Hokkaido Electric Power Company (9509) · TargetRestatedLatest M&A and Subsidiary Changes (2026-10-09): "Advanced"

Early Restart and Safety Improvements at the Tomari Nuclear Power Station

First written in FY2016. 13 of 19 entries say "Advanced", first in FY2018. Latest entry: 2026-10-09.

19entries
11years
2from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2016 – FY2017AdvancedFY2019 – FY2022-Q2AdvancedFY2023 – 2026-05-262016: 120162017: 120172018: 120182019: 220192020: 020202021: 220212022: 320222023: 220232024: 320242025: 120252026: 32026
Same theme, other companies
Early restart and safety improvements at the Tomari Nuclear Power StationA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. 2026-10-09AdvancedM&A and Subsidiary Changes

    「当社は,2026 年 7 月 30 日付で開示した「泊発電所における防潮堤設置工事の完了時期について」において,工事の完了時期を 2027 年 8 月とし,工事費の変更額については精査中としておりましたが,本日,工事の完了時期の決定に伴う工事費が 1,255 億円に決定いたしましたので,お知らせいたします。」

    泊発電所の防潮堤設置工事について、完了時期が2027年8月と決定されたことに伴い、工事費1,255億円が確定した。工事の工程および費用に関する具体化が進んだ。
  2. FY2026RestatedAnnual report

    「For Unit 3 of the Tomari Nuclear Power Station, we will devote all available resources to the approval of the design and construction plan, the review of approval for changes to the operational safety program, pre-use operator inspections, and safety-related construction including the seawall, with a view to restarting the unit as early as possible in 2027.」

    Even after obtaining approval for the change to the reactor installation in July 2025, the company has reaffirmed its policy of proceeding with the remaining licensing reviews, inspections, and construction work, including the seawall, with the aim of restarting operations as early as possible in 2027.
  3. 2026-05-26AdvancedGeneral Meetings of Shareholders

    「With a view to restarting Unit 3 of the Tomari Nuclear Power Station as early as possible in 2027, we will devote our full efforts to the review of applications for approval of the design and construction plan and approval of changes to the operational safety program, pre-use operator inspections, and safety improvement construction, including the seawall.」

    The restart timing was specified as “as early as possible in 2027,” and the remaining approval reviews, inspections and safety improvement construction were identified as specific initiatives.
  4. FY2026-H1AdvancedAnnual report

    「We are responding to the review of compliance with the new regulatory standards toward the restart of the Tomari Nuclear Power Station, and in July 2025 received permission from the Nuclear Regulation Authority to change the installation of Unit 3 at the Tomari Nuclear Power Station.」

    For Unit 3 of the Tomari Nuclear Power Station, the company obtained permission to change the installation in July 2025. It continues to respond to the review of approval for the design and construction plan, approval for changes to the operational safety program and other matters. The new seawall is targeted for completion in approximately 3 years from the start of construction, but the completion date has not been determined.
  5. FY2025-H1AdvancedAnnual report

    「We are responding to the review of compliance with the new regulatory standards toward the restart of the Tomari Nuclear Power Station. Explanations at review meetings have been completed for the assessment of the thickness of deposited pyroclastic material (volcanic ash), the assessment of the impact if the breakwater is damaged by a tsunami, measures to prevent drifting of vessels transporting fuel and other materials, and volcanic monitoring. We continue to address the remaining major review items, including the formulation of design-basis ground motion (Note 1) and the formulation of the design-basis tsunami (Note 2).」

    With respect to the compliance review, explanations have been completed for the thickness of volcanic ash deposits, the impact if the breakwater is damaged, measures to prevent drifting of vessels transporting fuel and other materials, and volcanic monitoring. The design-basis tsunami was deemed generally appropriate in November 2024, while the design-basis ground motion is being explained again to reflect the latest findings, and responses to the remaining review items are continuing.
  6. FY2024AdvancedAnnual report

    「In June 2023, during the review of compliance with the new regulatory standards for the Tomari Nuclear Power Station, we received an assessment that the design-basis ground motion had been examined in a generally appropriate manner. We will continue to devote all available resources to the other review items toward achieving an early restart. We will also steadily carry out the construction to install a new seawall, which began in March 2024, while actively communicating information about the status of the review and our initiatives.」

    The company received an appropriateness assessment for the design-basis ground motion and began construction to install a new seawall in March 2024. The review response and safety measures toward an early restart have made concrete progress.
  7. FY2024-Q3AdvancedAnnual report

