Komori
Chubu Electric Power Company (9502) · RiskWorsened

Impact of compliance violations on public trust and results

First written in FY2017. 5 of 13 entries say "Worsened", first in FY2023-Q3. Latest entry: FY2026.

13entries
10years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2017 – FY2019MaterialisedFY2021 – FY2024-Q1WorsenedFY2024-Q3 – FY2025-H12017: 120172018: 120182019: 120192020: 020202021: 220212022: 120222023: 320232024: 220242025: 120252026: 12026
Same theme, other companies
Reputational damage risk from non-compliance with laws and regulationsA theme 119 companies write about · 119 as a headwind · 0 as a tailwind

Chubu Electric Power Company moved to the "Worse" side of this theme in 2021, 4 years before the typical company in this theme (2025).

The whole theme swung hardest in 2024: 8 of 54 companies on the "Worse" side.

3 other companies' latest entry also says "Worsened".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 119 companies compared. The sentences above are computed from all 119.
Full recordFilings, disclosures and news, newest first
  1. FY2026WorsenedAnnual report

    「In the Nuclear Regulation Authority’s review of compliance with the new regulatory standards for Units 3 and 4 of the Hamaoka Nuclear Power Station under the Act on the Regulation of Nuclear Source Material, Nuclear Fuel Material and Reactors, an incident occurred in which the seismic motion of the Hamaoka Nuclear Power Station had been evaluated using an inappropriate method.」

    In addition to the Antimonopoly Act-related matters, the inappropriate evaluation of seismic motion at Hamaoka is described as a compliance and internal control event, and measures are being advanced through an external investigation committee and a review meeting for fundamental reconstruction.
  2. FY2025MitigatedAnnual report

    「In addition to the “Measures to Ensure Thorough Compliance” announced on 7 April 2023, we and 中部電力ミライズ㈱ are implementing the “Measures to Strengthen the Measures to Ensure Thorough Compliance” announced on 4 March 2024, striving to ensure that no further violations of the Antimonopoly Act occur and that there is no cause for suspicion of such violations.」

    As Antimonopoly Act-related matters continue, the company is implementing measures to ensure thorough compliance and measures to strengthen them, and is taking steps to prevent recurrence and suspicion of violations.
  3. FY2025-H1WorsenedAnnual report

    「On 4 March 2024, in connection with the supply of city gas to large-volume customers in the Chubu region, we received from the committee a surcharge payment order under the Antimonopoly Act, while 中部電力ミライズ received from the committee a cease-and-desist order and a surcharge payment order under the Act. In addition, 中部電力ミライズ received from the committee a warning concerning the supply of city gas for household use and other matters in the Chubu region, while 中部電力ミライズ and its subsidiary 株式会社シーエナジー each received from the committee a warning concerning the supply of liquefied natural gas in Aichi, Gifu and Mie prefectures.」

    The disclosure states that, in addition to the surcharge payment order and cease-and-desist order concerning city gas supply in the existing Antimonopoly Act-related matters, warnings were also received concerning the supply of city gas for household use and liquefied natural gas.
  4. FY2024-Q3WorsenedAnnual report

    「On 20 December 2023, in connection with the supply of city gas to large-volume customers in the Chubu region, we received from the committee a notice of hearing of opinions concerning a draft surcharge payment order under the Antimonopoly Act, while 中部電力ミライズ received from the committee notices of hearing of opinions concerning a draft cease-and-desist order and a draft surcharge payment order under the Act.」

    In addition to the orders and other measures concerning the existing electricity supply, we also received a notice of hearing of opinions concerning a draft surcharge payment order and related matters for the supply of city gas to large-volume customers. In response, we recorded ¥26 million as an extraordinary loss for the provision for losses related to the Antimonopoly Act.
  5. FY2024-Q2MitigatedAnnual report

    「Regarding each order, the company and Chubu Electric Power Miraiz decided to seek a fair judicial determination because they disagreed with the Japan Fair Trade Commission on the findings of fact and the interpretation of the law, and filed actions for rescission on 25 September of the same year. Regarding the surcharge, the company recorded a loss related to the Antimonopoly Act as an extraordinary loss in the previous fiscal year and paid the surcharge by the payment deadline.」

    The company states that it filed an action for rescission on 25 September 2023 regarding the surcharge payment orders and other orders related to the Antimonopoly Act, and paid the surcharge by the payment deadline. It also continues to implement measures to ensure thorough compliance and prevent recurrence.
  6. FY2024-Q1WorsenedAnnual report

    「On 30 March 2023, regarding the supply of extra-high-voltage and high-voltage electricity in the Chubu region and elsewhere, the company received from the Japan Fair Trade Commission an order to pay a surcharge under the Antimonopoly Act, while Chubu Electric Power Miraiz received a cease-and-desist order and an order to pay a surcharge under the Act. Because the company and Chubu Electric Power Miraiz disagree with the Commission on the findings of fact and the interpretation of the law relating to each order, they decided to file actions for rescission and seek a fair judicial determination. Following these orders, the company and Chubu Electric Power Miraiz were subject to measures by the Ministry of Economy, Trade and Industry and other authorities, including suspension of subsidies and other grants and suspension of nomination for contracts. On 14 July 2023, Chubu Electric Power Miraiz received an order from the Minister of Economy, Trade and Industry to improve its operations under the Electricity Business Act, and on 28 July of the same year submitted a report addressing that order.」

