Delays, Damages and Reputational Damage in Large-Scale Systems Development Projects

First written in FY2016. 11 of 23 entries say "Materialised", first in FY2016. Latest entry: 2026-10-29.

23entries
11years
5from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseCited as achievedFY2019-Q1 – FY2022-Q3MitigatedFY2025-H1 – FY2026-H12016: 320162017: 220172018: 320182019: 120192020: 120202021: 020212022: 120222023: 120232024: 320242025: 220252026: 62026
Same theme, other companies
Risk of Quality Issues and Deteriorating Profitability in Large Contract-Based ProjectsA theme 18 companies write about · 18 as a headwind · 0 as a tailwind

Saison Technology moved to the "Worse" side of this theme in 2016, 5 years before the typical company in this theme (2021).

The whole theme swung hardest in 2020: 6 of 11 companies on the "Worse" side.

4 other companies' latest entry also says "Mitigated".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 18 companies compared. The sentences above are computed from all 18.
Full recordFilings, disclosures and news, newest first
  1. FY2026.Annual report

    「The main factors behind the decrease in profit were the decline in revenue and the recognition in cost of sales of ¥439 million in provision for contract loss, including future development costs required to restore some projects in which high workloads had arisen, among other factors.」

    High workloads actually arose in some projects, and ¥439 million in provision for contract loss was recognized, including future development costs required to restore them.
  2. FY2026-H1.Annual report

    「Provision for contract loss 9,463 —」

    The ¥9,463 thousand provision for contract loss recorded at the end of the previous consolidated fiscal year was no longer recognized at the end of the current interim consolidated period, indicating that the factors causing losses in contract development in prior years are being resolved in the financial statements.
  3. FY2025.Annual report

    「The main factor behind the increase in profit was that, although a provision for contract loss had been recognized in the previous consolidated fiscal year, the impact of extraordinary factors such as contract losses was limited in the current consolidated fiscal year, among other factors.」

    The Company explained that, compared with the impact of the provision for contract loss incurred in the previous fiscal year, the impact of extraordinary factors such as contract losses was limited in the current fiscal year, allowing operating profit to recover.
  4. FY2025-H1.Annual report

    「The main factor behind the increase in profit was that a provision for contract loss had been recognized in the previous interim consolidated period, whereas no extraordinary factors such as contract losses occurred in the current interim consolidated period, among other factors.」

    The Company explained that no extraordinary factors such as the provision for contract loss recognized in the previous interim period occurred in the current interim period. However, ¥252 million remains in the provision for contract loss.
  5. FY2024.Annual report

    「Due to the high workload arising in some projects under development, the Company recognized ¥1,805 million in provision for contract loss in cost of sales as development costs required to restore those projects.」

    High workloads in projects under development continued, and the provision for contract loss increased to ¥1,805 million.
  6. FY2024-Q3.Annual report

    「As stated in the extraordinary report submitted to the Kanto Local Finance Bureau on 31 October 2023, some projects under development have experienced high workloads. The Company is considering strengthening the measures described under “(4) Risks Related to Contract Development” within the “Business and Other Risks” section of the annual securities report for the previous fiscal year.」

    The high workload situation in some projects under development has continued, and the Company is considering strengthening measures to address contract development risks.
  7. FY2024-Q2.Annual report

    「Due to the high workload arising in some projects under development, the Company recognized ¥1,272 million in provision for contract loss in cost of sales as future development costs required to restore those projects.」

    As a risk related to contract development, high workloads actually arose in projects under development, and ¥1,272 million in provision for contract loss was recognized for future development costs required to restore the projects.
  8. FY2022-Q3.Annual report

    「Although the Company has continued to invest in research and development, it has worked to improve productivity since the end of the fiscal year ended March 2016, when it recorded a loss related to delays in a long-term large-scale project. As a result, revenue per employee grew to ¥31.4 million in the fiscal year ended March 2021, up 29.1% from the fiscal year ended March 2016, while gross profit per employee grew to ¥13.3 million, up 96.3%.」

    The Company again cites the recognition of a loss related to delays in a former long-term large-scale project as the premise for explaining its productivity improvement initiatives.
  9. FY2020.Annual report

    「In addition, in the Financial IT Services business, the Company expects customer investment in systems development to remain on a declining trend following the large-scale development project completed two years ago, making it difficult to foresee positive growth going forward.」

    The Company continues to cite the previously completed large-scale development project as the premise for the subsequent decline in customer investment in systems development and the outlook for business growth.
  10. FY2019-Q3.Annual report

