Subcontractor Shortages, Financial Distress and Construction Delays in the Construction Contracting Business
First written in FY2017. 5 of 8 entries say "Restated". Latest entry: 2026-07-16.
C.S. Lumber Co.,Inc moved to the "Worse" side of this theme in 2026, 2 years after the typical company in this theme (2024).
The whole theme swung hardest in 2026: 14 of 57 companies on the "Worse" side.
5 other companies' latest entry also says "Materialised".
- 2026-07-16MaterialisedRevision of earnings forecasts
「As a result, construction delays were observed at some building sites, and the situation remains unpredictable.」
Construction delays are cited as an actual impact at building sites, with schedule-delay risk becoming a tangible event. - FY2022RestatedAnnual report
「各業種とも3社以上の複数外注先と取引をしており、少なくとも年に一度は外注先の経営者との面談を実施しております。」
複数外注先、早期の工程確定、基礎工事の一部内製化、継続発注による外注先不足・工期遅延への対応を継続している。 - FY2021RestatedAnnual report
「各業種とも3社以上の複数外注先と取引をしており、少なくとも年に一度は外注先の経営者との面談を実施しております。」
外注先不足・経営不振・工期遅延リスクに対し、複数外注先との取引、早期の工程確定、内製化、経営者面談による対応を継続している。 - FY2020MitigatedAnnual report
「基礎工事は一部社内職人による内製化を実施し、また大工工事は仕事の安定化を考慮し継続的に発注を行っております。更に季節的な繁忙期をずらすなどの工夫も行っております。」
外注先不足・工期遅延リスクへの対応として、早期の工程確定、一部基礎工事の内製化、継続発注、各業種3社以上の複数外注先との取引、年1回以上の経営者面談を具体化している。 - FY2019RestatedAnnual report
「当社グループは、建築請負事業における施工面の大部分を外注に出しているため、万が一、建築請負数の増加に伴って当社グループの選定基準に合致する外注先を十分に確保できない場合や、外注先の経営不振等により工期が遅延した場合には、当社グループの経営成績及び財政状態に影響を及ぼす可能性があります。」
外注先の確保難、経営不振、工期遅延のリスクを継続記載している。 - FY2018RestatedAnnual report
「当社グループは、建築請負事業における施工面の大部分を外注に出しているため、万が一、建築請負数の増加に伴って当社グループの選定基準に合致する外注先を十分に確保できない場合や、外注先の経営不振等により工期が遅延した場合には、当社グループの経営成績及び財政状態に影響を及ぼす可能性があります。」
外注先の確保難、経営不振、工期遅延のリスクを継続記載している。 - FY2018-Q3RestatedAnnual report
「施工体制や外注先への発注価格の見直しに取り組み」
建築請負事業で施工体制と外注先への発注価格の見直しを継続しているが、当四半期のセグメント損失は35百万円だった。 - FY2017MaterialisedAnnual report
「職人不足による外注費の高騰、新築施工工事にかかる補修工事、追加工事の増加により前期を大きく下回りました。」
外注先の確保難や外注費高騰が当期の建築請負事業の損益に実際に影響したと記載。