Construction of new production facilities for butter and other products at the Isobunai Plant
First written in FY2018-Q2. 3 of 5 entries say "Advanced", first in FY2019. Latest entry: FY2021.
No other company in this theme has enough history to compare yet.
- FY2021AdvancedAnnual report
「The company made major investments mainly in butter production facilities, including the construction of a new building, at its Isobunai Plant.」
Capital expenditure in the dairy products segment was ¥16,521 million, up 38.6% year on year, as major investments in butter production facilities and other equipment at the Isobunai Plant progressed. - FY2020AdvancedAnnual report
「Isobunai Plant | Hokkaido | Shibecha, Kawakami District | Dairy products | Production facilities for butter and other products | 20,790 | 7,808 | Internal funds and borrowings | February 2018 | September 2020 | Raw milk processing capacity: 210,000 t/year」
For the Isobunai Plant capital expenditure plan, payments made to date increased from ¥1,662 million to ¥7,808 million, and the plan scheduled for completion in September 2020 is progressing. - FY2019AdvancedAnnual report
「Isobunai Plant | Hokkaido | Shibecha, Kawakami District | Dairy products | Production facilities for butter and other products | 20,790 | 1,662 | Internal funds and borrowings | February 2018 | September 2020 | Raw milk processing capacity: 210,000 t/year」
For the production facilities for butter and other products at the Isobunai Plant, the company disclosed ¥1,662 million in payments made to date and continues to pursue the plan for completion in September 2020 and raw milk processing capacity of 210,000 t/year. - FY2018-Q3RestatedAnnual report
「Isobunai Plant | Production facilities for butter and other products | 20,790 | – | Internal funds and borrowings | February 2018 | September 2020 | Raw milk processing capacity: 210,000 t/year」
The company continues to disclose a plan for production facilities for butter and other products at the Isobunai Plant, with a total investment of ¥20,790 million, work commencing in February 2018, completion in September 2020 and raw milk processing capacity of 210,000 t/year. - FY2018-Q2First statedAnnual report
「Isobunai Plant Butter and other production facilities Total: ¥20,790 million Commencement: February 2018 Completion: September 2020 Raw milk processing capacity: 210,000 t/year」
As a major capital expenditure plan newly finalized during the current cumulative second quarter, the company has disclosed a plan to construct new production facilities for butter and other products at the Isobunai Plant, invest a total of ¥20,790 million and add raw milk processing capacity of 210,000 t/year.