How it moved
ProgressHeldSoftenedWorseAdvancedFY2018 – FY2020-Q3AdvancedFY2025-H1 – 2026-08-292016: 12017: 320172018: 420182019: 320192020: 320202021: 320212022: 420222023: 220232024: 220242025: 220252026: 22026
Same theme, other companies
Expanding the Solar, Wind and Biomass Power PortfolioA theme 31 companies write about · 0 as a headwind · 38 as a tailwind

The whole theme swung hardest in 2025: 2 of 20 companies on the "Worse" side.

4 other companies' latest entry also says "Restated".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 31 companies compared. The sentences above are computed from all 31.
Full recordFilings, disclosures and news, newest first
  1. FY2026RestatedAnnual report

    「In the Green Energy business, we will expand investment in wood biomass-related fields, including forest management.」

    The group continues to expand investment in wood biomass-related fields, including forest management, with energy efficiency and domestically produced renewable energy as its central themes.
  2. 2026-08-29AdvancedGeneral Meetings of Shareholders

    「The total amount of capital expenditure by the corporate group during the current consolidated fiscal year was ¥1,726 million. The principal expenditure was as follows: (i) major facilities completed during the current consolidated fiscal year: Green Energy business, ㈱エフバイオス, sawmill equipment.」

    The disclosure states that sawmill equipment was completed in connection with the use and expansion of renewable resources.
  3. FY2025RaisedAnnual report

    「Toward carbon neutrality, our group formulated the “EF-ON Group Transition Strategy,” targeting a 50% reduction in Scope 1 and 2 emissions excluding power generation by fiscal 2030 from fiscal 2021 levels, and net zero by fiscal 2050.」

    In addition to the existing renewable-energy expansion policy, the group established time-bound targets for a 50% reduction in Scope 1 and 2 emissions excluding power generation by fiscal 2030, net zero by fiscal 2050, 1 billion kWh of wood biomass generation by fiscal 2030 and forest CO2 absorption of 6,000 t-CO2.
  4. FY2025-H1AdvancedAnnual report

    「During the current interim consolidated accounting period, the proportion of unused wood in fuel used at the group's power plants other than EF-ON Shingu improved year on year, increasing revenue. In addition, fuel, maintenance and other costs returned to normal levels, resulting in higher profit as these factors offset EF-ON Shingu's weak performance.」

    Improved use of unused wood at plants other than Shingu and the normalization of costs contributed to higher profit and offset Shingu's weak performance.
  5. FY2024-Q3RestatedAnnual report

    「Except for scheduled voluntary inspections at EF-ON Shingu in January and EF-ON Mibu in March, operations progressed steadily without any major problems.」

    The renewable-energy generation business operated without major problems while conducting scheduled voluntary inspections.
  6. FY2024-Q2AdvancedAnnual report

    「Total electricity transmission from the group's power plants reached a record high, including shutdown periods, as each plant maintained high utilization together with EF-ON Shingu, which began operations in the previous fiscal year.」

    The group's total electricity transmission reached a record high, including shutdown periods, because the plants, including Shingu, maintained high utilization.
  7. FY2024-Q1RestatedAnnual report

    「As EF-ON Shingu transitioned to full-scale operations in August of last year and contributed to performance during the current quarterly accounting period, total electricity transmission substantially exceeded the year-earlier period.」

    The filing continues to report the contribution of EF-ON Shingu's full-scale operations and increased electricity transmission. It does not indicate a new construction stage.
  8. FY2023-Q3AdvancedAnnual report

    「During the current quarterly consolidated accounting period, our group's EF-ON Shirakawa power plant transitioned to the FIP scheme (Feed-in Premium). Performance under the FIP scheme during the period exceeded the projected revenue under the previous FIT scheme.」

    EF-ON Shirakawa transitioned from the FIT scheme to the FIP scheme, and performance under the new scheme exceeded projected revenue under FIT.
  9. FY2023-Q1AdvancedAnnual report

    「EF-ON Shingu transitioned to full-scale operations in August, and total electricity transmission substantially exceeded the year-earlier period.」

    EF-ON Shingu transitioned to full-scale operations in August, and total group electricity transmission substantially exceeded the year-earlier period.
  10. FY2022WorsenedAnnual report

    「The newly built EF-ON Shingu power plant experienced a problem during maximum-output trial operation of the generating equipment, resulting in a significant delay in the transition to commercial operations. Restoration work was completed by the end of June, and work is proceeding diligently toward completion.」

    The transition to commercial operations was significantly delayed, although restoration work was completed by the end of June.
  11. FY2022-Q3WorsenedAnnual report

    「The newly built EF-ON Shingu power plant completed connection work for the grid interconnection line, but a problem occurred during maximum-output trial operation of the generating equipment, delaying the construction schedule. Work is proceeding diligently toward completion in July.」

