Strategic Inventory Hub and Enhanced Delivery Capabilities in the Eastern Region
First written in FY2016. 10 of 21 entries say "Restated". Latest entry: 2026-10-02.
1 other company's latest entry also says "Achieved".
- FY2026SoftenedAnnual report
「Hasuda Logistics Center (Hasuda, Saitama) Logistics management 5,000 2,989 Internal funds January 2025 August 2026 Strengthening logistics capabilities」
For the Hasuda Logistics Center project, the total investment of ¥5 billion, ¥2,989 million already paid, and funding from internal funds were disclosed. The scheduled completion date has changed from April 2026 to August 2026. - 2026-05-28SoftenedGeneral Meetings of Shareholders
「Construction and start of operations of the Hasuda Logistics Center (August 2026); construction and relocation of the Matsumoto Sales Office (August 2026)」
The Hasuda Logistics Center was listed as scheduled for construction and commencement of operations in August 2026, revised from the previous scheduled completion date of April 2026. - FY2025AdvancedAnnual report
「Reporting company Hasuda Logistics Center (Hasuda, Saitama) Logistics management 5,000 1,805 Internal funds January 2025 April 2026 Strengthening logistics capabilities」
As a new facilities plan to strengthen strategic inventory and delivery capabilities, the Hasuda Logistics Center is being planned with a total investment of ¥5 billion, completion scheduled for April 2026, and funding from internal funds. - FY2023RestatedAnnual report
「Specifically, to help resolve the challenges faced by manufacturers, we actively pursued proposals utilizing our logistics capabilities, one of our strengths, to streamline parts procurement and production management, among other areas.」
We continue to propose ways to streamline parts procurement and production management by utilizing our logistics capabilities. - FY2023-Q3RestatedAnnual report
「Specifically, to help resolve the challenges faced by manufacturers, we actively pursued proposals utilizing our logistics capabilities, one of our strengths, to improve materials procurement and streamline production management, among other areas.」
We continue to pursue proposals to improve materials procurement and streamline production management by utilizing our logistics capabilities. - FY2023-Q2RestatedAnnual report
「Specifically, to help resolve the challenges faced by manufacturers, we actively pursued proposals utilizing our logistics capabilities, one of our strengths, to improve materials procurement and streamline production management, among other areas.」
We continue to pursue proposals to improve materials procurement and streamline production management by utilizing our logistics capabilities. - FY2023-Q1Development of proposals utilizing logistics capabilitiesAnnual report
「Specifically, to help resolve the challenges faced by manufacturers, we actively pursued proposals utilizing our logistics capabilities, one of our strengths, to improve materials procurement and streamline production management, among other areas.」
In addition to strengthening strategic inventory and delivery capabilities, we explicitly identified proposals to improve materials procurement and streamline production management by utilizing our logistics capabilities. - FY2022-Q3RestatedAnnual report
「We are also working to expand inventory in order to meet our supply responsibilities even as product lead times lengthen.」
We continue to expand inventory to meet our supply responsibilities in response to longer product lead times. - FY2022-Q2AchievedAnnual report
「In terms of facilities, in September 2021 we newly built and relocated the Seibu Logistics Center to Kadoma, Osaka, to expand strategic inventory and strengthen delivery capabilities in western Japan. We also opened the Kadoma Sales Office at the center as a new sales base and are working to develop sales activities more closely aligned with the local community.」
The planned new construction and relocation of the Seibu Logistics Center to Kadoma, Osaka, was completed in September 2021. The Kadoma Sales Office was also opened, putting strategic inventory and delivery capabilities in western Japan into operation. - FY2021AdvancedAnnual report
「Filing company New Western Distribution Center (Kadoma, Osaka) Logistics management 10,300 696 Internal funds and finance leases March 2020 September 2021 Operational rationalization」
Regarding the new Seibu Logistics Center project, the planned investment was updated from ¥9,958 million to ¥10,300 million, with ¥696 million already paid and completion scheduled for September 2021. The building has also been handed over, and lease assets under a finance lease are now being recognized. - FY2021-Q3Change in investment amount and scheduled completion date for the relocation planAnnual report
「Filing company New Western Distribution Center (Kadoma, Osaka) Logistics management 9,958 61 Internal funds and finance leases March 2020 September 2021 Operational rationalization」
For the New Western Distribution Center plan, planned investment increased from ¥8,232 million to ¥9,958 million, and the scheduled completion date changed from August 2021 to September 2021. The objective of operational rationalization and the funding method remained unchanged. - FY2020-Q3RestatedAnnual report
「Filing company New Western Distribution Center (Kadoma, Osaka) Logistics management 8,232 ― Internal funds and finance leases March 2020 August 2021 Operational rationalization」
The company continues to report the plan for the New Western Distribution Center, including planned investment of ¥8,232 million, commencement in March 2020 and completion in August 2021, funding through internal funds and finance leases, and the objective of operational rationalization. - FY2020-Q2AdvancedAnnual report
「Filing company New Western Distribution Center (Kadoma, Osaka) Logistics management 8,232 ― Internal funds and finance leases March 2020 August 2021 Operational rationalization」
For the previously announced Western Distribution Center relocation plan, the company provided specifics on the location of the New Western Distribution Center, planned investment of ¥8,232 million, scheduled start and completion dates, funding method, and objective of operational rationalization. - FY2019Announcement of the Western Distribution Center relocation planAnnual report
「The company planned to relocate the Western Distribution Center in August 2021, but the specific amount of capital investment had not yet been determined.」
As part of efforts to strengthen strategic inventory and delivery functions, the company provided its first specific details of the plan to relocate the Western Distribution Center in August 2021. The investment amount was stated as undecided. - FY2019-Q3RestatedAnnual report
「Specifically, the Company continued to actively exhibit at various trade shows and worked to expand strategic inventories.」
The company is reaffirming the strengthening of inventory functions through continued expansion of strategic inventory, contributing to greater convenience for business partners. - FY2019-Q2RestatedAnnual report
「In addition to continuing to actively exhibit at various trade shows, we worked to expand strategic inventory and improve the provision of information and convenience for business partners.」
The company continues expanding strategic inventory and working to improve convenience for business partners. - FY2019-Q1RestatedAnnual report
「Specifically, the Company continued to actively exhibit at various trade shows and worked to expand strategic inventories.」
The company continues expanding strategic inventory as part of the same effort to strengthen inventory and delivery functions through the development of new logistics bases. - FY2016First statedAnnual report
「In August 2015, the company newly built and relocated the Eastern Distribution Center to Kuki, Saitama, to strengthen its strategic inventory base and delivery functions in eastern Japan.」
The company is strengthening inventory positioning and delivery functions in eastern Japan by newly building and relocating its distribution center.