Resumption of Operations at Karumai Nishi Solar Power Plant
合同会社軽米西ソーラー (the Company's consolidated subsidiary)
Karumai West Solar Power Plant
Malfunction in the receiving and substation equipment
Although revenue is expected to decrease, compensation is expected to be received under profit insurance. Amount: Not disclosed.
The current fiscal year (fiscal year ending March 2027)
Already reflected in the consolidated earnings forecast for the current fiscal year (fiscal year ending March 2027). The impact on earnings is immaterial.
Company response
Operations at Karumai Nishi Solar Power Plant were suspended from 22 April 2026.
1 July 2026 (normal operations have resumed)
The Company will promptly disclose any matters that should be disclosed.
| Item | Details |
|---|---|
| Event name | Resumption of Operations at Karumai Nishi Solar Power Plant |
| Date of occurrence | 1 July 2026 (date normal operations resumed) |
| Subject Entity | 合同会社軽米西ソーラー (the Company's consolidated subsidiary) |
| Target Locations / Products | Karumai West Solar Power Plant |
| Cause | Malfunction in the receiving and substation equipment |
| Amount of Impact on Business Performance | Although revenue is expected to decrease, compensation is expected to be received under profit insurance. Amount: Not disclosed. |
| Accounting period in which recognized | The current fiscal year (fiscal year ending March 2027) |
| Impact on Earnings Forecast | Already reflected in the consolidated earnings forecast for the current fiscal year (fiscal year ending March 2027). The impact on earnings is immaterial. |
| Suspended operations | Operations at Karumai Nishi Solar Power Plant were suspended from 22 April 2026. |
| Scheduled resumption date | 1 July 2026 (normal operations have resumed) |
| Outlook | The Company will promptly disclose any matters that should be disclosed. |
| Planned follow-up disclosure | The Company will promptly disclose any matters that should be disclosed. |
Items this document does not state (13)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.The repair work to address the malfunction in the receiving and substation equipment was completed as scheduled. Although the shutdown is expected to reduce revenue, compensation is expected to be received under profit insurance.