East Japan Railway Company (9020) · InitiativeAdvanced

Iidabashi Station Improvement Works

First written in FY2017-Q2. 4 of 5 entries say "Advanced", first in FY2017. Latest entry: FY2022.

5entries
7years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseAdvancedFY2017 – FY20222016: 12017: 120172018: 120182019: 120192020: 020202021: 020212022: 12022
Same theme, other companies
Iidabashi Station Improvement WorksA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2022AdvancedAnnual report

    「Iidabashi Station upgrade project 17,255 14,597 Internal funds Contributions June 2014 Fiscal 2022」

    The Iidabashi Station upgrade project maintained its planned total cost of ¥17,255 million and scheduled completion in fiscal 2022, while amounts paid to date increased to ¥14,597 million.
  2. FY2019AdvancedAnnual report

    「Iidabashi Station upgrade project 17,255 5,873」

    The Iidabashi Station upgrade project maintained its planned total cost of ¥17.255 billion and scheduled completion in fiscal 2022, while amounts paid to date reached ¥5.873 billion.
  3. FY2018AdvancedAnnual report

    「The Iidabashi Station upgrade project has a planned total cost of ¥17,255 million and is scheduled for completion in fiscal 2022. Amounts paid to date total ¥2,819 million.」

    The Iidabashi Station upgrade project maintained its planned total cost and scheduled completion in fiscal 2022, while amounts paid to date reached ¥2,819 million.
  4. FY2017AdvancedAnnual report

    「During the consolidated fiscal year, the company made capital investments totaling ¥506.7 billion overall, mainly in the transportation business.」

    For the Iidabashi Station upgrade project, the company maintained the planned total cost of ¥17,255 million and the scheduled completion in fiscal 2022. Amounts paid to date reached ¥2,210 million. The project remains part of the capital investment plan following commencement of the main construction work.
  5. FY2017-Q2First statedAnnual report

    「During the six-month period ended in the second quarter, the company commenced the Iidabashi Station upgrade project as part of transport improvements and other measures in the transportation business. The planned total cost of the project is ¥17,255 million, and completion is scheduled for fiscal 2022.」

    The company commenced the Iidabashi Station upgrade project as part of its capital investment plan for transport improvements, with a planned total cost of ¥17,255 million and completion scheduled for fiscal 2022.
Moved together

"Expanding customer touchpoints through the use of Suica, electronic money and ICT" moved the same way as this thread, in the same document, in 4 of its 5 moves.

444444★123456
  1. ★This thread
  2. 1Expanding customer touchpoints through the use of Suica, electronic money and ICT4×
  3. 2Achieving No. 1 Customer Satisfaction in the Railway Industry4×
  4. 3Energy and Environmental Strategy and Development of Northern Tohoku as a Renewable Energy Hub4×
  5. 4Railway System Innovation through ICT and Open Innovation4×
  6. 5Building disaster-resilient railways4×
  7. 6Plan for Accumulation and Drawdown of the Provision for Major Shinkansen Railway Repairs4×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
East Japan Railway Company's next results are scheduled for 2026-10-30. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Iidabashi Station Improvement Works | East Japan Railway Company (9020) | Komori