Construction of the Ishikariwan Shinko LNG-Fired Power Plant
First written in FY2016. 9 of 17 entries say "Advanced", first in FY2017-Q1. Latest entry: FY2026.
0 other companies' latest entry also says "Reframed".
- FY2026ReframedAnnual report
「We will steadily work toward the start of operations of Ishikariwan Shinko Power Station Units 2 and 3, LNG-fired power plants with planned output of 580 MW each, scheduled to begin operations in fiscal 2030 and fiscal 2033, respectively.」
For Ishikariwan Shinko LNG-fired Units 2 and 3, the management vision sets planned output at 580 MW each and the start of operations at fiscal 2030 for Unit 2 and fiscal 2033 for Unit 3. The facility plan also lists March 2031 for Unit 2 and March 2034 for Unit 3 as the scheduled start months. - 2026-05-26AdvancedGeneral Meetings of Shareholders
「We will steadily work toward the commencement of operations at Units 2 and 3 of the Ishikariwan Shinko Power Station, each with a planned output of 580,000 kW. Unit 2 is scheduled to begin operations in FY2030 and Unit 3 in FY2033.」
The planned start dates for Units 2 and 3 were provided, along with specific progress against the previous plan and future initiatives. - FY2024RaisedAnnual report
「Ishikariwan Shinko (new construction: LNG-fired power generation) 1,138,800 Unit 2 (569,400) May 2027 FY2030 Unit 3 (569,400) March 2034 December 2037」
For Ishikariwan Shinko LNG-fired Unit 2, the plan has been brought forward from the previously indicated start of construction in March 2031 and start of operations in December 2034 to start of construction in May 2027 and start of operations in fiscal 2030. - FY2023SoftenedAnnual report
「Ishikariwan Shinko (new construction: LNG-fired power generation) 1,138,800 Unit 2 (569,400) March 2031 December 2034 Unit 3 (569,400) March 2034 December 2037」
The scheduled construction starts and operating dates for Units 2 and 3 of the Ishikariwan Shinko LNG-fired power plant were pushed back from the plan previously presented. Unit 2 is scheduled to begin construction in March 2031 and operations in December 2034, while Unit 3 is scheduled to begin construction in March 2034 and operations in December 2037. - FY2022RaisedAnnual report
「Ishikariwan Shinko (new construction: LNG-fired power generation) 1,138,800 Unit 2 (569,400) March 2027 December 2030 Unit 3 (569,400) March 2032 December 2035」
Following the start of commercial operation of Unit 1, the company presented construction plans and start dates for Units 2 and 3 of the Ishikariwan Shinko LNG-fired power plant, with combined output of 1,138,800kW, thereby expanding the scope of the project. - FY2019AchievedAnnual report
「In February of this year, Unit 1 of the Ishikariwan Shinko Power Plant, Hokkaido's first large-scale LNG combined-cycle power plant, began commercial operation. The unit has output of 56.94万kW.」
Unit 1 of the Ishikariwan Shinko Power Plant began commercial operation in February 2019, achieving the planned start of operations for the LNG-fired power plant. - FY2019-Q3AdvancedAnnual report
「For Unit 1 of the Ishikariwan Shinko Power Plant, the company's first LNG-fired power plant, the comprehensive commissioning schedule was brought forward and power generation began so that the unit could be used as emergency generating capacity during winter, when electricity supply and demand are tight. The company will make every effort to begin commercial operation in February 2019.」
The company brought forward the comprehensive commissioning schedule and began power generation, progressing to the stage of preparing for commercial operation in February 2019. - FY2019-Q1AdvancedAnnual report
「This was due to an increase in electricity business fixed assets from the capitalization of facilities following the amendment of the Ministerial Ordinance on Provisions for Decommissioning Nuclear Power Facilities, as well as an increase in construction in progress for fixed assets, including construction of Unit 1 of the Ishikariwan Shinko Power Plant, partly offset by a decrease in cash and deposits.」
Construction in progress for fixed assets, including construction of Unit 1 of the Ishikariwan Shinko Power Plant, increased, continuing to indicate progress in construction investment. - FY2018RestatedAnnual report
「The company will steadily continue construction of Unit 1 of the Ishikariwan Shinko Power Plant, its first LNG-fired power plant, with the aim of beginning commercial operation in February 2019.」
The company is reaffirming the plan to begin commercial operation of Unit 1 of the Ishikariwan Shinko Power Plant in February 2019 and to continue construction. - FY2018-Q3AdvancedAnnual report
