Notice Regarding the Suspension of Operations at the Tokushima Tsuda Biomass Power Plant

Operations at the Tokushima Tsuda Biomass Power Plant were suspended on 8 July 2026, and damage to the steam control valve connected to the high-pressure turbine was confirmed. The company plans to repair the part and resume operations during July 2026, but will not revise its consolidated earnings forecasts for the current fiscal year.

Worth reading
37Immaterial
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Neutral
Direction inferred from the company’s description.
Scale
—
Displayed only when the document provides numerical figures.
Wording
Conditional
How definitive the wording is.

Suspension of operations at the Tokushima Tsuda Biomass Power Plant

Subject Entity

合同会社徳島津田バイオマスエナジー (a consolidated subsidiary of the company)

Target Locations / Products

Tokushima Tsuda Biomass Power Plant, high-pressure turbine equipment, and steam control valve

Occurrence8 July 2026
This disclosure07/21/2026
Cause

Abnormal pressure occurred within the high-pressure turbine equipment during operation, damaging the steam control valve connected to the high-pressure turbine.

Accounting period in which recognized

Fiscal year ending March 2027

Impact on Earnings Forecast

No impact on consolidated earnings forecasts for the current fiscal year (the fiscal year ending March 2027)

Company response

Suspended operations

Operation of the Tokushima Tsuda Biomass Power Plant

Scheduled resumption date

Scheduled for July 2026

Outlook

Proceed with repairs to the part toward resuming operations

Planned follow-up disclosure

The company will promptly disclose any matters that should be disclosed if they arise.

Event that occurred
ItemDetails
Event nameSuspension of operations at the Tokushima Tsuda Biomass Power Plant
Date of occurrence8 July 2026
Subject Entity合同会社徳島津田バイオマスエナジー (a consolidated subsidiary of the company)
Target Locations / ProductsTokushima Tsuda Biomass Power Plant, high-pressure turbine equipment, and steam control valve
CauseAbnormal pressure occurred within the high-pressure turbine equipment during operation, damaging the steam control valve connected to the high-pressure turbine.
Accounting period in which recognizedFiscal year ending March 2027
Impact on Earnings ForecastNo impact on consolidated earnings forecasts for the current fiscal year (the fiscal year ending March 2027)
Suspended operationsOperation of the Tokushima Tsuda Biomass Power Plant
Scheduled resumption dateScheduled for July 2026
OutlookProceed with repairs to the part toward resuming operations
Planned follow-up disclosureThe company will promptly disclose any matters that should be disclosed if they arise.
Items this document does not state (14)
Date recognized / date notice receivedAmount of Impact on Business PerformanceType of litigation or proceedingCourt or authorityPlaintiffDefendantDate of filing / date of actionClaim amount / surcharge amountAmount of receivables at risk of non-collection or delayed collectionInvestigation structureMeasures to prevent recurrenceDirectors' and officers' liabilityVoting rights ownership percentage before the changeVoting rights ownership percentage after the change

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

Abnormal pressure occurred within the high-pressure turbine equipment during operation, and an inspection confirmed damage to the steam control valve connected to the high-pressure turbine. The number of days of suspended operations is stated to be within the range of unplanned outage days anticipated at the beginning of the fiscal year for the biomass power generation business as a whole.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Notice Regarding the Suspension of Operations at the Tokushima Tsuda Biomass Power Plant | RENOVA,Inc. (9519) timely disclosure | Komori