    「Following the completion in the previous consolidated fiscal year of the large-scale systems development project that had continued for more than a decade, the Company formulated and is implementing a three-year medium-term management plan beginning in the current consolidated fiscal year to promote the transformation to a new business structure.」

    The Company continues to cite the completion of the former large-scale systems development project as the premise for transforming to a new business structure and its medium-term management plan.
  11. FY2019-Q2.Annual report

    「Following the completion in the previous consolidated fiscal year of the large-scale systems development project that had continued for several years, the Company formulated a new three-year medium-term management plan beginning in the current consolidated fiscal year to promote the transformation to a new business structure.」

    The Company continues to cite the completion of the former large-scale systems development project as the premise for transforming to a new business structure and formulating a medium-term management plan.
  12. FY2019-Q1.Annual report

    「Following the completion in the previous consolidated fiscal year of the large-scale systems development project that had continued for several years, the Company formulated a new three-year medium-term management plan beginning in the current consolidated fiscal year to promote the transformation to a new business structure.」

    The Company cites the completion of the large-scale systems development project that had previously led to delays and a settlement as the premise for transforming to a new business structure and formulating a medium-term management plan.
  13. FY2018.Annual report

    「In terms of revenue, the large-scale systems development project that had been a longstanding concern was successfully completed, has already entered operation and is making a significant contribution to performance.」

    The Company states that the large-scale systems development project that had previously led to delays, a settlement and damages was completed, entered operation and is contributing to performance.
  14. FY2018-Q2.Annual report

    「The main factors behind the decrease were the ¥850 million reduction in the provision for contract termination losses due to payment of the termination fee related to the agreed termination of the large-scale systems development contract, and the ¥700 million decrease in long-term borrowings, among other factors.」

    Payment of the termination fee related to the agreed termination of the large-scale systems development contract was made, reducing the provision for contract termination losses by ¥850 million.
  15. FY2017-Q3.Annual report

    「In the previous consolidated fiscal year, the Company recognized ¥6,646 million in damages related to the conditional settlement concerning the development delay issue involving the large-scale systems development project as a provision for damages and recorded it as a loss. However, receipt of a neutral evaluation from the Software Dispute Resolution Center, a third-party organization, on 29 July 2016 satisfied the condition precedent for the settlement, causing the settlement to take effect immediately. As the loss amount was thereby finalized at the amount already recognized in the previous consolidated fiscal year, the payment of the settlement amount had no impact on profit or loss for the cumulative third quarter of the current consolidated fiscal year.」

    The Company continues to explain that the damages expense related to the delay issue involving the large-scale systems development project has been finalized and that payment of the settlement amount has no impact on profit or loss.
  16. FY2017-Q2.Annual report

    「The main factor behind the decrease was the payment of ¥6,646 million in damages related to the development delay issue involving the large-scale systems development project, among other factors.」

    Payment of damages related to the delay in the large-scale systems development project was made. The loss had already been recognized in the previous consolidated fiscal year, and it was explained that the payment had no impact on profit or loss for the current quarter.
  17. FY2017-Q1.Annual report

    「Receipt of the neutral evaluation in this matter satisfied the condition precedent for the settlement, and the settlement therefore took effect immediately. Of the total payment of ¥14,975.216 million stated above, part will be offset against advance payments and other amounts already paid, resulting in an actual payment of ¥7,764.651 million.」

    A neutral evaluation was received concerning the delay issue involving the large-scale systems development project, and the settlement took effect. The total actual payment was stated as ¥7,764.651 million.
  18. FY2016.Annual report

    「Net loss attributable to owners of the parent was ¥6,094 million, mainly due to the recognition of ¥6,646 million in provision for damages arising from a conditional settlement with the customer concerning delays in the development of a large-scale systems development project, and an impairment loss of ¥1,254 million on business-use assets.」

    Provision for damages, impairment loss and net loss related to delays in a large-scale project were recognized during the fiscal year.
Moved together

"Decline in Future Earnings from the Distribution and IT Solutions Business" moved the same way as this thread, in the same document, in 8 of its 23 moves.

844444★123456
  1. ★This thread
  2. 1Decline in Future Earnings from the Distribution and IT Solutions Business8×
  3. 2Focus on the priority-customer market business4×
  4. 3Business transformation through 4 shifts4×
  5. 4Sustained Achievement of 15% ROE4×
  6. 5Accelerating growth in the HULFT business4×
  7. 6Expansion of cross-industry systems integration and cloud solutions4×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next