Securing Personnel Through the Construction of Company Housing
First written in FY2017-Q1. 4 of 15 entries say "Advanced", first in FY2017-Q3. Latest entry: FY2022.
No other company in this theme has enough history to compare yet.
- FY2022AdvancedAnnual report
「The group will construct Pico House No. 5, a 140-unit company dormitory near the plant, with completion scheduled for September 2022, to help secure personnel.」
Near the Kansai Plant in Ono, the group is constructing the 140-unit Pico House No. 5, scheduled for completion in September 2022, and advancing its personnel recruitment initiative. - FY2022-Q2AdvancedAnnual report
「The group will construct Pico House No. 5, a 140-unit company dormitory near the plant, with completion scheduled for September 2022, to help secure personnel.」
Near the Kansai Plant in Ono, construction of the 140-unit Pico House No. 5 is under way, with completion scheduled for September 2022, giving concrete form to the personnel recruitment initiative. - FY2021RaisedAnnual report
「In addition, the group will construct Pico House No. 5, a 140-unit company dormitory with a site area of 5,936 m² near Ono City Hall, to help secure personnel.」
In addition to developing the existing company dormitories, the group added a plan to construct Pico House No. 5 in Ono, with a site area of 5,936 m² and 140 units. - FY2021-Q3AchievedAnnual report
「Pico House No. 1 (Chikusei, Ibaraki Prefecture; 150 units; completed in January 2017), Pico House No. 2 (Wanouchi, Anpachi District, Gifu Prefecture; 102 units; completed in March 2017), Pico House No. 3 (Koga, Ibaraki Prefecture; 63 units; completed in March 2020), and Pico House No. 4 (Fukuyama, Hiroshima Prefecture; 18 units; completed in October 2020)」
The planned Pico House No. 4 was completed in October 2020, completing the development of the 4 existing facilities. - FY2020AdvancedAnnual report
「In addition to Pico House No. 1 (Chikusei, Ibaraki Prefecture; 150 units; completed in January 2017) and Pico House No. 2 (Wanouchi, Anpachi District, Gifu Prefecture; 102 units; completed in March 2017), Pico House No. 3 (renovation of a company dormitory in Koga, Ibaraki Prefecture; 63 units; completed in March 2020) has been completed, and construction of Pico House No. 4 (new construction in Fukuyama, Hiroshima Prefecture; 18 units; scheduled for completion in October 2020) is under way.」
Pico House No. 3, with 63 units, was completed in March 2020, while construction of Pico House No. 4, with 18 units, is continuing with completion scheduled for October 2020. - FY2020-Q2Update to the company housing plan and completion scheduleAnnual report
「To support employees' working environment, the group plans to construct furnished studio-type company dormitories, in addition to Pico House No. 1 (Chikusei, Ibaraki Prefecture; 150 units; completed in January 2017) and Pico House No. 2 (Wanouchi, Anpachi District, Gifu Prefecture; 102 units; completed in March 2017): Pico House No. 3 (renovation of a company dormitory in Koga, Ibaraki Prefecture; 63 units; scheduled for completion in March 2020) and Pico House No. 4 (new construction in Fukuyama, Hiroshima Prefecture; 18 units; scheduled for completion in September 2020).」
The plans for the additional company housing have been updated: Pico House No. 3 will be in Koga, with 63 units and completion scheduled for March 2020, while Pico House No. 4 will be in Hiroshima, with 18 units and completion scheduled for September 2020. - FY2020-Q1Update to the company housing plan and completion scheduleAnnual report
「To support employees' working environment, the group plans to construct furnished studio-type company dormitories, in addition to Pico House No. 1 (Chikusei, Ibaraki Prefecture; 150 units; completed in January 2017) and Pico House No. 2 (Wanouchi, Anpachi District, Gifu Prefecture; 102 units; completed in March 2017): Pico House No. 3 (renovation of a company dormitory in Koga, Ibaraki Prefecture; 63 units; scheduled for completion in March 2020) and Pico House No. 4 (new construction in Fukuyama, Hiroshima Prefecture; scheduled for completion in October 2020).」
The plans for the additional company housing have been updated: Pico House No. 3 will be in Koga, with 63 units and completion scheduled for March 2020, while Pico House No. 4 will be in Fukuyama, with completion scheduled for October 2020. - FY2019RestatedAnnual report
