Expansion of the Lumajang Plant
First written in FY2021. 1 of 5 entries say "Softened", first in FY2022. Latest entry: FY2026-H1.
No other company in this theme has enough history to compare yet.
- FY2026-H1AchievedAnnual report
「The Indonesian subsidiary established a new plant in Jember Regency to strengthen laminated lumber production capacity and produce new materials for sale, including plywood made from falcata wood and LVL with specially processed, enhanced strength. It also worked to establish a structure for strengthening competitiveness in Japan and overseas.」
The company disclosed that the new plant had been established under the previous Jember Plant construction plan, bringing the project to the completion stage. - FY2024AdvancedAnnual report
「PT. NANKAI INDONESIA Jember Plant (Note) Republic of Indonesia, East Java Wood-related business Construction of a new plant 1,141,000 886,097 Internal funds and bank borrowings December 2020 September 2024」
For construction of the Jember Plant, payments already made reached ¥886 million, and completion was disclosed as scheduled for September 2024. - FY2023ReframedAnnual report
「PT. NANKAI INDONESIA Jember Plant (Note) Republic of Indonesia, East Java Wood-related business Construction of a new plant 1,141,000 336,000 Internal funds and bank borrowings December 2020 December 2023」
Under the previous Lumajang Plant expansion plan, the construction site changed from the Lumajang Plant to the Jember Plant to diversify volcanic-eruption risk, and the plan was restructured as a new plant construction project. - FY2022SoftenedAnnual report
「PT. NANKAI INDONESIA Lumajang Plant Wood-related business Plant expansion 600,000 125,733 Internal funds and bank borrowings December 2020 December 2024」
Payments already made for the Lumajang Plant expansion increased to ¥125.733 million, while the scheduled completion date changed from December 2022 to December 2024. - FY2021First statedAnnual report
「PT. NANKAI INDONESIA Lumajang Plant Wood-related business Plant expansion 600,000 115,218 Internal funds, bank borrowings December 2020 December 2022」
The company disclosed an expansion plan for the Lumajang Plant of PT.NANKAI INDONESIA, with a total cost of ¥600 million, ¥115 million already paid and completion scheduled for December 2022.