Acquisition of Land for Office in Pyeongtaek, South Korea
First written in FY2017-Q3. 3 of 7 entries say "Advanced", first in FY2017. Latest entry: FY2020.
15 other companies' latest entry also says "Achieved".
- FY2020AchievedAnnual report
「In addition, Tokyo Electron Korea Ltd. opened an office in Pyeongtaek-si, Gyeonggi-do, South Korea, to strengthen its customer support structure.」
The plan progressed from acquiring land and constructing an office in Pyeongtaek-si to completing the opening of a customer support center. - FY2019AdvancedAnnual report
「In addition, Tokyo Electron Korea Ltd. began construction of an office in Pyeongtaek-si, Gyeonggi-do, South Korea, to strengthen its customer support structure.」
After acquiring the land for the Pyeongtaek office, the Company began construction of the office to strengthen its customer support structure. - FY2018AdvancedAnnual report
「Tokyo Electron Korea Ltd. acquired land in Pyeongtaek-si, Gyeonggi-do, South Korea, to open a new office.」
The acquisition of land for the Pyeongtaek office was completed, and a plan was listed for the office in Pyeongtaek-si, with a planned investment amount of ¥2,050 million, construction scheduled to begin in September 2018 and be completed in November 2019. - FY2018-Q3Update to the planned investment amountAnnual report
「Tokyo Electron Korea Ltd. — Pyeongtaek office — South Korea, Gyeonggi-do, Pyeongtaek-si — Semiconductor production equipment — Company-wide — Office — 2,081 — 5 — Internal funds — September 2018 — November 2019」
For the Pyeongtaek office plan, the scheduled start date of September 2018 and completion date of November 2019 were maintained, while the planned investment amount was updated to ¥2,081 million. - FY2018-Q2ReframedAnnual report
「Tokyo Electron Korea Ltd. — Pyeongtaek office — South Korea, Gyeonggi-do, Pyeongtaek-si — Semiconductor production equipment — Company-wide — Office — 1,932 — 5 — Internal funds — September 2018 — November 2019」
The plan was changed from the previous plan to acquire land for the Pyeongtaek office to a plan for the Pyeongtaek office itself, with an investment amount of ¥1,932 million, construction scheduled to begin in September 2018 and be completed in November 2019. - FY2017AdvancedAnnual report
「Tokyo Electron Korea Ltd. — Head office and other sites — South Korea, Gyeonggi-do, Hwaseong-si and other locations — Land for office use — 3,276 — 327 — Internal funds — October 2016 — October 2018」
The planned investment amount for land for the Pyeongtaek office changed from ¥3,158 million to ¥3,276 million, and ¥327 million already paid was recorded. Completion is scheduled for October 2018. - FY2017-Q3First statedAnnual report
「Tokyo Electron Korea Ltd. — Pyeongtaek office — South Korea, Gyeonggi-do, Pyeongtaek-si — Semiconductor production equipment — Company-wide — Land for office use — 3,158 — 315 — Internal funds — October 2016 — October 2018」
A new plan was listed for land for the Pyeongtaek office, with a planned investment amount of ¥3,158 million, construction scheduled to begin in October 2016 and be completed in October 2018.