「In addition to Pico House No. 1 (Chikusei, Ibaraki Prefecture; 150 units; completed in January 2017) and Pico House No. 2 (Wanouchi, Anpachi District, Gifu Prefecture; 102 units; completed in March 2017), furnished studio-type company dormitories, the group plans to construct Pico House No. 3 (new construction in Fukuyama, Hiroshima Prefecture; 48 units) and Pico House No. 4 (renovation of a company dormitory in Koga, Ibaraki Prefecture; 64 units), both scheduled for completion in March 2020.」
In addition to the existing 252 units, the group plans company dormitories with 48 units in Hiroshima and 64 in Koga, reconfirming the planned completion date of March 2020. - FY2019-Q3RaisedAnnual report
「In addition to Pico House No. 1 (Chikusei, Ibaraki Prefecture; 150 units; completed in January 2017) and Pico House No. 2 (Wanouchi, Anpachi District, Gifu Prefecture; 102 units; completed in March 2017), the group plans to construct Pico House No. 3 (new construction in Fukuyama, Hiroshima Prefecture; 48 units) and Pico House No. 4 (renovation of a company dormitory in Koga, Ibaraki Prefecture; 64 units), both scheduled for completion in March 2020.」
In addition to the existing 252 company housing units, the group plans to add 2 facilities, comprising 48 units in Hiroshima and 64 in Koga, for a total of 112 additional units, with completion planned for March 2020. - FY2018-Q2RestatedAnnual report
「To secure personnel from a wider area, our group constructed Pico House No. 1, a 150-unit studio-type company dormitory in Chikusei, Ibaraki Prefecture, in the Kanto area, and Pico House No. 2, a similar 102-unit facility in Wanouchi, Anpachi District, Gifu Prefecture, in the Chubu area.」
The group has reconfirmed its efforts to secure personnel from a wider area by utilizing 150 company housing units in Kanto and 102 in Chubu. - FY2018-Q1RestatedAnnual report
「In addition to the existing company housing, amid a serious labor shortage and rising labor costs following improvements in the employment environment, our group constructed Pico House No. 1, a 150-unit studio-type company dormitory in Chikusei, Ibaraki Prefecture, for the Kanto area, and Pico House No. 2, a similar 102-unit facility in Wanouchi, Anpachi District, Gifu Prefecture, for the Chubu area, in order to secure personnel from a wider area.」
The group has reconfirmed its efforts to secure personnel from a wider area through the construction of 150 company housing units in Kanto and 102 in Chubu. - FY2017AchievedAnnual report
「In the Kanto area, our group constructed 150 studio-type company housing units, Pico House No. 1, in Chikusei, Ibaraki Prefecture, completed in January 2017, to secure personnel from a wider area. In the Chubu area, it also constructed 102 units of similar housing, Pico House No. 2, in Wanouchi, Anpachi District, Gifu Prefecture, completed in March 2017.」
Both the 150 Kanto units and the 102 Chubu units of company housing have been completed. - FY2017-Q3AdvancedAnnual report
「In the Kanto area, to secure personnel from a wider area, our group constructed 150 studio-type company housing units in Chikusei, Ibaraki Prefecture, completed in January 2017. In the Chubu area, it is also constructing 102 units of similar housing in Wanouchi, Anpachi District, Gifu Prefecture, scheduled for completion in March 2017.」
The 150 company housing units in Kanto were completed in January 2017, while the 102 units in Chubu are scheduled for completion in March 2017. - FY2017-Q2Update to the company housing unit planAnnual report
「Against this backdrop, to address the labor shortage in the Kanto region and secure personnel from a wider area, our group is constructing 150 studio-type company housing units in Chikusei, Ibaraki Prefecture, scheduled for completion in December 2016. In the Chubu area, where securing personnel is difficult, it is also constructing 102 units of similar housing in Wanouchi, Anpachi District, Gifu Prefecture, scheduled for completion in March 2017.」
The plan for 150 units in Kanto remains unchanged, while the number of company housing units in the Chubu area has been updated from the previously stated 100 to 102. - FY2017-Q1First statedAnnual report
「Against this backdrop, to address the labor shortage in the Kanto region and secure personnel from a wider area, our group is constructing 150 studio-type company housing units in Chikusei, Ibaraki Prefecture, scheduled for completion in December 2016. In the Chubu area, where securing personnel is difficult, it is also constructing 100 units of similar housing in Wanouchi, Anpachi District, Gifu Prefecture, scheduled for completion in March 2017.」
To address the labor shortage, the group is constructing 150 company housing units in Kanto and 100 in Chubu to secure personnel from a wider area.