    The matter progressed from the Japan Fair Trade Commission's on-site inspection stage to the receipt of surcharge payment and cease-and-desist orders. The impact of and response to the compliance matter have been specified in detail, including the policy of filing actions for rescission, suspension of subsidies and other grants and suspension of nomination, and receipt of and reporting on an order to improve operations under the Electricity Business Act.
  7. FY2023-Q3WorsenedAnnual report

    「On 1 December 2022, the company received from the Japan Fair Trade Commission a notice of an opportunity to state its views regarding a draft surcharge payment order under the Antimonopoly Act concerning the supply of extra-high-voltage and high-voltage electricity in the Chubu region and elsewhere. Chubu Electric Power Miraiz received separate notices of an opportunity to state its views regarding draft cease-and-desist orders and draft surcharge payment orders under the Antimonopoly Act.」

    Following the on-site inspections concerning suspected violations of the Antimonopoly Act, the company received a notice of an opportunity to state its views regarding a draft surcharge payment order, while Chubu Electric Power Miraiz received such notices regarding draft cease-and-desist and surcharge payment orders. The company also recorded ¥27.555 billion in provision expense for losses related to surcharge payments.
  8. FY2022-Q3MaterialisedAnnual report

    「On 5 October of the same year, the Japan Fair Trade Commission conducted an on-site inspection of the offices of the company and Chubu Electric Power Miraiz Co., Inc., among others, on suspicion of violations of the Antimonopoly Act in connection with the supply of extra-high-voltage and high-voltage electricity and city gas for large-volume customers in the Chubu region.」

    The company states that, following the on-site inspection on 13 April, it also underwent an on-site inspection by the Japan Fair Trade Commission on 5 October in connection with suspected violations of the Antimonopoly Act.
  9. FY2022-Q2MaterialisedAnnual report

    「Against this background, on 13 April 2021, the Japan Fair Trade Commission conducted an on-site inspection of the offices of the company and Chubu Electric Power Miraiz Co., Inc., among others, on suspicion of violations of the Antimonopoly Act in connection with the supply of extra-high-voltage and high-voltage electricity in the Chubu region and elsewhere, and the supply of low-voltage electricity and city gas in the Chubu region and elsewhere. On 5 October of the same year, the Commission also conducted an on-site inspection of the offices of the company and Chubu Electric Power Miraiz Co., Inc., among others, on suspicion of violations of the Antimonopoly Act in connection with the supply of extra-high-voltage and high-voltage electricity and city gas for large-volume customers in the Chubu region.」

    The company states that, following the on-site inspection in April, it also underwent an on-site inspection by the Japan Fair Trade Commission in October in connection with suspected violations of the Antimonopoly Act.
  10. FY2021MaterialisedAnnual report

    「Against this background, on 13 April 2021, the Japan Fair Trade Commission conducted an on-site inspection of the offices of the company and Chubu Electric Power Miraiz Co., Inc., among others, on suspicion of violations of the Antimonopoly Act in connection with the supply of extra-high-voltage and high-voltage electricity in the Chubu region and elsewhere, and the supply of low-voltage electricity and city gas in the Chubu region.」

    In addition to the previously stated possibility of an impact on credit and business performance from compliance violations, the company describes the fact that the Japan Fair Trade Commission conducted an on-site inspection in connection with suspected violations of the Antimonopoly Act.
  11. FY2019RestatedAnnual report

    「However, if an event in violation of compliance requirements causes a decline in social credit or other consequences, business performance may be affected.」

    The company continues to describe the possibility of a decline in social credit and an impact on business performance due to compliance violations.
  12. FY2018RestatedAnnual report

    「However, if an event in violation of compliance requirements causes a decline in social credit or other consequences, business performance may be affected.」

    The company continues to identify the possibility of a decline in social credit and an impact on business performance due to compliance violations as a risk.
  13. FY2017First statedAnnual report

    「However, if an event in violation of compliance requirements causes a decline in social credit or other consequences, business performance may be affected.」

    The company identifies a decline in social credit and an impact on business performance resulting from compliance violations as an independent risk.
Moved together

"Fluctuations in electricity sales volumes and generation costs caused by economic conditions, temperature and precipitation" moved the same way as this thread, in the same document, in 8 of its 13 moves.

876554★123456
  1. ★This thread
  2. 1Fluctuations in electricity sales volumes and generation costs caused by economic conditions, temperature and precipitation8×
  3. 2Interest-bearing debt and fluctuations in market interest rates7×
  4. 3Fluctuations in fuel costs and procurement disruptions caused by fuel prices, foreign exchange rates and supplier conditions6×
  5. 4Impact on business performance from intensifying competition and changes in supply and demand5×
  6. 5Leakage of Personal and Other Sensitive Information5×
  7. 6Guarantee exposure relating to JERA and overseas power-generation businesses4×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Chubu Electric Power Company's next results are scheduled for 2026-10-29. Read the earnings preview
Impact of compliance violations on public trust and results | Chubu Electric Power Company,Incorporated (9502) | Komori