How it moved
ProgressHeldSoftenedWorseFirst statedFY2020AdvancedFY2021 – FY20222020: 120202021: 120212022: 120222023: 020232024: 020242025: 020252026: 12026
Same theme, other companies
Fire-Resistance Technology and Ministerial Certification for Timber Buildings Using λ-WOODA theme 2 companies write about · 0 as a headwind · 2 as a tailwind

0 other companies' latest entry also says "Cited as achieved".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. 2026-05-27Cited as achievedGeneral Meetings of Shareholders

    「By introducing the Company’s new technologies, including the “Environmentally Considerate λ-WOOD II 1.5-Hour Fire-Resistant Beam,” “Dress Wood,” and “CLT 1- and 2-Hour Fire-Resistant Floors,” the project will realize a timber-and-steel hybrid office building with high fire-resistance performance.」

    Cites the λ-WOOD II fire-resistance technology as having been introduced in an actual completed construction project.
  2. FY2022AchievedAnnual report

    「今回ですべての主要構造部の耐火認定を取得したことにより、15階以上の木造建築を純木造で建築できるようになった。」

    断熱耐火λ-WOODについて、柱・梁・床・壁の主要構造部で1~3時間の耐火認定を取得し、15階以上の高層建築物を純木造で建築できる状態に到達した。今後は事業化を含めた採用拡大を検討している。
  3. FY2021AdvancedAnnual report

    「今回大臣認定を取得した、1~3時間の集成材柱の特徴として、荷重支持部(柱)の周囲に設置する「燃え止まり層」に、普通硬質せっこうボードと断熱耐火パネルを積層することにより、その部分の厚さを薄くした。…今般実施工として、「断熱耐火λ-WOOD(柱)」を現在施工中の当社福井本店の建替工事に採用している。」

    λ-WOODについて、従来のCLT壁・床に加え、柱の1~3時間耐火構造の大臣認定を取得し、実工事にも採用した。
  4. FY2020First statedAnnual report

    「By obtaining Minister of Land, Infrastructure, Transport and Tourism certifications for 1-hour and 2-hour fire-resistant structures for CLT floors, CLT floors and walls can now be used from the top floor down to the fourth floor in 1-hour fire-resistant structures and from the top floor down to all floors in 2-hour fire-resistant structures.」

    The Company obtained Minister of Land, Infrastructure, Transport and Tourism certifications for 1-hour and 2-hour fire-resistant CLT floors and aims to obtain certification for columns and beams within 1 year.
Moved together

"Accelerated Bridge Deck Renewal Using the Kotter Deck Method" moved the same way as this thread, in the same document, in 2 of its 4 moves.

222222★123456
  1. ★This thread
  2. 1Accelerated Bridge Deck Renewal Using the Kotter Deck Method2×
  3. 2Strengthening oversight and auditing by outside directors and outside Audit & Supervisory Board members2×
  4. 3Strengthening the renewable energy business, including biomass power generation2×
  5. 4Strengthening overseas operations, centered on Taiwan2×
  6. 5Creating new revenue streams outside construction contracting and making equity investments2×
  7. 6Collaboration and creation of synergies through the capital and business alliance with Sumitomo Forestry Co.,Ltd.2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next