Development of infrastructure facilities through the construction of parking lots, employee dormitories and company housing
First written in FY2018-Q3. 4 of 6 entries say "Advanced", first in FY2018. Latest entry: FY2026-H1.
No other company in this theme has enough history to compare yet.
- FY2026-H1Changes in investment amount and scheduled completionAnnual report
「The total planned investment was changed from ¥11,429 million to ¥12,859 million. The scheduled completion date was changed from May 2026 to March 2027.」
For the Kanagawa Techno Station, planned investment was increased to ¥12,859 million, and the scheduled completion date was postponed to March 2027. - FY2020-Q3AdvancedAnnual report
「Of the major facilities that were under construction at the end of the previous consolidated fiscal year, those completed during the cumulative third-quarter consolidated period were as follows.」
The parking facility at the Shinagawa Konan Building was completed in October 2019 and recorded as a completed facility with total investment of ¥4,810 million. The Hirakata Asphalt Plant was also completed in August 2019. - FY2019AdvancedAnnual report
「The planned investment for the Shinagawa Konan Building was changed from ¥4,340 million to ¥4,802 million, and the scheduled completion date was changed from July 2019 to October 2019.」
Updated the planned investment and scheduled completion date for the Shinagawa Konan Building, providing greater detail on the plan. - FY2019-Q2AdvancedAnnual report
「Of the major facilities that were under construction at the end of the previous consolidated fiscal year, those completed during the cumulative second-quarter consolidated period were as follows.」
The facilities list shows that the Daei Seisakusho head office and the Hiyoshi Dormitory were completed in July 2018. - FY2018AdvancedAnnual report
「The scheduled completion date for the Shinagawa Konan Building was changed from May 2019 to July 2019. The total planned investment for rental real estate was changed from ¥332 million to ¥317 million. For the Funabashi Dormitory, total planned investment was changed from ¥348 million to ¥381 million, and the commencement date was changed from July 2018 to March 2018.」
Updated the existing capital investment plans, including the scheduled completion of the Shinagawa Konan Building, the investment amount for rental real estate, and the investment amount and commencement date for the Funabashi Dormitory. - FY2018-Q3First statedAnnual report
「日本コムシス株式会社 Shinagawa Konan Building (Minato-ku, Tokyo) 日本コムシス Group Parking facility 4,340 2,806 Internal funds February 2018 May 2019 — コムシスシェアードサービス株式会社 Hiyoshi Dormitory (Kohoku-ku, Yokohama) Other Dormitory and company housing 303 9 Internal funds October 2017 July 2018 — コムシスシェアードサービス株式会社 Funabashi Dormitory (Funabashi, Chiba) Other Dormitory and company housing 381 0 Internal funds March 2018 February 2019 —」
The company has specified plans to build a parking facility at the Shinagawa Konan Building and the Hiyoshi and Funabashi dormitories. It disclosed planned investment, amounts already paid, commencement dates and scheduled completion dates, and also described changes to the scheduled completion dates and investment amounts for the Hiyoshi and Funabashi dormitories.