Yaesu 2-chome Central District Type 1 Urban Redevelopment Project
First written in FY2022-Q2. 2 of 4 entries say "Advanced", first in FY2025-H1. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026AdvancedAnnual report
「Hankyu Hanshin Properties Corp. Yaesu 2-chome Central District Type 1 Urban Redevelopment Project 38,027 17,961 Internal funds and borrowings August 2024 Fiscal 2028」
The planned total investment for the Yaesu 2-chome Central District Redevelopment Project was updated to ¥38,027 million, with ¥17,961 million already paid, indicating progress toward completion in fiscal 2028. - FY2025-H1AdvancedAnnual report
「Hankyu Hanshin Properties Corp. Yaesu 2-chome Central District Type 1 Urban Redevelopment Project 36,551 Internal funds and borrowings August 2024 Fiscal 2028」
For the Yaesu 2-chome Central District redevelopment project, the planned investment amount was specified as ¥36,551 million, compared with previously being undetermined, and construction scheduled to begin in August 2024 was disclosed. Completion is scheduled for fiscal 2028, with funding to continue to come from internal funds and borrowings. - FY2022-Q3RestatedAnnual report
「Hankyu Hanshin Properties Corp. Yaesu 2-chome Central District Type 1 Urban Redevelopment Project Undetermined Internal funds and borrowings Fiscal 2024 Fiscal 2028」
The Group has continued to disclose its plan for the Yaesu 2-chome Central District Type 1 Urban Redevelopment Project, with the planned investment amount undetermined, construction scheduled to begin in fiscal 2024, completion scheduled for fiscal 2028, and funding from internal funds and borrowings. - FY2022-Q2First statedAnnual report
「Hankyu Hanshin Properties Corp. Yaesu 2-chome Central District Type 1 Urban Redevelopment Project Undetermined Internal funds and borrowings Fiscal 2024 Fiscal 2028」
The project was newly confirmed as a planned major capital investment. The planned investment amount is undetermined, funding will be from internal funds and borrowings, construction is scheduled to begin in fiscal 2024, and acquisition and completion are scheduled for fiscal 2028.