Enhancing Storage Capacity Through Expansion of Chubu Cross-Dock Center

First written in FY2020-Q2. 6 of 9 entries say "Advanced", first in FY2020-Q3. Latest entry: FY2022-Q2.

9entries
3years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseAdvancedFY2020-Q3 – FY2021-Q1AdvancedFY2021-Q3 – FY2022-Q22019: 120192020: 420202021: 42021
Same theme, other companies
Continued investment in logistics centers and transportation equipmentA theme 32 companies write about · 0 as a headwind · 32 as a tailwind

2 other companies' latest entry also says "Achieved".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 32 companies compared. The sentences above are computed from all 32.
Full recordFilings, disclosures and news, newest first
  1. FY2022-Q2AchievedAnnual report

    「To accommodate future demand growth and ensure stable product supply, the company expanded the Chubu Hub Center, completed in September 2021, with an automated sorting and shipping system that sorts products according to their delivery areas. Following the Chubu Hub Center’s start of operations, approximately 75% of nationwide shipments are sorted by the automated system, contributing to lower handling costs and shorter loading times.」

    The Chubu Hub Center expansion was completed in September 2021, and an automated sorter began operating. Approximately 75% of nationwide shipments were sorted by the automated sorter, reducing handling costs and loading time.
  2. FY2022-Q1AdvancedAnnual report

    「Reporting company: Chubu Hub Center (Wanouchi, Anpachi, Gifu) | Warehouse expansion | 5,285 | 2,471 | Internally funded and borrowings | December 2019 | September 2021 | Storage capacity in the Chubu area to increase by approximately 25%」

    The Company reported the plan for the Chubu Hub Center expansion, including ¥2,471 million in payments made to date, completion scheduled for September 2021, and an approximately 25% increase in storage capacity in the Chubu area.
  3. FY2021AdvancedAnnual report

    「Reporting company: Chubu Hub Center (Wanouchi, Anpachi, Gifu) | Warehouse expansion | 5,285 | 2,471 | Internally funded and borrowings | December 2019 | September 2021 | Storage capacity in the Chubu area to increase by approximately 25%」

    Payments made to date for the Chubu Hub Center expansion increased from ¥751 million to ¥2,471 million, and the plan for completion in September 2021 and a approximately 25% increase in storage capacity continued.
  4. FY2021-Q3AdvancedAnnual report

    「Reporting company: Chubu Distribution Center (Wanouchi, Anpachi, Gifu) | Warehouse expansion | 5,285 | 751 | Internally funded and borrowings | December 2019 | September 2021 | Storage capacity in the Chubu area to increase by approximately 25%」

    Payments made to date for the Chubu Distribution Center expansion increased from ¥304 million to ¥751 million. Completion remained scheduled for September 2021, and the plan to increase storage capacity by approximately 25% was maintained.
  5. FY2021-Q2SoftenedAnnual report

    「Chubu Distribution Center (Wanouchi, Anpachi, Gifu) | Warehouse expansion | 5,285 | 304 | Internally funded and borrowings | December 2019 | September 2021 | Storage capacity in the Chubu area to increase by approximately 25%」

    Payments made to date for the Chubu Distribution Center expansion increased from ¥101 million to ¥304 million, while the scheduled completion changed from July 2021 to September 2021. The plan to increase storage capacity by approximately 25% was maintained.
  6. FY2021-Q1AdvancedAnnual report

    「Chubu Distribution Center (Wanouchi, Anpachi, Gifu) | Warehouse expansion | 5,285 | 101 | Internally funded and borrowings | December 2019 | July 2021 | Storage capacity in the Chubu area to increase by approximately 25%」

    Payments made to date for the Chubu Distribution Center expansion increased from ¥81 million to ¥101 million. Completion remained scheduled for July 2021, and the plan to increase storage capacity by approximately 25% was maintained.
  7. FY2020AdvancedAnnual report

    「Chubu Cross-Dock Center (Wanouchi, Anpachi, Gifu) Warehouse expansion 5,285 81 Internally funded and borrowings December 2019 July 2021 Storage capacity in the Chubu area to increase by approximately 25%」

    Payments made to date for the Chubu Cross-Dock Center expansion increased from ¥55 million to ¥81 million. Completion remained scheduled for July 2021, and the plan to increase storage capacity by approximately 25% was maintained.
  8. FY2020-Q3AdvancedAnnual report

    「Chubu Cross-Dock Center (Wanouchi, Anpachi, Gifu) | Warehouse expansion | 5,285 | 55 | Internally funded and borrowings | December 2019 | July 2021 | Storage capacity in the Chubu area to increase by approximately 25%」

    The warehouse expansion at the Chubu Cross-Dock Center began, and ¥55 million in payments made to date was reported. Completion was scheduled for July 2021, with storage capacity planned to increase by approximately 25%.
  9. FY2020-Q2First statedAnnual report

    「Chubu Cross-Dock Center (Wanouchi, Anpachi, Gifu) | Warehouse expansion | 5,285 | 1 | Internally funded and borrowings | December 2019 | July 2021 | Storage capacity in the Chubu area to increase by approximately 25%」

    To address growing demand, the Company decided to expand the warehouse at the Chubu Cross-Dock Center, with work scheduled to begin in December 2019 and finish in July 2021. Storage capacity in the Chubu area was planned to increase by approximately 25%.
Moved together

"Promoting Tray-to-Tray and Bottle-to-Tray Recycling" moved the same way as this thread, in the same document, in 7 of its 9 moves.

776666★123456
  1. ★This thread
  2. 1Promoting Tray-to-Tray and Bottle-to-Tray Recycling7×
  3. 2Accelerating the Development of High-Value-Added, Original Products7×
  4. 3Record Highs in Revenue and Profit6×
  5. 4Strengthening the Supply Chain and Optimizing Total Costs6×
  6. 5Completion of the Nationwide Logistics Network and Stable Supply6×
  7. 6Improvement Proposal for Reducing Labor Requirements and Improving Work Productivity6×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Fp's next results are scheduled for 2026-10-30. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.