    A problem during maximum-output trial operation delayed the construction schedule, with completion targeted for July.
  12. FY2022-Q2WorsenedAnnual report

    「The newly built EF-ON Shingu power plant completed connection work for the grid interconnection line, but a problem occurred while the generating equipment was being operated at maximum output. As resolving the problem will require a certain amount of time, the scheduled start of operations has been delayed.」

    Although grid interconnection work was completed, a problem during maximum-output operation delayed the scheduled start of operations.
  13. FY2022-Q1AdvancedAnnual report

    「We have entered into specified wholesale supply agreements with our subsidiary power plants for use in EF-ON's retail electricity business not only in Kyushu but also in the Kanto and Tohoku regions, and by purchasing traceable non-fossil certificates, we have established the framework to sell electricity generated by our group as 100% renewable energy.」

    The renewable-energy retail framework was expanded from Kyushu to Kanto and Tohoku through specified wholesale supply agreements and traceable non-fossil certificates.
  14. FY2021-Q3AdvancedAnnual report

    「At the Shingu plant, the main facilities, including the turbine building, condenser and fuel warehouse, have now been erected, and work has progressed to the installation of piping and auxiliary equipment.」

    The Shingu plant has progressed from construction of its main facilities to installation of piping and auxiliary equipment.
  15. FY2021-Q2AdvancedAnnual report

    「To maintain stable operations at our wood biomass power plants and contribute to regional economic development, our group is promoting the revitalization of forest resources. We are focusing on securing and training personnel and acquiring logging equipment and operating sites in order to accumulate expertise in forest management and develop this into a core business in the future. Construction of our group's fifth plant, EF-ON Shingu, is progressing generally smoothly, and the buildings housing the turbine, condenser and other equipment are beginning to take visible shape.」

    The filing reports progress in revitalizing forest resources, securing personnel and acquiring equipment and operating sites, while construction of EF-ON Shingu has reached the stage at which the buildings are visibly taking shape.
  16. FY2021-Q1RestatedAnnual report

    「The Mibu plant, which began operating in the second half of the previous fiscal year, experienced an unplanned shutdown lasting just under one week in September, but operations and fuel consumption during the summer progressed smoothly and made a significant contribution to improving group performance. Construction of the power plant in Shingu, Wakayama Prefecture, is also progressing as planned, without any impact from the spread of COVID-19.」

    The filing continues to report operations at Mibu and construction at Shingu. It does not indicate that either project has reached a new stage.
  17. FY2020-Q3AdvancedAnnual report

    「In our group's power-generation business, performance recovered year on year and we achieved higher revenue and profit as EF-ON Mibu commenced operations, offsetting the decline in revenue caused by deteriorating fuel efficiency in the first quarter due to unfavorable weather and the allocation of fuel centered on recycled wood. EF-ON Shirakawa and EF-ON Hita power plants underwent annual scheduled maintenance from October through December, but during the other periods, including the third quarter, the existing power plants maintained high utilization, and overall electricity transmission substantially exceeded the year-earlier period as EF-ON Mibu also commenced operations, making a significant contribution to improved group performance. Construction of the new power plant in Shingu, Wakayama Prefecture, is also progressing as planned, with no impact from the spread of COVID-19 at this point.」

    The filing states that EF-ON Mibu commenced operations, significantly increasing total electricity transmission year on year, while the Shingu plant continued to progress as planned.
  18. FY2020-Q2AdvancedAnnual report

    「EF-ON Mibu began trial operations during the period and contributed to improved results. For the power plant construction plan in Shingu, Wakayama Prefecture, civil engineering work has begun and is progressing as planned.」

    Specific progress includes the start of trial operations at the Mibu plant and commencement of civil engineering work at Shingu.
  19. FY2020-Q1AdvancedAnnual report

    「Development of the new biomass power plant in Mibu, Tochigi Prefecture, is proceeding with installation of most equipment substantially complete, and trial operations are scheduled to begin in the second quarter. For the power plant construction plan in Shingu, Wakayama Prefecture, a groundbreaking ceremony was held and construction has begun; both plants are progressing as planned.」

    The Mibu plant reached substantial completion of equipment installation and was scheduled to begin trial operations in the second quarter, while construction of Shingu began after its groundbreaking ceremony.
  20. FY2019-Q3AdvancedAnnual report

    「Construction of the new biomass power plant in Mibu, Tochigi Prefecture, is progressing smoothly toward commencing operations at the end of 2019. Construction of the turbine-building structure and foundations for various items of equipment has been completed, and equipment installation, exterior work and infrastructure work are under way. For the new power plant construction plan in Shingu, Wakayama Prefecture, we have acquired the project site and arranged project financing, and have also entered into an agreement with the supplier of the main equipment, including the boiler and turbine. The project is likewise progressing smoothly.」

