Direct access to central Tokyo through reciprocal through services with JR and Tokyu lines
First written in FY2016. 17 of 25 entries say "Restated". Latest entry: FY2024.
No other company in this theme has enough history to compare yet.
- FY2024RestatedAnnual report
「Through service with the JR lines began in November 2019 and with the Tokyu Line in March 2023. We will continue to pursue development along our railway lines while expanding our business outside these areas and overseas.」
With through service with the JR lines and Tokyu Line already in place, we continue to pursue the next measures, including development along our railway lines. - FY2023AchievedAnnual report
「In addition to the through-service operation with the JR Line, which opened in November 2019, through-service operation with the Tokyu Line began in March 2023, improving access to the Shinkansen and travel speed into central Tokyo and creating a broad-area network through seamless connectivity.」
Through service with the Tokyu Line began on 18 March 2023, providing access to central Tokyo following the JR lines. - FY2023-Q3AdvancedAnnual report
「Under these business conditions, preparations for the 18 March 2023 opening of the through-service operation with the Tokyu Line were pursued as an important project for future growth.」
The opening date for through-service operation with the Tokyu Line was specified as 18 March 2023, and the project progressed to the opening preparation stage. - FY2023-Q2RestatedAnnual report
「Under these business conditions, the plan for through-service operation with the Tokyu Line was pursued diligently as an important project for future growth,」
The plan for through-service operation with the Tokyu Line continues to be pursued as an important project for future growth. No new opening date or completion milestone was provided. - FY2023-Q1RestatedAnnual report
「Under these business conditions, the plan for through-service operation with the Tokyu Line was pursued diligently as an important project for future growth,」
The plan for through-service operation with the Tokyu Line continues to be pursued as an important project, but no new completion milestone, such as an opening, was provided. - FY2022AdvancedAnnual report
「The through-service operation between the Sotetsu and JR lines, which opened in November 2019, and the planned through-service operation between the Sotetsu and Tokyu lines in March 2023 are expected to improve convenience for residents along the Sotetsu Line and significantly enhance the area’s future prospects and potential.」
The opening of through-service operation with the Tokyu Line was explicitly scheduled for March 2023. Preparations for the opening also progressed, including the construction of 32 cars of the 21000 series for the Tokyu through line. - FY2022-Q3RestatedAnnual report
「Under these business conditions, the plan for through-service operation with the Tokyu Line was pursued diligently as an important project for future growth,」
The plan for through-service operation with the Tokyu Line continues to be pursued as an important project for future growth. No new opening date or completion milestone was provided. - FY2022-Q2RestatedAnnual report
「In the railway business, although passenger numbers were showing signs of recovery, the business environment remained challenging due to the impact of requests to refrain from going out amid the spread of COVID-19 and the widespread adoption of telework by companies. Under these business conditions, the plan for through-service operation with the Tokyu Line was pursued diligently as an important project for future growth,」
The plan for through-service operation with the Tokyu Line continues to be pursued as an important project for future growth. No new completion milestone, such as an opening, was reported. - FY2022-Q1RestatedAnnual report
「The plan for through-service operation with the Tokyu Line was pursued diligently as an important project for future growth,」
The plan for through-service operation with the Tokyu Line continues to be pursued as an important project, but no new opening date or completion milestone was provided. - FY2021-Q2RestatedAnnual report
「Under these business conditions, the plan for through-service operation with the Tokyu Line was pursued diligently as an important project for future growth,」
The plan for through-service operation with the Tokyu Line continues to be pursued as an important project for future growth, but no new opening date or completion milestone was provided. - FY2021-Q1RestatedAnnual report
「The plan for through-service operation with the Tokyu Line is also being pursued diligently.」
The plan for through-service operation with the Tokyu Line continues to be pursued, but no new opening date or completion milestone was provided. - FY2020-Q3AdvancedAnnual report
「In the railway business, the Sotetsu-JR Through Line opened on 30 November, and the timetable was revised on the same date.」
The Sotetsu-JR Through Line opened on 30 November 2019, and the timetable was also revised. The plan for through-service operation with the Tokyu Line remains ongoing. - FY2020-Q2RestatedAnnual report
「The planned through-service operation between the Sotetsu and JR lines on 30 November 2019 and between the Sotetsu and Tokyu lines in the second half of 2022 are expected to improve convenience for residents along the Sotetsu Line,」
The planned opening dates remain 30 November 2019 for the JR through-service operation and the second half of 2022 for the Tokyu through-service operation. - FY2020-Q1RestatedAnnual report
「Preparations are under way for the opening of the through-service operation with the JR Line, and the plan for through-service operation with the Tokyu Line is also being pursued diligently.」
