New power plant construction project in Shingu, Wakayama Prefecture
First written in FY2018-Q1. 11 of 19 entries say "Advanced", first in FY2018-Q3. Latest entry: FY2023-Q2.
No other company in this theme has enough history to compare yet.
- FY2023-Q2RestatedAnnual report
「The operation of the エフオン新宮 Power Plant contributed to consolidated results and substantially recovered performance for the cumulative second-quarter consolidated period.」
The disclosure continues to report the contribution of the Shingu Power Plant to consolidated results following the start of full-scale operation. The construction and start-of-operation stages had already been reported through the previous quarter. - FY2023-Q1AdvancedAnnual report
「EF-ON Shingu Power Plant had been inspecting and adjusting its equipment through test operations since the beginning of the period, and completed those adjustments in August before moving into full-scale operations.」
The disclosure reports concrete progress on the Shingu Power Plant construction plan, stating that trial operation and equipment adjustments had been completed and that the plant transitioned to full-scale operation in August. - FY2022WorsenedAnnual report
「The newly built EF-ON Shingu power plant experienced a problem during maximum-output trial operation of the generating equipment, resulting in a significant delay in the transition to commercial operations. Restoration work was completed by the end of June, and work is proceeding diligently toward completion.」
The transition to commercial operation at the Shingu Power Plant was substantially delayed by problems during trial operation. Although restoration work was completed by the end of June, completion and commercial operation were carried over to the following fiscal year. - FY2022-Q3WorsenedAnnual report
「The newly built EF-ON Shingu power plant completed connection work for the grid interconnection line, but a problem occurred during maximum-output trial operation of the generating equipment, delaying the construction schedule. Work is proceeding diligently toward completion in July.」
A problem occurred during maximum-output trial operation at the Shingu Power Plant following completion of the grid interconnection line connection work, delaying the construction schedule. Work is continuing toward completion in July. - FY2022-Q2WorsenedAnnual report
「The newly built EF-ON Shingu power plant completed connection work for the grid interconnection line, but a problem occurred while the generating equipment was being operated at maximum output. As resolving the problem will require a certain amount of time, the scheduled start of operations has been delayed.」
The Shingu Power Plant completed connection work for the grid interconnection line and progressed to operation at maximum output, but resolving problems with the generating equipment took a certain amount of time, delaying the scheduled start of operations. - FY2021AdvancedAnnual report
「株式会社エフオン新宮 Planned investment: ¥12,369 million Amount paid to date: ¥10,225 million Borrowings March 2019 March 2022」
For the Shingu Power Plant, the equipment plan specifies total planned investment of ¥12,369 million, ¥10,225 million paid to date, financing through borrowings, and scheduled completion in March 2022. After completion, an annual increase of 120,000 MWh in transmitted electricity is expected. - FY2021-Q3AdvancedAnnual report
「At the Shingu plant, the main facilities, including the turbine building, condenser and fuel warehouse, have now been erected, and work has progressed to the installation of piping and auxiliary equipment.」
The disclosure states that major facilities at the Shingu Power Plant, including the turbine building, condenser and fuel storage facility, had been erected and that installation of piping and auxiliary equipment had begun. - FY2021-Q2AdvancedAnnual report
「Construction of the Group's fifth power plant, the エフオン新宮 Power Plant, is progressing generally smoothly, and buildings such as the turbine building and condenser building have begun to take visible form.」
The disclosure states that construction of the Shingu Power Plant progressed to the point where buildings such as the turbine building and condenser building had become visible. - FY2021-Q1RestatedAnnual report
「Construction of the power plant in Shingu, Wakayama Prefecture is progressing as planned, with no impact from the spread of the novel coronavirus.」
The disclosure continues to state that the Shingu Power Plant construction plan is progressing as planned without being affected by the novel coronavirus. - FY2020AdvancedAnnual report
「At the Shingu Power Plant, which is under construction, foundation work for the turbine building and column erection work are progressing as scheduled. There have so far been no disruptions, such as delays in procuring construction materials or personnel shortages caused by travel restrictions, as a result of measures to prevent the spread of the novel coronavirus.」
The Shingu Power Plant has progressed from the groundbreaking ceremony and start of civil engineering work to foundation work for the turbine building and column erection work. The disclosure also states that no delays in materials procurement or personnel shortages caused by the spread of infection had occurred at that time. - FY2020-Q3RestatedAnnual report
「The power plant construction plan in Shingu, Wakayama Prefecture is progressing as planned, with no impact from the spread of the novel coronavirus so far.」
The disclosure continues to state that the Shingu Power Plant construction plan is progressing as planned without being affected by the novel coronavirus. - FY2020-Q2AdvancedAnnual report
「For the power plant construction plan in Shingu, Wakayama Prefecture, civil engineering work has begun and the project is progressing as planned.」
The disclosure states that the Shingu Power Plant project progressed to the stage of commencing civil engineering work, following the groundbreaking ceremony and the start of construction. - FY2020-Q1AdvancedAnnual report
「For the power plant construction plan in Shingu, Wakayama Prefecture, a groundbreaking ceremony was held and construction is under way. Both power plants are progressing as planned.」
The disclosure states that the Shingu Power Plant project reached the stage of commencing construction following the groundbreaking ceremony. - FY2019-Q3AdvancedAnnual report
「In the plan to construct a new power plant in Shingu, Wakayama Prefecture, the Company acquired the project site, raised funds for the project and entered into a contract with the supplier of major equipment, including the boiler and turbine. The project is likewise progressing smoothly.」
The disclosure states that the Shingu Power Plant project has progressed through the signing of a contract with the supplier of major equipment, including the boiler and turbine, in addition to site acquisition and financing. - FY2019-Q2AdvancedAnnual report
「In the plan to construct a new power plant in Shingu, Wakayama Prefecture, the Company acquired the project site and raised funds for the project, and the project is likewise progressing smoothly.」
The disclosure states that, in addition to the previously reported site acquisition, funds for the Shingu Power Plant project have been raised. - FY2019-Q1AdvancedAnnual report
「In the plan to construct a new power plant in Shingu, Wakayama Prefecture, the Company acquired the project site, and the project is also progressing smoothly.」
The disclosure reports concrete progress on the Shingu Power Plant project, namely the acquisition of the project site. - FY2018RestatedAnnual report
「The Company will continue to promote development of the エフオン新宮 Power Plant in Shingu, Wakayama Prefecture, which will be its fifth plant.」
The plan to develop the Shingu Power Plant as the fifth plant continues to be disclosed. - FY2018-Q3AdvancedAnnual report
「Although the Group's planned new power plant in Shingu, Wakayama Prefecture is not affected by the price revision because certification of its business plan at fiscal 2017 prices has already been obtained, attention is considered necessary in formulating future development plans.」
The disclosure states that certification of the business plan for the Shingu power plant at fiscal 2017 prices had already been obtained, leaving the project unaffected by the price revision. - FY2018-Q1First statedAnnual report
「In addition, construction of the new power plant in Shingu, Wakayama Prefecture, announced in September, is being actively advanced according to plan.」
The Company first disclosed the announcement and advancement of a new power plant construction plan in Shingu, Wakayama Prefecture.