Sankyu (9065) · InitiativeAdvanced

Reconstruction of the Toas General Logistics Center

First written in FY2023. 2 of 4 entries say "Advanced", first in FY2025. Latest entry: FY2026.

4entries
4years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2023SoftenedFY2024AdvancedFY2025 – FY20262023: 120232024: 120242025: 120252026: 12026
Same theme, other companies
Rebuilding of the Singapore Tuas Integrated Logistics CenterA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2026AdvancedAnnual report

    「Sankyu (Singapore) Pte. Ltd. Singapore Toas Logistics business Toas Logistics Center 14,899 13,786 Bank borrowings October 2023 January 2026 Total floor area: 38,380 m²」

    It was disclosed that ¥13,786 million of the planned investment of ¥14,899 million for the Toas logistics center in Singapore had been paid, bringing construction close to its scheduled completion date.
  2. FY2025AdvancedAnnual report

    「Toas Logistics Center 12,846 6,938 Bank borrowings October 2023 January 2026 Total floor area: 37,200 m²」

    Construction of the Toas logistics center in Singapore is progressing toward scheduled completion in January 2026, with ¥6,938 million of the planned investment of ¥12,846 million already paid.
  3. FY2024Postponement of scheduled completionAnnual report

    「Sankyu (Singapore) Pte. Ltd. Singapore Toas Logistics business Toas Logistics Center 12,846 1,172 Bank borrowings October 2023 January 2026 Total floor area: 37,200 m² Building: four-story reinforced concrete structure」

    The scheduled completion of the Toas Integrated Logistics Center was pushed back from September 2025 to January 2026, and the total floor area was updated from 37,975 m² to 37,200 m².
  4. FY2023First statedAnnual report

    「Sankyu (Singapore) Pte. Ltd. Singapore Toas Logistics business Rebuilding of the Toas Integrated Logistics Center 12,846 - Bank borrowings October 2023 September 2025 Total floor area: 37,975 m² Building: four-story reinforced concrete structure」

    The company first disclosed a plan to rebuild the logistics center in Toas, Singapore, at a planned investment of ¥12,846 million. Construction was scheduled to begin in October 2023 and be completed in September 2025, funded through bank borrowings.
Moved together

"Construction Cost Overruns and Construction Loss Risk" moved the same way as this thread, in the same document, in 3 of its 4 moves.

322222★123456
  1. ★This thread
  2. 1Construction Cost Overruns and Construction Loss Risk3×
  3. 2Positioning the current medium-term plan as a “medium-term plan for improving profitability”2×
  4. 3Building a Cost Structure That Can Win in the Market2×
  5. 4Cost Structure Reform through Cost Management by Expense Category and Productivity Improvement2×
  6. 5Advancing Plant Engineering through EPTC and 3PM2×
  7. 6Reviewing the Rationale for and Reducing Cross-Shareholdings2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Sankyu's next results are scheduled for 2026-10-30. Read the earnings preview