Construction of a New Logistics Warehouse at Tokyo Electron Miyagi Headquarters

First written in FY2017-Q2. 1 of 4 entries say "Restated". Latest entry: FY2018.

4entries
3years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2017-Q2 – FY2017-Q3AdvancedFY2017 – FY20182016: 120162017: 220172018: 12018
Same theme, other companies
Construction of a logistics warehouse at the headquarters of 東京エレクトロン宮城A theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2018AchievedAnnual report

    「Tokyo Electron Miyagi Co., Ltd., which manufactures and develops etching equipment in a growing market, constructed a logistics building to expand production capacity by shortening lead times.」

    The logistics building at Tokyo Electron Miyagi progressed from the planning stage to construction and commencement of operations.
  2. FY2017AdvancedAnnual report

    「Tokyo Electron Miyagi Co., Ltd. Head office and other locations Miyagi Prefecture Kurokawa District Taiwa Town and other locations Logistics warehouse 3,342 1,044 Internal funds March 2017 December 2017」

    The planned total investment for the logistics warehouse changed from ¥3,220 million to ¥3,342 million, and ¥1,044 million in payments made to date was recorded. The project had entered the construction and ongoing execution stage.
  3. FY2017-Q3RestatedAnnual report

    「Tokyo Electron Miyagi Co., Ltd. Head office Logistics warehouse 3,220 — Internal funds March 2017 December 2017」

    The Company has reiterated the plan to construct a logistics warehouse at Tokyo Electron Miyagi, with the same investment amount, construction start date and scheduled completion date.
  4. FY2017-Q2First statedAnnual report

    「The major new facilities planned during the first six months of the current fiscal year are as follows: Tokyo Electron Miyagi Co., Ltd. Head office Logistics warehouse 3,220 Internal funds March 2017 December 2017」

    The Company newly disclosed a plan to construct a logistics warehouse at the head office of Tokyo Electron Miyagi. The planned investment is ¥3,220 million, with construction scheduled to begin in March 2017 and be completed in December 2017, funded internally.
Moved together

"Board Objectivity Through the Diverse Expertise of Outside Officers" moved the same way as this thread, in the same document, in 2 of its 4 moves.

222222★123456
  1. ★This thread
  2. 1Board Objectivity Through the Diverse Expertise of Outside Officers2×
  3. 2Achieving the Financial Model for the Fiscal Year Ending March 20202×
  4. 3Strengthening Product Competitiveness and Centralizing Development Functions2×
  5. 4Enhancing Customer Responsiveness and Becoming a Company That Creates Customer Needs2×
  6. 5Global Talent Utilization and Compensation Systems Based on Responsibilities and Roles2×
  7. 6Research and development into miniaturization, new structures, new materials and advanced packaging technologies2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Tokyo Electron Limited's next results are scheduled for 2026-10-30. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.