Development of Technologies for Higher-Efficiency, Low-Carbon Coal-Fired Power Generation

First written in FY2016. 2 of 6 entries say "Advanced", first in FY2017. Latest entry: FY2026.

6entries
11years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseAdvancedFY2017 – FY2019ReframedFY2022 – FY20242016: 120162017: 120172018: 020182019: 120192020: 020202021: 020212022: 120222023: 020232024: 120242025: 020252026: 12026
Same theme, other companies
Development and Capacity Expansion of High-Efficiency, Low-Environmental-Impact Thermal Power GenerationA theme 6 companies write about · 0 as a headwind · 12 as a tailwind

Electric Power Development moved to the "Worse" side of this theme in 2022.

4 other companies' latest entry also says "Advanced".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2026AdvancedAnnual report

    「From the perspective of pursuing a range of possibilities across the hydrogen, ammonia and CCS supply chains, from upstream to downstream, the company established a new organization in April 2025 that consolidated its CCS-related functions and organization. It is also considering the commercialization of CCS businesses in western Japan and conducting studies of CCS businesses off the coast of Australia and off the Malay Peninsula.」

    The development of lower-carbon technologies for coal-fired power has progressed into concrete initiatives, including establishing a new CCS organization and considering the commercialization of CCS businesses in Japan and overseas.
  2. FY2024ReframedAnnual report

    「In addition to advancing the GENESIS Matsushima Plan to commercialize coal gasification combined-cycle (IGCC) technology for future CO2-free hydrogen power generation, the Group is pursuing a range of possibilities across the hydrogen, ammonia and CCS supply chains, from upstream to downstream, to secure decarbonization technologies and achieve a reliable transition for thermal power generation.」

    The company has organized its initiatives around a thermal power transition that includes CO2-free hydrogen power generation centered on GENESIS Matsushima, ammonia and CCS, moving beyond the development of high-efficiency and lower-carbon coal-fired power technologies.
  3. FY2022ReframedAnnual report

    「Matsushima is Japan's first thermal power station fueled by imported coal, built in response to the need to diversify energy sources after the oil shocks. By adding new coal gasification equipment to the power station, which has been in operation for 40 years, the company is taking the first step toward future CO2-free hydrogen power generation under the GENESIS Matsushima Plan. The environmental impact assessment process began in September 2021.」

    The focus has expanded from demonstrations of IGCC and CO2 separation and capture to upcycling the existing Matsushima thermal power station for CO2-free hydrogen power generation.
  4. FY2019AchievedAnnual report

    「At Osaki CoolGen Co., Ltd., the first-stage oxygen-blown IGCC technology demonstration test had been under way since 2017, and ended in February 2019 after achieving its objectives, including demonstrating basic performance, controllability and operability. In addition, detailed design is under way for the CO2 separation and capture facilities required for the second-stage demonstration test of oxygen-blown IGCC technology with CO2 separation and capture, scheduled to begin in FY2019, and a third-stage demonstration test is planned to develop a system incorporating fuel cells into these technologies.」

    The first-stage oxygen-blown IGCC demonstration test at Osaki CoolGen ended in February 2019, and achievement of its objectives, including basic performance, controllability and operability, was stated. The second and third stages are described as ongoing plans.
  5. FY2017AdvancedAnnual report

    「The oxygen-blown IGCC technology demonstration test (first stage) began in March 2017, and detailed design is under way for the CO2 separation and capture facilities required for the second-stage demonstration of oxygen-blown IGCC technology with CO2 separation and capture, scheduled to begin in FY2019.」

    The first-stage oxygen-blown IGCC technology demonstration test at Osaki CoolGen began in March 2017, and equipment design is under way for the second stage.
  6. FY2016First statedAnnual report

    「To continue using coal while addressing climate change, the company is promoting the development of more efficient oxygen-blown integrated coal gasification combined cycle (oxygen-blown IGCC) technology and conducting research and development into technologies such as carbon capture and storage (CCS), with the aim of achieving further decarbonization.」

    The first-stage demonstration at Osaki CoolGen, scheduled to begin in March 2017, and the second-stage demonstration, scheduled to begin in FY2019, are being advanced.
Moved together

"Development and Expansion of the Wind Power Generation Business" moved the same way as this thread, in the same document, in 3 of its 6 moves.

332222★123456
  1. ★This thread
  2. 1Development and Expansion of the Wind Power Generation Business3×
  3. 2Managing Growth and Financial Soundness Using J-POWER EBITDA and Interest-Bearing Debt Multiples3×
  4. 3Growth in overseas power generation operations and expansion of overseas equity-method generation capacity2×
  5. 4Fair and Transparent Management and Thorough Compliance2×
  6. 5Contributing to sustainable development through a stable energy supply2×
  7. 6Expansion of Renewable Energy Deployment2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Electric Power Development's next results are scheduled for 2026-10-30. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.