Enhancing Storage Capacity Through Expansion of Chubu Cross-Dock Center
First written in FY2020-Q2. 6 of 9 entries say "Advanced", first in FY2020-Q3. Latest entry: FY2022-Q2.
2 other companies' latest entry also says "Achieved".
- FY2022-Q2AchievedAnnual report
「To accommodate future demand growth and ensure stable product supply, the company expanded the Chubu Hub Center, completed in September 2021, with an automated sorting and shipping system that sorts products according to their delivery areas. Following the Chubu Hub Center’s start of operations, approximately 75% of nationwide shipments are sorted by the automated system, contributing to lower handling costs and shorter loading times.」
The Chubu Hub Center expansion was completed in September 2021, and an automated sorter began operating. Approximately 75% of nationwide shipments were sorted by the automated sorter, reducing handling costs and loading time. - FY2022-Q1AdvancedAnnual report
「Reporting company: Chubu Hub Center (Wanouchi, Anpachi, Gifu) | Warehouse expansion | 5,285 | 2,471 | Internally funded and borrowings | December 2019 | September 2021 | Storage capacity in the Chubu area to increase by approximately 25%」
The Company reported the plan for the Chubu Hub Center expansion, including ¥2,471 million in payments made to date, completion scheduled for September 2021, and an approximately 25% increase in storage capacity in the Chubu area. - FY2021AdvancedAnnual report
「Reporting company: Chubu Hub Center (Wanouchi, Anpachi, Gifu) | Warehouse expansion | 5,285 | 2,471 | Internally funded and borrowings | December 2019 | September 2021 | Storage capacity in the Chubu area to increase by approximately 25%」
Payments made to date for the Chubu Hub Center expansion increased from ¥751 million to ¥2,471 million, and the plan for completion in September 2021 and a approximately 25% increase in storage capacity continued. - FY2021-Q3AdvancedAnnual report
「Reporting company: Chubu Distribution Center (Wanouchi, Anpachi, Gifu) | Warehouse expansion | 5,285 | 751 | Internally funded and borrowings | December 2019 | September 2021 | Storage capacity in the Chubu area to increase by approximately 25%」
Payments made to date for the Chubu Distribution Center expansion increased from ¥304 million to ¥751 million. Completion remained scheduled for September 2021, and the plan to increase storage capacity by approximately 25% was maintained. - FY2021-Q2SoftenedAnnual report
「Chubu Distribution Center (Wanouchi, Anpachi, Gifu) | Warehouse expansion | 5,285 | 304 | Internally funded and borrowings | December 2019 | September 2021 | Storage capacity in the Chubu area to increase by approximately 25%」
Payments made to date for the Chubu Distribution Center expansion increased from ¥101 million to ¥304 million, while the scheduled completion changed from July 2021 to September 2021. The plan to increase storage capacity by approximately 25% was maintained. - FY2021-Q1AdvancedAnnual report
「Chubu Distribution Center (Wanouchi, Anpachi, Gifu) | Warehouse expansion | 5,285 | 101 | Internally funded and borrowings | December 2019 | July 2021 | Storage capacity in the Chubu area to increase by approximately 25%」
Payments made to date for the Chubu Distribution Center expansion increased from ¥81 million to ¥101 million. Completion remained scheduled for July 2021, and the plan to increase storage capacity by approximately 25% was maintained. - FY2020AdvancedAnnual report
「Chubu Cross-Dock Center (Wanouchi, Anpachi, Gifu) Warehouse expansion 5,285 81 Internally funded and borrowings December 2019 July 2021 Storage capacity in the Chubu area to increase by approximately 25%」
Payments made to date for the Chubu Cross-Dock Center expansion increased from ¥55 million to ¥81 million. Completion remained scheduled for July 2021, and the plan to increase storage capacity by approximately 25% was maintained. - FY2020-Q3AdvancedAnnual report
「Chubu Cross-Dock Center (Wanouchi, Anpachi, Gifu) | Warehouse expansion | 5,285 | 55 | Internally funded and borrowings | December 2019 | July 2021 | Storage capacity in the Chubu area to increase by approximately 25%」
The warehouse expansion at the Chubu Cross-Dock Center began, and ¥55 million in payments made to date was reported. Completion was scheduled for July 2021, with storage capacity planned to increase by approximately 25%. - FY2020-Q2First statedAnnual report
「Chubu Cross-Dock Center (Wanouchi, Anpachi, Gifu) | Warehouse expansion | 5,285 | 1 | Internally funded and borrowings | December 2019 | July 2021 | Storage capacity in the Chubu area to increase by approximately 25%」
To address growing demand, the Company decided to expand the warehouse at the Chubu Cross-Dock Center, with work scheduled to begin in December 2019 and finish in July 2021. Storage capacity in the Chubu area was planned to increase by approximately 25%.