    「We have positioned safety assurance at the Tomari Nuclear Power Station as our top management priority and, under the president's leadership, are working to further improve safety based on the Safety Improvement Plan. Specifically, in addition to complying with the new regulatory standards for nuclear power stations, we are undertaking safety-related construction to further improve safety and reliability, conducting nuclear emergency preparedness drills assuming severe accidents and other scenarios, diversifying safety measures, and strengthening and enhancing systems for responding to severe accidents and other events. We are also responding to the review of compliance with the new regulatory standards toward the restart of the Tomari Nuclear Power Station. The assessment of the combination of tsunamis caused by earthquakes and tsunamis caused by landslides on land was deemed to have been examined in a generally appropriate manner. With respect to the seawall design policy, we completed the explanation of the assessment results regarding the structural feasibility of the seawall and the matters pointed out, and there were no matters requiring attention. We continue to address such matters as the formulation of the design-basis tsunami, the assessment of the possibility of volcanic activity, the assessment of the thickness of deposited pyroclastic material (volcanic ash), the assessment of the impact of drifting objects from vessels transporting fuel and other materials, and the assessment of the impact if the breakwater is damaged by a tsunami.」

    While continuing safety-related construction, emergency preparedness drills and the strengthening of response systems, the company received an appropriateness assessment for the combined tsunami assessment and completed its explanation of the seawall design policy with no matters requiring attention. Responses to the remaining review items are continuing.
  8. FY2023AdvancedAnnual report

    「In October 2022, during the review of compliance with the new regulatory standards for the Tomari Nuclear Power Station, we received an assessment that the assessment of seismic motion developed without specifying an earthquake source had been examined in a generally appropriate manner.」

    In the compliance review, the assessment of seismic motion developed without specifying an earthquake source received a new assessment of its appropriateness. Responses to other review items and efforts toward an early restart are continuing.
  9. FY2023-Q3RestatedAnnual report

    「We have positioned safety assurance at the Tomari Nuclear Power Station as our top management priority and, under the president's leadership, are working to further improve safety based on the Safety Improvement Plan.」

    The company continues to address safety improvement plans, safety-related construction, emergency preparedness drills and the compliance review, with safety assurance at the Tomari Nuclear Power Station as its top priority.
  10. FY2023-Q2AdvancedAnnual report

    「Following the enforcement of the new regulatory standards, we submitted applications for permission to change the installation of nuclear reactors and other applications and have been responding to the compliance review. The re-evaluation of the tsunami caused by earthquakes assumed in the eastern margin of the Sea of Japan and the assessment of seismic motion developed without specifying an earthquake source were deemed to have been examined in a generally appropriate manner. We are continuing to address such matters as the assessment of design-basis ground motion, the combined assessment of tsunamis caused by earthquakes and tsunamis caused by landslides on land, the assessment of tsunamis caused by active faults assumed northwest offshore of the Shakotan Peninsula, the assessment of the possibility of volcanic activity, the assessment of the thickness of deposited pyroclastic material (volcanic ash), the assessment of the impact of soil liquefaction beneath the seawall caused by earthquakes, and the assessment of the impact if the breakwater is damaged by a tsunami.」

    In the compliance review, in addition to the re-evaluation of tsunamis along the eastern margin of the Sea of Japan, the assessment of seismic motion developed without specifying an earthquake source was also deemed to have been examined in a generally appropriate manner. Responses to review items involving design-basis ground motion, tsunamis, volcanoes and soil liquefaction, among others, are continuing.
  11. FY2023-Q1AdvancedAnnual report

    「Following the enforcement of the new regulatory standards, we submitted applications for permission to change the installation of nuclear reactors and other applications and have been responding to the compliance review. We received an assessment that the re-evaluation of the tsunami caused by earthquakes assumed in the eastern margin of the Sea of Japan had been generally appropriate.」

    With respect to the compliance review for the Tomari Nuclear Power Station, the re-evaluation of the tsunami caused by earthquakes assumed in the eastern margin of the Sea of Japan was deemed to have been examined in a generally appropriate manner, marking progress in the review process.
  12. FY2022RestatedAnnual report

    「In July 2021, during the review of compliance with the new regulatory standards for the Tomari Nuclear Power Station, the Nuclear Regulation Authority assessed the activity of faults within the power station site, which we had identified as the top-priority issue, as having been examined in a generally appropriate manner. We will continue to devote all available resources to the other major review items as well and proceed with measures toward the early restart of the Tomari Nuclear Power Station, with safety assurance as the overriding priority.」

    Based on the assessment of the activity of faults within the site, the company continues to address other review items, safety measures and the early restart.
  13. FY2022-Q2AdvancedAnnual report

