Komori
Occurring Fact9519RENOVA,Inc.Electricity and gas

Notice Regarding the Resumption of Operations at the Tokushima Tsuda Biomass Power Plant

The Tokushima Tsuda Biomass Power Plant, which had been shut down since 8 July due to damage to a steam control valve, resumed normal operations on 25 July following completion of repairs to the part.

Worth reading
38Recurring
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Neutral
Direction inferred from the company’s description.
Scale
—
Displayed only when the document provides numerical figures.
Wording
Definitive
How definitive the wording is.

Resumption of operations at the Tokushima Tsuda Biomass Power Plant

Subject Entity

徳島津田バイオマス発電所合同会社 (a consolidated subsidiary of the filing company)

Target Locations / Products

Tokushima Tsuda Biomass Power Plant

Occurrence25 July 2026
This disclosure07/29/2026
Cause

Damage to the steam control valve connected to the high-pressure turbine

Amount of Impact on Business Performance

No impact. No impact on the consolidated earnings forecasts for the fiscal year ending March 2027

Impact on Earnings Forecast

No impact on consolidated earnings forecasts for the current fiscal year (the fiscal year ending March 2027)

Company response

Suspended operations

Operations at the Tokushima Tsuda Biomass Power Plant were suspended from 8 July 2026

Scheduled resumption date

25 July 2026 (normal operations have resumed)

Outlook

The company will promptly disclose any matters requiring disclosure should they arise

Event that occurred
ItemDetails
Event nameResumption of operations at the Tokushima Tsuda Biomass Power Plant
Date of occurrence25 July 2026
Subject Entity徳島津田バイオマス発電所合同会社 (a consolidated subsidiary of the filing company)
Target Locations / ProductsTokushima Tsuda Biomass Power Plant
CauseDamage to the steam control valve connected to the high-pressure turbine
Amount of Impact on Business PerformanceNo impact. No impact on the consolidated earnings forecasts for the fiscal year ending March 2027
Impact on Earnings ForecastNo impact on consolidated earnings forecasts for the current fiscal year (the fiscal year ending March 2027)
Suspended operationsOperations at the Tokushima Tsuda Biomass Power Plant were suspended from 8 July 2026
Scheduled resumption date25 July 2026 (normal operations have resumed)
OutlookThe company will promptly disclose any matters requiring disclosure should they arise
Planned follow-up disclosureThe company will promptly disclose any matters requiring disclosure should they arise
Items this document does not state (14)
Date recognized / date notice receivedAccounting period in which recognizedType of litigation or proceedingCourt or authorityPlaintiffDefendantDate of filing / date of actionClaim amount / surcharge amountAmount of receivables at risk of non-collection or delayed collectionInvestigation structureMeasures to prevent recurrenceDirectors' and officers' liabilityVoting rights ownership percentage before the changeVoting rights ownership percentage after the change

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

Operations resumed because repairs to the part were completed as scheduled. The number of days the plant was offline was within the number of unplanned outage days initially anticipated for the biomass power generation business as a whole, and there is no impact on the consolidated earnings forecasts for the fiscal year ending March 2027.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Notice Regarding the Resumption of Operations at the Tokushima Tsuda Biomass Power Plant | RENOVA,Inc. (9519) timely disclosure | Komori