Construction of a New Hazardous Materials Warehouse in the Chubu Area
First written in FY2023. 1 of 3 entries say "Reframed", first in FY2024. Latest entry: FY2025.
0 other companies' latest entry also says "Achieved".
- FY2025AchievedAnnual report
「SANKYU INC. Komono, Mie District, Mie Logistics business Hokusei No. 3 Logistics Center (Hazardous Materials Warehouse) 1,154 October 2024 Warehouse area: approximately 4,000 m²」
The former Chubu Area Hazardous Materials Warehouse project was completed as the Hokusei No. 3 Logistics Center in October 2024. - FY2024Change in project name and scaleAnnual report
「SANKYU INC. Komono, Mie District, Mie Logistics business Hokusei No. 3 Logistics Center 1,252 344 Internal funds January 2024 September 2024 Total floor area: 3,879 m² Building: 4 single-story steel structures」
The former Chubu Area Hazardous Materials Warehouse project was renamed the “Hokusei No. 3 Logistics Center.” The planned investment was updated from ¥1,230 million to ¥1,252 million, and the scheduled completion from August to September 2024. - FY2023First statedAnnual report
「SANKYU INC. Komono, Mie District, Mie Logistics business Chubu Area Hazardous Materials Warehouse 1,230 - Internal funds January 2024 August 2024 Total floor area: 3,974 m² Building: 4 single-story steel structures」
The company first disclosed a plan to construct a new hazardous materials warehouse in Komono, Mie. The planned investment was ¥1,230 million, with construction scheduled to begin in January 2024 and be completed in August 2024.