「At the end of the third quarter of the current consolidated fiscal year, assets totaled ¥1,903.837 billion, up ¥7.4298 billion from the end of the previous consolidated fiscal year. This was due mainly to increases in construction in progress for fixed assets, including the construction of Unit 1 of the Ishikariwan Shinko Power Plant, and in cash and deposits, despite a decline in electricity business fixed assets due to depreciation.」
Construction in progress for fixed assets, including construction of Unit 1 of the Ishikariwan Shinko Power Plant, increased, continuing to indicate progress in construction investment. - FY2018-Q2AdvancedAnnual report
「At the end of the second quarter of the current consolidated fiscal year, assets totaled ¥1,876.330 billion, up ¥4.6790 billion from the end of the previous consolidated fiscal year. This was due mainly to increases in construction in progress for fixed assets, including the construction of Unit 1 of the Ishikariwan Shinko Power Plant, and in cash and deposits, despite a decline in electricity business fixed assets due to depreciation.」
Construction in progress for fixed assets, including construction of Unit 1 of the Ishikariwan Shinko Power Plant, increased, confirming continued progress in construction investment. - FY2018-Q1AdvancedAnnual report
「At the end of the first quarter of the current consolidated fiscal year, assets totaled ¥1,870.643 billion, up ¥4.1104 billion from the end of the previous consolidated fiscal year. This was due mainly to increases in construction in progress for fixed assets, including the construction of Unit 1 of the Ishikariwan Shinko Power Plant, and in cash and deposits, despite a decline in electricity business fixed assets due to depreciation.」
Construction in progress for fixed assets related to construction of Unit 1 of the Ishikariwan Shinko Power Plant increased from the end of the previous fiscal year, continuing to indicate progress in construction investment. - FY2017RestatedAnnual report
「For power generation facilities, the company aims to build a balanced power generation mix and operate its facilities efficiently, based on securing a stable long-term electricity supply, maintaining economic efficiency and long-term price stability, and giving consideration to global environmental conservation. It will also steadily advance safety measures at the Tomari Power Plant.」
For Unit 1 of the Ishikariwan Shinko Power Plant, the plan to begin commercial operation in February 2019 and the associated construction investment continue to be indicated. - FY2017-Q3AdvancedAnnual report
「At the end of the third quarter of the current consolidated fiscal year, assets totaled ¥1,802.025 billion, down ¥2.4116 billion from the end of the previous consolidated fiscal year. This was despite an increase in construction in progress for fixed assets, including the construction of Unit 1 of the Ishikariwan Shinko Power Plant, as electricity business fixed assets declined due to depreciation and the reserve for spent-fuel reprocessing and other costs included in investments and other assets was drawn down.」
Construction in progress for fixed assets related to construction of Unit 1 of the Ishikariwan Shinko Power Plant continued to increase, indicating that construction was progressing. - FY2017-Q2AdvancedAnnual report
「At the end of the second quarter of the current consolidated fiscal year, assets totaled ¥1,799.762 billion, down ¥2.6379 billion from the end of the previous consolidated fiscal year. This was despite an increase in construction in progress for fixed assets, including the construction of Unit 1 of the Ishikariwan Shinko Power Plant, as electricity business fixed assets declined due to depreciation and cash and deposits decreased.」
Construction in progress for fixed assets related to construction of Unit 1 of the Ishikariwan Shinko Power Plant continued to increase, indicating that construction was progressing. - FY2017-Q1AdvancedAnnual report
「At the end of the first quarter of the current consolidated fiscal year, assets totaled ¥1,807.199 billion, down ¥1.8942 billion from the end of the previous consolidated fiscal year. This was despite an increase in construction in progress for fixed assets, including the construction of Unit 1 of the Ishikariwan Shinko Power Plant, as electricity business fixed assets declined due to depreciation and cash and deposits decreased.」
The increase in construction in progress for fixed assets related to construction of Unit 1 of the Ishikariwan Shinko Power Plant was disclosed, indicating that construction was continuing. - FY2016First statedAnnual report
「The company will steadily advance construction of Unit 1 of the Ishikariwan Shinko Power Plant, scheduled to begin commercial operation in February 2019, and expansion of the Hokuto-Honshu interconnection facility, scheduled to begin operating in March 2019.」
The Ishikariwan Shinko LNG-fired power plant has total output of 1,708,200kW, including 569,400kW for Unit 1, which is scheduled to begin commercial operation in February 2019.