The JR through-service operation remains in the opening preparation stage, while the Tokyu through-service operation continues to be pursued, but no new completion milestone was provided. - FY2019AdvancedAnnual report
「For the Sotetsu-JR Through Line project, the opening was set for 30 November 2019, and preparations for the opening, including inspections, audits, driver familiarization runs and various training programs, are being pursued diligently. For the Sotetsu-Tokyu Through Line project, with an opening targeted for the second half of fiscal 2022, tunnel boring is under way on the tunnels from Hazawa-Yokohama-Kokudai to Shin-Yokohama and from Shin-Tsunashima to Shin-Yokohama, as well as construction of the Shin-Yokohama Station (tentative name) and Shin-Tsunashima Station (tentative name), track work and other work.」
The opening of the JR through line was set for 30 November 2019, and the project progressed to the opening preparation stage. For the Tokyu through line, the second half of fiscal 2022 was set as the opening target, with progress reported on tunnel, station and track construction. - FY2019-Q3AdvancedAnnual report
「In the railway business, the inbound tracks were elevated as part of the grade-separation project near Hoshikawa and Tennocho stations, completing the elevation of the entire section between Hoshikawa and Tennocho stations. Renovation work at Hoshikawa and Tennocho stations was also pursued. In conjunction with the elevation work, the timetable was revised to improve travel speed and convenience. The plans for through-service operations with the JR and Tokyu lines are also being pursued diligently.」
The entire section between Hoshikawa and Tennocho stations was elevated and the timetable was revised. Meanwhile, the plans for through-service operations with the JR and Tokyu lines continue to be pursued. - FY2019-Q2RestatedAnnual report
「At the grade-separation project near Hoshikawa and Tennocho stations, work is proceeding toward elevating the inbound tracks following the elevation of the outbound tracks, while the plans for through-service operations with the JR and Tokyu lines are also being pursued diligently.」
The plans for through-service operations with the JR and Tokyu lines continue to be pursued, but no new opening date or completion milestone was provided. - FY2018-Q3RestatedAnnual report
「In addition to continuing to pursue the grade-separation project near Hoshikawa and Tennocho stations, we are also pursuing the plans for through-service operations with the JR and Tokyu lines.」
The plans for through-service operations with the JR and Tokyu lines continue to be pursued, but no new opening date or completion milestone was provided. - FY2018-Q2RestatedAnnual report
「In addition to continuing to pursue the grade-separation project near Hoshikawa and Tennocho stations, we are also pursuing the plans for through-service operations with the JR and Tokyu lines.」
The plans for through-service operations with the JR and Tokyu lines continue to be pursued, but no new opening date or completion milestone was provided. - FY2018-Q1RestatedAnnual report
「The planned future through-service operations between the Sotetsu and JR lines and between the Sotetsu and Tokyu lines are expected to improve convenience for residents along the Sotetsu Line and significantly enhance the area’s future prospects and potential.」
Through-service operations with the JR and Tokyu lines continue to be planned, but no new opening date or completion milestone was provided. - FY2017SoftenedAnnual report
「For the Sotetsu-JR Through Line project, with an opening targeted for the second half of fiscal 2019, civil engineering work on the Nishiya Tunnel between Nishiya and Hazawa has already been completed, and equipment work, including track and electrical work, is under way. For the Sotetsu-Tokyu Through Line project, with an opening targeted for the second half of fiscal 2022, tunnel boring is under way on the section from Hazawa toward Shin-Yokohama.」
The planned openings for the JR and Tokyu through lines were postponed again from the previous schedule, with the JR line listed for the second half of fiscal 2019 and the Tokyu line for the second half of fiscal 2022. The completion of civil engineering work on the Nishiya Tunnel was also reported. - FY2017-Q3RestatedAnnual report
「In addition to continuing to pursue the grade-separation project near Hoshikawa and Tennocho stations, we are also pursuing the plans for through-service operations with the JR and Tokyu lines.」
The plans for through-service operations with the JR and Tokyu lines continue to be pursued, but no new opening date or completion milestone was provided. - FY2017-Q2RestatedAnnual report
「The planned future through-service operations between the Sotetsu and JR lines and between the Sotetsu and Tokyu lines are expected to improve convenience for residents along the Sotetsu Line,」
The plans for through-service operations with the JR and Tokyu lines continue to be scheduled and pursued, but no new opening date or completion milestone was provided. - FY2017-Q1RestatedAnnual report
「The plans for through-service operations with the JR and Tokyu lines are also being pursued diligently.」
The plans for through-service operations with the JR and Tokyu lines continue to be pursued, but no new opening date or completion milestone was provided this quarter. - FY2016First statedAnnual report
「For the Sotetsu-JR Through Line project, with an opening targeted within fiscal 2018, the shield tunnel between Nishiya and Hazawa was completed in May 2014, and work inside the tunnel is now under way in preparation for track and electrical work. For the Sotetsu-Tokyu Through Line project, with an opening targeted for 2019, tunnel boring is under way on the section from Hazawa toward Shin-Yokohama.」
The opening targets were set at within fiscal 2018 for the JR through line and 2019 for the Tokyu through line, with progress on the tunnel construction described.