    「Following the enforcement of the new regulatory standards, we submitted applications for permission to change the installation of nuclear reactors and other applications and have been responding to the compliance review. In July of that year, we received an assessment that the examination of the activity of faults within the power station site had been generally appropriate, and in October that the assessment of seismic motion caused by faults northwest offshore of the Shakotan Peninsula had been generally appropriate.」

    Following the assessment of the activity of faults within the site, the assessment of seismic motion caused by faults northwest offshore of the Shakotan Peninsula was also deemed generally appropriate, marking progress in the response to the compliance review.
  14. FY2022-Q1AdvancedAnnual report

    「Following the enforcement of the new regulatory standards, we submitted applications for permission to change the installation of nuclear reactors and other applications and have been responding to the compliance review. In July of that year, we received an assessment that the examination of the activity of faults within the power station site had been generally appropriate.」

    With respect to the compliance review for the Tomari Nuclear Power Station, concrete progress was demonstrated when the assessment of the activity of faults within the power station site was deemed generally appropriate. Responses to other assessment issues involving earthquakes, tsunamis, volcanoes and soil liquefaction, among others, are continuing.
  15. FY2019AdvancedAnnual report

    「To achieve the early restart of the Tomari Nuclear Power Station, we will conduct additional investigations into the activity of faults within the site, the top-priority issue in the review of compliance with the new regulatory standards, compile the results of our examination as soon as possible based on the data obtained, and explain them at review meetings.」

    With respect to the review of the Tomari Nuclear Power Station, the company is pursuing a specific response in the form of additional investigations into the activity of faults within the site.
  16. FY2019-Q3RestatedAnnual report

    「Alongside the early restart of the Tomari Nuclear Power Station, we will work to establish a highly competitive power generation mix for the future and seek to improve profitability by pursuing an integrated business strategy across the generation and retail businesses.」

    The company has reaffirmed its policy of pursuing the early restart of the Tomari Nuclear Power Station together with the establishment of a highly competitive power generation mix and improved profitability.
  17. FY2018AdvancedAnnual report

    「With a strong determination never to cause an accident like the one at the Fukushima Daiichi Nuclear Power Station, we have formulated the Tomari Nuclear Power Station Safety Improvement Plan to further reduce nuclear risks. In addition to complying with the new regulatory standards, we will make continuous efforts to achieve the world's highest level of safety, or excellence.」

    In addition to its policy on restarting the Tomari Nuclear Power Station, the company formulated a safety improvement plan and gave concrete form to initiatives aimed at achieving the world's highest level of safety.
  18. FY2017RestatedAnnual report

    「We are examining issues including the coastal landform on the west coast of the Shakotan Peninsula identified in the review of compliance with the new regulatory standards, the impact of a tsunami on the breakwater and earthquake-induced soil liquefaction beneath the seawall, and will devote all available resources to the restart of the Tomari Nuclear Power Station.」

    The company has reaffirmed its efforts toward an early restart by listing review issues and addressing them through safety-related construction, maintenance of facility soundness and responses to the review process.
  19. FY2016First statedAnnual report

    「To achieve the earliest possible restart of the Tomari Nuclear Power Station, with safety assurance as the overriding priority, we will establish a company-wide support structure so that confirmation by the Nuclear Regulation Authority can be obtained as soon as possible, and shorten the schedule by making maximum use of precedents.」

    The company has set out the early restart as a goal and identified work to comply with the new regulatory standards, responses to the review process and confirmation of the soundness of facilities that have been shut down for an extended period as measures to achieve it.
Moved together

"Expansion into Electricity Sales Outside Hokkaido and the Gas Supply Business" moved the same way as this thread, in the same document, in 9 of its 19 moves.

976665★123456
  1. ★This thread
  2. 1Expansion into Electricity Sales Outside Hokkaido and the Gas Supply Business9×
  3. 2Sales Strategies and Value-Added Services Tailored to Customer Needs7×
  4. 3Improving Earnings and Strengthening the Financial Base6×
  5. 4Decline in Electricity Sales Volumes Due to Competition, Economic Conditions and Energy Conservation6×
  6. 5Stable Dividends and the Use of Retained Earnings to Strengthen the Financial Position and Fund Capital Investment6×
  7. 6Return to ordinary profitability and resumption of dividend payments5×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Hokkaido Electric Power Company's next results are scheduled for 2026-10-30. Read the earnings preview It last moved in the M&A and Subsidiary Changes of 2026-10-09: "Advanced".
Early Restart and Safety Improvements at the Tomari Nuclear Power Station | Hokkaido Electric Power Company,Incorporated (9509) | Komori