    The Mibu plant moved to equipment installation after completion of foundation work, while the Shingu project advanced to execution of an agreement with the main-equipment supplier.
  21. FY2019-Q2AdvancedAnnual report

    「Construction of the new biomass power plant in Mibu, Tochigi Prefecture, is progressing smoothly toward commencing operations at the end of 2019. The turbine-building structure has been completed, exterior and infrastructure work is under way, and the generating equipment is being installed as planned. For the new power plant construction plan in Shingu, Wakayama Prefecture, we have acquired the project site and arranged project financing, and the project is likewise progressing smoothly.」

    The filing reports completion of the Mibu turbine-building structure and transition to exterior, infrastructure and generating-equipment work, as well as site acquisition and financing for Shingu.
  22. FY2019-Q1AdvancedAnnual report

    「Construction of the new biomass power plant in Mibu, Tochigi Prefecture, is progressing smoothly toward commencing operations at the end of 2019. The structural steel work for the turbine-building structure has been completed, and exterior work and foundation work for various items of equipment are under way. For the new power plant construction plan in Shingu, Wakayama Prefecture, we have acquired the project site, and that project is also progressing smoothly.」

    Specific progress includes completion of structural steel work and transition to subsequent construction at the Mibu plant, and acquisition of the Shingu plant site.
  23. FY2018AdvancedAnnual report

    「In the Green Energy business, we will expand investment in wood biomass-related fields. In the construction of wood biomass power plants, we will complete construction and commence operations at the fourth plant, EF-ON Mibu, in Mibu, Tochigi Prefecture by 2020, and advance development of the fifth plant, EF-ON Shingu, in Shingu, Wakayama Prefecture.」

    The filing specifies the deadline of 2020 for completing construction and commencing operations at the fourth plant, and the plan to advance development of the fifth plant.
  24. FY2018-Q3RestatedAnnual report

    「Construction of the new biomass power plant in Mibu, Tochigi Prefecture, is progressing as planned, and preparations are proceeding diligently toward commencing operations at the end of 2019.」

    The filing continues to report progress following construction commencement and maintains the end-2019 operations target.
  25. FY2018-Q2AdvancedAnnual report

    「Construction of the new biomass power plant in Mibu, Tochigi Prefecture, began in November and is progressing smoothly, with operations targeted to begin by the end of 2019.」

    The Mibu plant reached the specific stage of construction commencement in November, while the end-2019 operations target was maintained.
  26. FY2018-Q1AdvancedAnnual report

    「Construction of the new biomass power plant in Mibu, Tochigi Prefecture, is progressing smoothly, with operations targeted to begin by the end of 2019. We are expanding the business steadily toward achieving the Fourth Medium-Term Management Plan, centered on this project. We are also working diligently to advance the construction plan for a new power plant in Shingu, Wakayama Prefecture, announced in September.」

    The filing describes the target of commencing operations at the Mibu plant by the end of 2019 and the new Shingu plant construction plan under the Fourth Medium-Term Management Plan.
  27. FY2017-Q3AdvancedAnnual report

    「For the new biomass power plant project in Mibu, Tochigi Prefecture, we acquired the project site and entered into a financing agreement for construction costs, and the project is progressing smoothly.」

    Specific progress is reported for the expansion of renewable energy, particularly wood biomass, through the acquisition of the Mibu plant site and execution of a construction-financing agreement.
  28. FY2017-Q2RestatedAnnual report

    「We are also currently advancing a new biomass power plant project in Mibu, Tochigi Prefecture.」

    The policy of expanding energy efficiency and domestically produced renewable energy, particularly wood biomass, is reiterated through the Mibu project.
  29. FY2016First statedAnnual report

    「Under the EF-ON Group's Fourth Medium-Term Management Plan, our immediate strategy is to expand investment, particularly in the wood biomass-related field, with the aim of promoting and expanding “energy efficiency” and “domestically produced renewable energy” and contributing to the realization of the energy mix set out in the Basic Energy Plan.」

    The filing identifies the two pillars of the medium-term management plan and explicitly prioritizes investment in wood biomass.
Moved together

"New power plant construction project in Shingu, Wakayama Prefecture" moved the same way as this thread, in the same document, in 11 of its 29 moves.

111010987★123456
  1. ★This thread
  2. 1New power plant construction project in Shingu, Wakayama Prefecture11×
  3. 2Advancing operations, facility maintenance and fuel management10×
  4. 3Start of construction of the fourth wood biomass power plant10×
  5. 4Substantial growth in consolidated revenue and earnings led by the power-generation business9×
  6. 5Development of a wood biomass fuel supply infrastructure8×
  7. 6Dependence on Interest-Bearing Debt and Interest-Rate Risk7×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Ef-On's next results are scheduled for 2026-11-05. Read the earnings preview It last moved in the General Meetings of Shareholders of 2026-08-29: "Advanced".
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.