The company announced that grid connection had begun at an approximately 2 MW grid-scale energy storage facility in Makurazaki, Kagoshima, and said the joint project with Nippon Chikudenchi aims for continued monetization through entry into the balancing market around March 2027.
Remixpoint has disclosed progress on a project to develop an approximately 2 MW-class grid-scale energy storage facility in Makurazaki in partnership with Nippon Chikudenchi. The facility has begun grid connection, and operations are progressing under the joint development framework established by the two companies.
The facility's operation is based on materials published by Nikkei Company Information DIGITAL. The materials specify that the project involves an energy storage facility with output of approximately 2 MW in Makurazaki, Kagoshima. The facility is described as medium-scale energy storage infrastructure.
Looking ahead, the company has outlined plans to enter the balancing market around March 2027. This is expected to enable monetization of the facility's operations through market transactions.
The project is being carried out jointly by Remixpoint and Nippon Chikudenchi, and has been reported as an initiative aimed at stabilizing energy supply and demand and generating long-term revenue.