Komori
Hokkaido Electric Power Company (9509) · InitiativeRestated

Enhancement of the Hokkaido-Honshu Interconnection Facilities

First written in FY2016. 5 of 9 entries say "Restated". Latest entry: FY2026.

9entries
11years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2016 – FY2017AchievedFY2019 – FY2022RestatedFY2023 – FY20262016: 120162017: 120172018: 220182019: 220192020: 020202021: 020212022: 120222023: 120232024: 020242025: 020252026: 12026
Same theme, other companies
Integrated development of power sources and transmission and substation networksA theme 4 companies write about · 0 as a headwind · 9 as a tailwind

1 other company's latest entry also says "Restated".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2026RestatedAnnual report

    「For transmission and distribution facilities, we will expand interregional interconnection facilities and build new transmission lines and other facilities to serve new demand and connect power plants, while appropriately addressing facility aging and seeking to maintain supply reliability and achieve efficient facility development.」

    The policy of developing interregional interconnection facilities, including the expansion of the Hokuto-Imabetsu DC Trunk Line, and transmission lines for new demand and power plant connections remains in place.
  2. FY2023RestatedAnnual report

    「Hokuto-Imabetsu DC Trunk Line (expansion) Hokuto Converter Station–Imabetsu Converter Station DC 250 122 1→2 October 2023 March 2028」

    The plan to expand the Hokuto-Imabetsu DC Trunk Line from 1 circuit to 2 circuits and begin operations in March 2028 has been reaffirmed.
  3. FY2022RaisedAnnual report

    「Hokuto-Imabetsu DC Trunk Line (expansion) Hokuto Converter Station–Imabetsu Converter Station DC 250 122 1→2 March 2024 March 2028」

    The plan calls for expanding the Hokuto-Imabetsu DC Trunk Line from 1 circuit to 2 circuits, in addition to the existing Hokkaido-Honshu interconnection facilities.
  4. FY2019AchievedAnnual report

    「Furthermore, the New Hokkaido-Honshu Interconnection Facility, with a capacity of 300 MW, began operations in March this year to improve our ability to respond to the risk of emergency shutdowns of power sources in Hokkaido, increasing interconnection capacity between Hokkaido and Honshu from 600 MW to 900 MW.」

    The 300 MW New Hokkaido-Honshu Interconnection Facility began operations in March 2019, increasing interconnection capacity from 600 MW to 900 MW.
  5. FY2019-Q3RestatedAnnual report

    「In addition to maintaining facilities using data accumulated across our power facilities and new insights, we will proceed with construction of the New Hokkaido-Honshu Interconnection Facility, our first DC interconnection facility, which is scheduled to begin operations in March 2019, to ensure a stable power supply.」

    The plan to begin operations of the New Hokkaido-Honshu Interconnection Facility in March 2019 and the maintenance policy using facility data and insights have been reaffirmed.
  6. FY2018RestatedAnnual report

    「We will also proceed with construction of the New Hokkaido-Honshu Interconnection Facility, our first DC interconnection facility, to ensure a stable power supply.」

    The policy of ensuring a stable power supply through the expansion and construction of the Hokkaido-Honshu interconnection facilities remains in place.
  7. FY2018-Q3AdvancedAnnual report

    「Donan Trunk Line (Connection to Hokuto Converter Station) Nishifutaba Switching Station – Hokuto Converter Station 275 kV 0.3 2 circuits May 2016 October 2017 (Line 2) November 2017 (Line 1) Hokuto Trunk Line (Connection to Hokuto Converter Station) Hokuto Converter Station – Ono Converter Station 275 kV 0.6 2 circuits May 2016 October 2017 (Line 2) November 2017 (Line 1)」

    The 275 kV, 2-circuit connection lines for the Donan and Hokuto trunk lines, related to the expansion of the Hokkaido-Honshu interconnection facilities, began operations in October and November 2017.
  8. FY2017RestatedAnnual report

    「For transmission and distribution facilities, we will develop core transmission and transformation facilities and expand the Hokkaido-Honshu interconnection facilities while coordinating with power development plans and other initiatives, and will seek to maintain supply reliability while improving efficiency.」

    The plan to expand the Hokkaido-Honshu interconnection facilities by 300 MW, with operations scheduled to begin in March 2019, remains in place.
  9. FY2016First statedAnnual report

    「We will steadily proceed with construction of the 300 MW expansion of the Hokkaido-Honshu interconnection facilities, scheduled to begin operations in March 2019.」

    The plan calls for a 300 MW expansion, including AC/DC converter facilities such as the Hokuto and Imabetsu converter stations.
Moved together

"Construction of the Ishikariwan Shinko LNG-Fired Power Plant" moved the same way as this thread, in the same document, in 3 of its 9 moves.

322222★123456
  1. ★This thread
  2. 1Construction of the Ishikariwan Shinko LNG-Fired Power Plant3×
  3. 2Improving Earnings and Strengthening the Financial Base2×
  4. 3Efficiency improvements in equipment maintenance, business operations, and materials and equipment costs2×
  5. 4Expansion into Electricity Sales Outside Hokkaido and the Gas Supply Business2×
  6. 5Interest-bearing debt and fluctuations in market interest rates2×
  7. 6Expansion of Renewable Energy Deployment2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Hokkaido Electric Power Company's next results are scheduled for 2026-10-30. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Enhancement of the Hokkaido-Honshu Interconnection Facilities | Hokkaido Electric Power Company,Incorporated (9509) | Komori