyazaki Prefecture, specifying total planned investment of ¥6,606 million, ¥3,576 million already paid, scheduled completion in December 2026, and production capacity of 1,300 tonnes per month. - FY2026-H1RestatedAnnual report
「At our production plants, the heart of our business as a food manufacturer, we are proceeding with construction of a new Kyushu plant in Miyakonojo, Miyazaki Prefecture, as a new supply base, with the aim of strengthening production capacity in the West Japan region in addition to fully restoring the Kanto No. 1 Plant, and are targeting completion in December 2026.」
The Company has reconfirmed its plan to proceed with construction of the new Kyushu plant in Miyakonojo, Miyazaki Prefecture, with completion targeted for December 2026. - FY2025AdvancedAnnual report
「Eat-and Foods Co., Ltd. Kyushu Plant (Miyakonojo, Miyazaki Prefecture) Food business Food ingredient processing 6,700 116 Subsidies, borrowings, etc. August 2025 December 2026 1,300t/month」
The plan for the new Kyushu plant in Miyakonojo, Miyazaki Prefecture, specifies total planned investment of ¥6.7 billion, ¥116 million already paid, construction beginning in August 2025 and scheduled for completion in December 2026, and production capacity of 1,300 tonnes per month after completion. - FY2025-H1AdvancedAnnual report
「In addition, with the aim of strengthening its production capacity in the West Japan region, the Company has finalized the acquisition of Plot G in the Sakuragi District of the Miyakonojo Interchange Industrial Park, with a site area of 8,259.88㎡. This will enable the Company to proceed with construction of a new plant in Miyakonojo, Miyazaki Prefecture, as a new supply base for the West Japan region, with operations scheduled to begin in 2026.」
For the new plant project in Miyakonojo, Miyazaki Prefecture, the acquisition of the site at the Miyakonojo Interchange Industrial Park has been finalized. Based on the 8,259.88㎡ site, the project has advanced to the stage of targeting the start of operations in 2026. - FY2024First statedAnnual report
「We are proceeding with construction of a new plant in Miyakonojo, Miyazaki Prefecture, as a new supply base for the West Japan region, with operations scheduled to begin in 2026.」
The Company has for the first time described a plan to construct a new plant in Miyakonojo, Miyazaki Prefecture, as a new supply base for the West Japan region, with operations scheduled to begin in 2026. The site covers 8,259.88㎡, and the Company has obtained priority negotiating rights for a plot in an industrial park.