Establishment of the SANKYU Honmoku Logistics Center
First written in FY2023-Q2. 2 of 4 entries say "Softened", first in FY2023. Latest entry: FY2025.
No other company in this theme has enough history to compare yet.
- FY2025AchievedAnnual report
「SANKYU INC. Naka Ward, Yokohama, Kanagawa Logistics business Yokohama Logistics Center 3,880 March 2025 Warehouse area: 20,921 m² Building: four-story steel-reinforced concrete structure」
The facility planned as the Honmoku Logistics Center was completed as the Yokohama Logistics Center in March 2025. - FY2024Postponement of scheduled completionAnnual report
「SANKYU INC. Naka Ward, Yokohama, Kanagawa Logistics business Honmoku Logistics Center 3,904 - Internal funds March 2024 February 2025 Total floor area: 21,398 m² Building: four-story steel-reinforced concrete structure」
The scheduled completion of the Honmoku Logistics Center was pushed back by 1 month, from January 2025 to February 2025. - FY2023SoftenedAnnual report
「SANKYU INC. Naka Ward, Yokohama, Kanagawa Logistics business Honmoku Logistics Center 3,904 – Internal funds March 2024 January 2025 Total floor area: 21,398 m² Building: 4-story reinforced-concrete and steel-frame building」
The plan for the SANKYU Honmoku Logistics Center remains in place, but the scheduled completion was pushed back from August 2024 to January 2025. - FY2023-Q2First statedAnnual report
「SANKYU INC. Naka Ward, Yokohama Logistics business SANKYU Honmoku Logistics Center 3,904 - Internal funds June 2023 August 2024 Warehouse area: 21,398 m² Building: 4-story reinforced-concrete and steel-frame building」
The plan to construct the SANKYU Honmoku Logistics Center in Naka Ward, Yokohama, was disclosed for the first time. The planned investment was ¥3,904 million, with construction scheduled to begin in June 2023 and completion scheduled for August 2024. The warehouse area is 21,398 m².