Start of construction of the fourth wood biomass power plant
First written in FY2016. 9 of 20 entries say "Restated". Latest entry: FY2024-Q3.
No other company in this theme has enough history to compare yet.
- FY2024-Q3RestatedAnnual report
「エフオン新宮発電所 conducted a scheduled self-inspection for 13 days, while エフオン壬生発電所 conducted one for 14 days.」
The filing states that scheduled self-inspections were conducted for 13 days at 新宮 and 14 days at 壬生 to maintain operations at the wood biomass power plants. It does not indicate the start of operations at any new power plant. - FY2024-Q2RestatedAnnual report
「The EF-ON Shirakawa Power Plant conducted a statutory periodic operator inspection lasting approximately 15 days, while the EF-ON Hita Power Plant conducted one lasting approximately 18 days.」
Regarding continued operations at the woody biomass power plants, the disclosure states that statutory inspections were conducted at Shirakawa and Hita while the power plants maintained high operating rates. - FY2023-Q1RestatedAnnual report
「The EF-ON Shingu Power Plant conducted inspections and adjustments of its facilities through trial operations from the beginning of the period, completed the adjustments in August and transitioned to full-scale operations. In addition, EF-ON Shirakawa, EF-ON Bungo-Ono and the EF-ON Mibu Power Plant maintained high operating rates and operated smoothly.」
The disclosure describes the continued operation of the power plants, including the Mibu Power Plant. While the Shingu Power Plant transitioned to full-scale operations, there was no new change in the policy of maintaining high operating rates at the group of power plants central to this thread. - FY2022-Q1RestatedAnnual report
「EF-ON Shirakawa, EF-ON Bungo-Ono and the EF-ON Mibu Power Plant maintained high operating rates and operated smoothly.」
The disclosure describes the continued high operating rates of the power plants, including the Mibu Power Plant, but does not indicate that a new stage, such as the start of operations, has been reached. - FY2021-Q3RestatedAnnual report
「EF-ON Mibu conducted its first annual inspection and underwent a planned outage of approximately 2 weeks, while the other 3 power plants operated smoothly.」
The disclosure states that the Mibu Power Plant, corresponding to Unit 4, has continued operating and underwent a planned outage of approximately 2 weeks for its first annual inspection. - FY2021-Q2RestatedAnnual report
「Operations at EF-ON Mibu during the current fiscal year resulted in a substantial improvement in the business's performance compared with the prior-year period.」
The disclosure describes the continued operation of the Mibu Power Plant, corresponding to Unit 4, and its contribution to performance. It does not indicate that a new operating stage has begun. - FY2021-Q1RestatedAnnual report
「The Mibu Power Plant, which began operations in the second half of the previous fiscal year, experienced an unplanned outage lasting just under 1 week in September. However, its summer operations and fuel consumption proceeded smoothly and made a significant contribution to improved Group performance.」
The disclosure states that the Mibu Power Plant, corresponding to Unit 4, has continued operating and contributing to performance, while experiencing an unplanned outage lasting just under 1 week in September. - FY2020-Q3AchievedAnnual report
「Revenue and profit increased substantially as the newly built EF-ON Mibu Power Plant operated at full capacity for almost 3 months.」
EF-ON Mibu, corresponding to the fourth plant, completed the construction phase, began operations and reached almost 3 months of full operation. - FY2020-Q2AdvancedAnnual report
「EF-ON Mibu began test operations during the period and contributed to improved results.」
The Mibu power plant progressed to the stage of beginning test operations after installation of its equipment was substantially completed. - FY2020-Q1AdvancedAnnual report
「Regarding development of the new biomass power plant in Mibu, Tochigi Prefecture, installation of the various facilities is largely complete and trial operations are scheduled to begin in the second quarter.」
Regarding the Mibu Power Plant, the disclosure states that installation of the various facilities is largely complete and construction has progressed to the stage where trial operations are scheduled to begin in the second quarter. - FY2019-Q3AdvancedAnnual report
「At the new biomass power plant in Mibu, Tochigi Prefecture, construction of the turbine building and foundations for various equipment has been completed, while equipment installation, external works and various infrastructure works are under way. The project is progressing smoothly toward the target of commencing operations at the end of 2019.」
Regarding the Mibu Power Plant, the disclosure states that construction of the turbine building and foundations for various equipment has been completed and work has moved on to equipment installation, external works and infrastructure construction. The target of commencing operations at the end of 2019 is maintained. - FY2019-Q2AdvancedAnnual report
「At the new biomass power plant in Mibu, Tochigi Prefecture, construction of the turbine building has been completed, while external works and various infrastructure works are under way. The power generation facilities are also being constructed as planned, and the project is progressing smoothly toward the target of commencing operations at the end of 2019.」
Regarding the Mibu Power Plant, the disclosure states that construction of the turbine building has been completed and work has moved on to external works, infrastructure and construction of the power generation facilities. The target of commencing operations at the end of 2019 is also maintained. - FY2019-Q1AdvancedAnnual report
「At the new biomass power plant in Mibu, Tochigi Prefecture, structural steelwork for the turbine building has been completed, and exterior work and foundation work for various equipment are under way. Construction is progressing smoothly toward the target of commencing operations at the end of 2019.」
Regarding the Mibu Power Plant, the disclosure states that structural steelwork for the turbine building has been completed and work has moved on to exterior work and foundation work for the various equipment. The target of commencing operations at the end of 2019 is also maintained. - FY2018AdvancedAnnual report
「Development of the new biomass power plant in Mibu, Tochigi Prefecture, began in November last year. The turbine building foundations and structural steel assembly are under way, and construction is progressing smoothly.」
Regarding the Mibu Power Plant, the disclosure states that progress following the commencement of construction has reached the turbine building foundations and structural steel assembly stage. - FY2018-Q3RestatedAnnual report
「Construction of the new biomass power plant in Mibu, Tochigi Prefecture, is progressing as planned, and preparations are proceeding diligently toward commencing operations at the end of 2019.」
Regarding the Mibu Power Plant, the disclosure continues to describe construction progress following the commencement of construction and the target of commencing operations at the end of 2019, as stated in the previous quarter. - FY2018-Q2AdvancedAnnual report
「Construction of the new biomass power plant in Mibu, Tochigi Prefecture, began in November and is progressing smoothly, with operations targeted to begin by the end of 2019.」
The Mibu project reached the concrete stage of commencing construction, while retaining its target of starting operations at the end of 2019. - FY2018-Q1AdvancedAnnual report
「Construction of a new biomass power plant in Mibu, Tochigi Prefecture, is progressing smoothly toward the target of commencing operations at the end of 2019.」
Regarding the Mibu Power Plant, the disclosure explicitly states the target of commencing operations at the end of 2019 and that construction is progressing smoothly. - FY2017-Q3AdvancedAnnual report
「For the new biomass power plant project in Mibu, Tochigi Prefecture, we acquired the project site and entered into a financing agreement for construction costs, and the project is progressing smoothly.」
The Mibu project, corresponding to the fourth plant, had reached the stage of site acquisition and execution of a construction financing agreement. Completion of construction was not yet stated. - FY2017-Q2RestatedAnnual report
「We are also currently advancing a new biomass power plant project in Mibu, Tochigi Prefecture.」
Regarding the new construction plan for Unit 4, the disclosure continues to state that the project is currently under way, rather than indicating that a new stage, such as the completion of commencement of construction, has been reached. - FY2016First statedAnnual report
「We will also promote the start of construction of a new fourth power plant during the period of this medium-term management plan.」
The plan includes promoting development of the fourth power plant in Mibu, Tochigi Prefecture.