Expansion into new business areas through battery storage facility development
First written in FY2025. 4 of 5 entries say "Advanced", first in FY2026-H1. Latest entry: FY2027-H1.
26 other companies' latest entry also says "Advanced".
- FY2027-H1AdvancedAnnual report
「松阪市大口町 Battery Storage Facility (Matsusaka, Mie Prefecture) Other Grid-scale Battery storage 671,000 538,489 Internal funds and borrowings February 2026 October 2026」
For the battery storage facility in Matsusaka, Mie Prefecture, the amount already paid against total planned investment of ¥671,000 thousand increased from ¥337,189 thousand to ¥538,489 thousand. The planned completion date of October 2026 remains unchanged. - FY2026AdvancedAnnual report
「三重県松阪市 Battery Storage Facility (Matsusaka, Mie Prefecture) Other Grid-scale Battery storage 671,000 337,189 Internal funds and borrowings February 2026 October 2026」
For the battery storage facility development business, the company added a plan for the 三重県松阪市 Battery Storage Facility, with total planned investment of ¥671,000 thousand, ¥337,189 thousand already paid, and construction scheduled to begin in February 2026 and be completed in October of the same year, funded by internal funds and borrowings. The 丹波篠山幡路 and 霧島市国分重久 Battery Storage Facilities are also included among the major facilities. - 2026-04-10AdvancedEarnings
「The main factor was a ¥2,873 million decrease in funds due to capital expenditures, including investments in grid-scale battery storage facilities and rental properties.」
Capital expenditures, including investments in grid-scale battery storage facilities, were recorded as investing activities for the period, reflecting the execution of battery-storage facility development. - FY2026-H1AdvancedAnnual report
「丹波篠山幡路 Battery Storage Facility (Tamba-Sasayama, Hyogo Prefecture) Other Grid-scale Battery storage 585,720 8,672 594,392 July 2025 霧島市国分重久 Battery Storage Facility (Kirishima, Kagoshima Prefecture) Other Grid-scale Battery storage 780,000 432,303 Internal funds and borrowings July 2025 January 2026」
For the battery storage facility development business, the 丹波篠山幡路 Battery Storage Facility was completed in July 2025, with a total acquisition cost of ¥594,392 thousand. The company also added a plan for the 霧島市国分重久 Battery Storage Facility, with total planned investment of ¥780,000 thousand, ¥432,303 thousand already paid, and completion scheduled for January 2026. - FY2025First statedAnnual report
「We will also expand our business areas and pursue further revenue opportunities by developing battery storage facilities as a new business and strengthening collaboration with condominium management companies as part of our efforts in asset-light businesses.」
The company has for the first time explicitly identified the development of battery storage facilities as a new business. For the 丹波篠山幡路 Battery Storage Facility in Tamba-Sasayama, Hyogo Prefecture, the equipment plan calls for total planned investment of ¥600,000 thousand, of which ¥512,800 thousand had already been paid, with construction scheduled to begin in September 2024 and be completed in July 2025, funded by internal funds and borrowings.